The FAR overhaul, side by side
FAR Part 15: Contracting by Negotiation
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 81 sections, 32,499 words (Part 15 as in force, eCFR as of Oct 29, 2026). Overhaul text: 91 sections, 28,441 words (on acquisition.gov ↗, issued Sep 30, 2025). By number: 1 the same, 44 changed, 36 not in the overhaul (10 with the same heading under another number), 46 new.
15.405-4: New number
Today
No section with this number.
Overhaul text: Should-cost review.
(a) General .
(1) Should-cost reviews are a specialized form of cost analysis. Should-cost reviews differ from traditional evaluation methods because they do not assume that a contractor's historical costs reflect efficient and economical operation. Instead, these reviews evaluate the economy and efficiency of the contractor's existing work force, methods, materials, equipment, real property, operating systems, and management. These reviews are accomplished by a multi-functional team of Government contracting, contract administration, pricing, audit, and engineering representatives. The objective of should-cost reviews is to promote both short and long-range improvements in the contractor's economy and efficiency in order to reduce the cost of performance of Government contracts. In addition, by providing rationale for any recommendations and quantifying their impact on cost, the Government will be better able to develop realistic objectives for negotiation.
(2) There are two types of should-cost reviews: program should-cost review and overhead should-cost review. These should-cost reviews may be performed together or independently. The scope of a should-cost review can range from a large-scale review examining the contractor's entire operation (including plant-wide overhead and selected major subcontractors) to a small-scale tailored review examining specific portions of a contractor's operation.
(b) Program should-cost review .
(1) A program should-cost review is used to evaluate significant elements of direct costs, such as material and labor, and associated indirect costs, usually associated with the production of major systems. When a program should-cost review is conducted relative to a contractor proposal, a separate audit report on the proposal is required.
(2) A program should-cost review should be considered, particularly in the case of a major system acquisition, when—
(i) Some initial production has already taken place;
(ii) The contract will be awarded on a sole source basis;
(iii) There are future year production requirements for substantial quantities of like items;
(iv) The items being acquired have a history of increasing costs;
(v) The work is sufficiently defined to permit an effective analysis and major changes are unlikely;
(vi) Sufficient time is available to plan and adequately conduct the should-cost review; and
(vii) Personnel with the required skills are available or can be assigned for the duration of the should-cost review.
(3) Contracting officers should decide which elements of the contractor's operation have the greatest potential for cost savings and assign the available personnel resources accordingly. The expertise of on-site Government personnel should be used, when appropriate. While the particular elements to be analyzed are a function of the contract work task, elements such as manufacturing, pricing and accounting, management and organization, and subcontract and vendor management are normally reviewed in a should-cost review.
(4) In acquisitions for which a program should-cost review is conducted, a separate program should-cost review team report, prepared in accordance with agency procedures, is required. Contracting officers must consider the findings and recommendations contained in the program should-cost review team report when negotiating the contract price. After completing the negotiation, contracting officers must provide the ACO a report of any identified uneconomical or inefficient practices, together with a report of correction or disposition agreements reached with the contractor. Contracting officers must establish a follow-up plan to monitor the correction of the uneconomical or inefficient practices.
(c) Overhead should-cost review .
(1) An overhead should-cost review is used to evaluate indirect costs, such as fringe benefits, shipping and receiving, real property, and equipment, depreciation, plant maintenance and security, taxes, and general and administrative activities. It is normally used to evaluate and negotiate an FPRA with the contractor. When an overhead should-cost review is conducted, a separate audit report is required.
(2) The following factors should be considered when selecting contractor sites for overhead should-cost reviews:
(i) Dollar amount of Government business.
(ii) Level of Government participation.
(iii) Level of noncompetitive Government contracts.
(iv) Volume of proposal activity.
(v) Major system or program.
(vi) Corporate reorganizations, mergers, acquisitions, or takeovers.
(vii) Other conditions (e.g., changes in accounting systems, management, or business activity).
(3) The objective of the overhead should-cost review is to evaluate significant indirect cost elements in-depth, and identify and recommend corrective actions regarding inefficient and uneconomical practices. If it is conducted in conjunction with a program should-cost review, a separate overhead should-cost review report is not required. However, the findings and recommendations of the overhead should-cost team, or any separate overhead should-cost review report, shall be provided to the ACO. The ACO should use this information to form the basis for the Government position in negotiating an FPRA with the contractor. The ACO shall establish a follow-up plan to monitor the correction of the uneconomical or inefficient practices.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 15.000 | Scope of part. | Scope. | Changed · 35% alike | 28 → 46 |
| 15.001 | Definitions. | Definitions. | Changed · 75% alike | 136 → 149 |
| 15.002 | Types of negotiated acquisition. | Types of negotiated acquisition. | Changed · 47% alike | 94 → 121 |
| 15.100 | Scope of subpart. | Scope. | Changed · 17% alike | 27 → 32 |
| 15.101 | Best value continuum. | Early exchanges with industry. | Changed · 5% alike | 95 → 452 |
| 15.101-1 | Tradeoff process. | none | Not in the overhaul | 153 → – |
| 15.101-2 | Lowest price technically acceptable source selection process. | none | Not in the overhaul | 555 → – |
| 15.101-3 | Tiered evaluation of small business offers. | none | Not in the overhaul | 28 → – |
| 15.102 | Oral presentations. | Structuring a request for proposals. | Changed · 8% alike | 550 → 330 |
| 15.103 | none | Developing a competitive source selection approach. | New number | – → 82 |
| 15.103-1 | none | Tradeoff approach. | New number | – → 64 |
| 15.103-2 | none | Lowest price technically acceptable approach. | New number | – → 385 |
| 15.103-3 | none | Highest technically rated with a fair and reasonable price approach | New number | – → 238 |
| 15.103-4 | none | Phased acquisition. | New number | – → 101 |
| 15.104 | none | Establishing competitive evaluation factors and significant subfactors. | New number | – → 709 |
| 15.105 | none | Other considerations. | New number | – → 0 |
| 15.105-1 | none | Oral presentations. | New number | – → 76 |
| 15.105-2 | none | Negotiations disclosure. | New number | – → 50 |
| 15.105-3 | none | Limitation on tiered evaluations for multiple award contracts. | New number | – → 35 |
| 15.105-4 | none | Request for cost or pricing data. | New number | – → 261 |
| 15.105-5 | none | Make-or-buy decision. | New number | – → 515 |
| 15.105-6 | none | Should-cost review. | New number Same heading as today's 15.407-4 | – → 28 |
| 15.105-7 | none | Unit prices. | New number | – → 55 |
| 15.106 | none | Amending a request for proposal. | New number | – → 328 |
| 15.107 | none | Submission, modification, revision, and withdrawal of proposals. | New number Same heading as today's 15.208 | – → 593 |
| 15.108 | none | Receiving proposals. | New number | – → 143 |
| 15.109 | none | Uniform contract format. | New number | – → 74 |
| 15.109-1 | none | Part I - The Schedule. | New number | – → 317 |
| 15.109-2 | none | Part II - Contract Clauses. | New number Same heading as today's 15.204-3 | – → 55 |
| 15.109-3 | none | Part III - List of Documents, Exhibits, and Other Attachments. | New number Same heading as today's 15.204-4 | – → 37 |
| 15.109-4 | none | Part IV - Representations and Instructions. | New number Same heading as today's 15.204-5 | – → 155 |
| 15.110 | none | Solicitation provisions and contract clauses. | New number Same heading as today's 15.209 | – → 1609 |
| 15.200 | Scope of subpart. | Scope. | Changed · 35% alike | 36 → 15 |
| 15.201 | Exchanges with industry before receipt of proposals. | Source selection responsibilities. | Changed · 7% alike | 527 → 352 |
| 15.202 | Advisory multi-step process. | Evaluating competitive proposals. | Changed · 9% alike | 250 → 735 |
| 15.203 | Requests for proposals. | Competitive award without negotiation. | Changed · 6% alike | 566 → 64 |
| 15.204 | Contract format. | Competitive award with negotiation. | Changed · 0% alike | 93 → 0 |
| 15.204-1 | Uniform contract format. | Establishing a competitive range. | Changed · 12% alike | 108 → 139 |
| 15.204-2 | Part I—The Schedule. | Competitive negotiations. | Changed · 6% alike | 359 → 409 |
| 15.204-3 | Part II—Contract Clauses. | none | Not in the overhaul Same heading at 15.109-2 | 61 → – |
| 15.204-4 | Part III—List of Documents, Exhibits, and Other Attachments. | none | Not in the overhaul Same heading at 15.109-3 | 37 → – |
| 15.204-5 | Part IV—Representations and Instructions. | none | Not in the overhaul Same heading at 15.109-4 | 189 → – |
| 15.205 | Issuing solicitations. | Source selection decision. | Changed · 7% alike | 40 → 72 |
| 15.206 | Amending the solicitation. | Preaward notices and debriefings. | Changed · 5% alike | 305 → 69 |
| 15.206-1 | none | Preaward notices. | New number | – → 189 |
| 15.206-2 | none | Preaward debriefing. | New number | – → 411 |
| 15.207 | Handling proposals and information. | Award. | Changed · 0% alike | 195 → 0 |
| 15.207-1 | none | Award to successful offeror. | New number | – → 185 |
| 15.207-2 | none | Award notice. | New number | – → 249 |
| 15.208 | Submission, modification, revision, and withdrawal of proposals. | none | Not in the overhaul Same heading at 15.107 | 611 → – |
| 15.209 | Solicitation provisions and contract clauses. | none | Not in the overhaul Same heading at 15.110 | 509 → – |
| 15.210 | Forms. | none | Not in the overhaul | 90 → – |
| 15.300 | Scope of subpart. | Scope. | Changed · 17% alike | 17 → 64 |
| 15.301 | [Reserved] | Postaward debriefing of offerors. | Changed · 0% alike | 0 → 15 |
| 15.301-1 | none | Debriefing process. | New number | – → 597 |
| 15.301-2 | none | Opportunity for follow-up questions. | New number | – → 22 |
| 15.302 | Source selection objective. | Protests against award. | Changed · 9% alike | 15 → 169 |
| 15.303 | Responsibilities. | Discovery of mistakes. | Changed · 6% alike | 211 → 27 |
| 15.304 | Evaluation factors and significant subfactors. | Defective certified cost or pricing data after award. | Changed · 5% alike | 712 → 1622 |
| 15.305 | Proposal evaluation. | Estimating systems. | Changed · 6% alike | 703 → 109 |
| 15.306 | Exchanges with offerors after receipt of proposals. | none | Not in the overhaul | 1314 → – |
| 15.307 | Proposal revisions. | none | Not in the overhaul | 116 → – |
| 15.308 | Source selection decision. | none | Not in the overhaul | 101 → – |
| 15.400 | Scope of subpart. | Scope of subpart. | Changed · 95% alike | 29 → 28 |
| 15.401 | Definitions. | Definitions. | Changed · 98% alike | 57 → 57 |
| 15.402 | Pricing policy. | General. | Changed · 51% alike | 440 → 232 |
| 15.403 | Obtaining certified cost or pricing data. | Obtaining cost or pricing data. | Same | 0 → 0 |
| 15.403-1 | Prohibition on obtaining certified cost or pricing data (10 U.S.C. chapter 271 and 41 U.S.C. chapter 35). | Data other than certified cost or pricing data. | Changed · 12% alike | 1320 → 708 |
| 15.403-2 | Other circumstances where certified cost or pricing data are not required. | Prohibitions on obtaining certified cost or pricing data. | Changed · 4% alike | 47 → 1218 |
| 15.403-3 | Requiring data other than certified cost or pricing data. | Certified cost or pricing data. | Changed · 7% alike | 847 → 752 |
| 15.403-4 | Requiring certified cost or pricing data (10 U.S.C. chapter 271 and 41 U.S.C. chapter 35). | Certificate of current cost or pricing data. | Changed · 12% alike | 809 → 500 |
| 15.403-5 | Instructions for submission of certified cost or pricing data and data other than certified cost or pricing data. | none | Not in the overhaul | 258 → – |
| 15.404 | Proposal analysis. | Cost and/or price analysis. | Changed · 0% alike | 0 → 287 |
| 15.404-1 | Proposal analysis techniques. | Price analysis. | Changed · 28% alike | 2546 → 481 |
| 15.404-2 | Data to support proposal analysis. | Cost analysis. | Changed · 7% alike | 909 → 411 |
| 15.404-3 | Subcontract pricing considerations. | Cost realism analysis. | Changed · 9% alike | 456 → 276 |
| 15.404-4 | Profit. | Technical cost or price analysis. | Changed · 4% alike | 1730 → 201 |
| 15.404-5 | none | Unit prices. | New number | – → 164 |
| 15.404-6 | none | Unbalanced pricing. | New number | – → 213 |
| 15.404-7 | none | Review and justification of pass-through contracts. | New number | – → 180 |
| 15.404-8 | none | Subcontract pricing considerations. | New number | – → 467 |
| 15.404-9 | none | Profit. | New number | – → 1489 |
| 15.405 | Price negotiation. | Special cost or pricing areas. | Changed · 0% alike | 369 → 0 |
| 15.405-1 | none | Inaccurate, incomplete, or noncurrent cost or pricing data. | New number | – → 99 |
| 15.405-2 | none | Make-or-buy programs. | New number Same heading as today's 15.407-2 | – → 359 |
| 15.405-3 | none | Forward pricing rate agreements. | New number Same heading as today's 15.407-3 | – → 200 |
| 15.405-4 | none | Should-cost review. | New number Same heading as today's 15.407-4 | – → 804 |
| 15.406 | Documentation. | Data to support proposal analysis. | Changed · 0% alike | 0 → 777 |
| 15.406-1 | Prenegotiation objectives. | none | Not in the overhaul Same heading at 15.408-1 | 132 → – |
| 15.406-2 | Certificate of current cost or pricing data. | none | Not in the overhaul | 540 → – |
| 15.406-3 | Documenting the negotiation. | none | Not in the overhaul Same heading at 15.408-2 | 444 → – |
| 15.407 | Special cost or pricing areas. | Price negotiation. | Changed · 0% alike | 0 → 301 |
| 15.407-1 | Defective certified cost or pricing data. | none | Not in the overhaul | 1720 → – |
| 15.407-2 | Make-or-buy programs. | none | Not in the overhaul Same heading at 15.405-2 | 1060 → – |
| 15.407-3 | Forward pricing rate agreements. | none | Not in the overhaul Same heading at 15.405-3 | 249 → – |
| 15.407-4 | Should-cost review. | none | Not in the overhaul Same heading at 15.105-6 | 852 → – |
| 15.407-5 | Estimating systems. | none | Not in the overhaul | 140 → – |
| 15.408 | Solicitation provisions and contract clauses. | Documentation. | Changed · 0% alike | 4305 → 0 |
| 15.408-1 | none | Prenegotiation objectives. | New number Same heading as today's 15.406-1 | – → 89 |
| 15.408-2 | none | Documenting the negotiation. | New number Same heading as today's 15.406-3 | – → 3301 |
| 15.500 | none | Scope of subpart. | New number | – → 18 |
| 15.501 | Definition. | Definitions. | Changed · 8% alike | 13 → 145 |
| 15.502 | Applicability. | General. | Changed · 2% alike | 52 → 374 |
| 15.503 | Notifications to unsuccessful offerors. | Preparing unsolicited proposals. | Changed · 0% alike | 538 → 0 |
| 15.503-1 | none | Scope of proposals. | New number | – → 167 |
| 15.503-2 | none | Content of proposals. | New number | – → 296 |
| 15.503-3 | none | Restricting use and disclosure of data. | New number | – → 232 |
| 15.504 | Award to successful offeror. | Receipt and initial review of unsolicited proposals. | Changed · 10% alike | 225 → 79 |
| 15.504-1 | none | Initial Review. | New number | – → 151 |
| 15.504-2 | none | Handling use and disclosure of data restrictions. | New number | – → 516 |
| 15.505 | Preaward debriefing of offerors. | Evaluation of unsolicited proposals. | Changed · 7% alike | 414 → 258 |
| 15.506 | Postaward debriefing of offerors. | Criteria for acceptance and negotiation of an unsolicited proposal. | Changed · 4% alike | 458 → 57 |
| 15.507 | Protests against award. | none | Not in the overhaul | 170 → – |
| 15.508 | Discovery of mistakes. | none | Not in the overhaul | 27 → – |
| 15.509 | Forms. | none | Not in the overhaul | 76 → – |
| 15.600 | Scope of subpart. | none | Not in the overhaul | 19 → – |
| 15.601 | Definitions. | none | Not in the overhaul | 145 → – |
| 15.602 | Policy. | none | Not in the overhaul | 72 → – |
| 15.603 | General. | none | Not in the overhaul | 228 → – |
| 15.604 | Agency points of contact. | none | Not in the overhaul | 198 → – |
| 15.605 | Content of unsolicited proposals. | none | Not in the overhaul | 298 → – |
| 15.606 | Agency procedures. | none | Not in the overhaul | 69 → – |
| 15.606-1 | Receipt and initial review. | none | Not in the overhaul | 159 → – |
| 15.606-2 | Evaluation. | none | Not in the overhaul | 161 → – |
| 15.607 | Criteria for acceptance and negotiation of an unsolicited proposal. | none | Not in the overhaul | 169 → – |
| 15.608 | Prohibitions. | none | Not in the overhaul | 120 → – |
| 15.609 | Limited use of data. | none | Not in the overhaul | 798 → – |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress