The FAR overhaul, side by side

FAR Part 34: Major System Acquisition

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 20 sections, 2,006 words (Part 34 as in force, eCFR as of Oct 29, 2026). Overhaul text: 9 sections, 446 words (on acquisition.gov ↗, issued May 2, 2025). By number: 0 the same, 8 changed, 12 not in the overhaul, 1 new.

34.003: Not in the overhaul

Today: Responsibilities.

This section in plain English

(a) As required by A-109, the agency head or designee shall establish written procedures for its implementation.

(b) The agency procedures shall identify the key decision points of each major system acquisition and the agency official(s) for making those decisions.

(c) Systems acquisitions normally designated as major are those programs that, as determined by the agency head, (1) are directed at and critical to fulfilling an agency mission need, (2) entail allocating relatively large resources for the particular agency, and (3) warrant special management attention, including specific agency-head decisions. The agency procedures may establish additional criteria, as specified in A-109, for designating major programs system acquisitions.

Overhaul text

No section with this number.

Section by section

SectionTodayOverhaul textStatusWords
34.000Scope of part.noneNot in the overhaul43 → –
34.001Definition.noneNot in the overhaul52 → –
34.002Policy.noneNot in the overhaul112 → –
34.003Responsibilities.noneNot in the overhaul110 → –
34.004Acquisition strategy.noneNot in the overhaul82 → –
34.005General requirements.noneNot in the overhaul0 → –
34.005-1Competition.noneNot in the overhaul103 → –
34.005-2Mission-oriented solicitation.noneNot in the overhaul313 → –
34.005-3Concept exploration contracts.noneNot in the overhaul94 → –
34.005-4Demonstration contracts.noneNot in the overhaul59 → –
34.005-5Full-scale development contracts.noneNot in the overhaul41 → –
34.005-6Full production.noneNot in the overhaul39 → –
34.100Scope of subpart.Testing, Qualification and Use of Industrial Resources Developed Under Title III of the Defense Production Act.Changed · 0% alike66 → 0
34.101Definitions.Scope.Changed · 12% alike59 → 59
34.102Policy.Definitions.Changed · 5% alike50 → 63
34.103Testing and qualification.Policy.Changed · 6% alike180 → 31
34.104Contract clause.Testing and qualification.Changed · 9% alike25 → 148
34.105noneContract clause.New number– → 27
34.201Policy.Policy.Changed · 31% alike170 → 74
34.202Integrated Baseline Reviews.Integrated Baseline Reviews.Changed · 8% alike253 → 13
34.203Solicitation provisions and contract clause.Contract clause.Changed · 33% alike155 → 31