The FAR overhaul, side by side

FAR Part 34: Major System Acquisition

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 20 sections, 2,006 words (Part 34 as in force, eCFR as of Oct 29, 2026). Overhaul text: 9 sections, 446 words (on acquisition.gov ↗, issued May 2, 2025). By number: 0 the same, 8 changed, 12 not in the overhaul, 1 new.

34.104: Changed (9% alike)

Today: Contract clause.

This section in plain English

Insert the clause at 52.234-1, Industrial Resources Developed under Defense Production Act, Title III, in all contracts for major systems and items of supply.

Overhaul text: Testing and qualification.

On acquisition.gov ↗

(a)

(1) When notified that a Title III project contractor has requested testing and approval of a Title III industrial resource, the contracting officer will review the request according to agency procedures to determine if—

(i) The Title III industrial resource is being used or might be used in the manufacture or development of a major system or item of supply; and

(ii) The remaining quantities available for purchase justify incurring the cost of testing and qualification.

(2) The contracting officer may also consult with the Defense Production Act Office, Title III Program, located at Wright Patterson Air Force Base, Ohio 45433-7739.

(b) If both conditions at 34.104(a)(1) are met, the contracting officer must modify the contract to require the contractor to conduct testing.

(c) The Title III Program will provide the contractor enough of the Title III industrial resource to conduct the necessary tests.

Section by section

SectionTodayOverhaul textStatusWords
34.000Scope of part.noneNot in the overhaul43 → –
34.001Definition.noneNot in the overhaul52 → –
34.002Policy.noneNot in the overhaul112 → –
34.003Responsibilities.noneNot in the overhaul110 → –
34.004Acquisition strategy.noneNot in the overhaul82 → –
34.005General requirements.noneNot in the overhaul0 → –
34.005-1Competition.noneNot in the overhaul103 → –
34.005-2Mission-oriented solicitation.noneNot in the overhaul313 → –
34.005-3Concept exploration contracts.noneNot in the overhaul94 → –
34.005-4Demonstration contracts.noneNot in the overhaul59 → –
34.005-5Full-scale development contracts.noneNot in the overhaul41 → –
34.005-6Full production.noneNot in the overhaul39 → –
34.100Scope of subpart.Testing, Qualification and Use of Industrial Resources Developed Under Title III of the Defense Production Act.Changed · 0% alike66 → 0
34.101Definitions.Scope.Changed · 12% alike59 → 59
34.102Policy.Definitions.Changed · 5% alike50 → 63
34.103Testing and qualification.Policy.Changed · 6% alike180 → 31
34.104Contract clause.Testing and qualification.Changed · 9% alike25 → 148
34.105noneContract clause.New number– → 27
34.201Policy.Policy.Changed · 31% alike170 → 74
34.202Integrated Baseline Reviews.Integrated Baseline Reviews.Changed · 8% alike253 → 13
34.203Solicitation provisions and contract clause.Contract clause.Changed · 33% alike155 → 31