The FAR overhaul, side by side

FAR Part 34: Major System Acquisition

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 20 sections, 2,006 words (Part 34 as in force, eCFR as of Oct 29, 2026). Overhaul text: 9 sections, 446 words (on acquisition.gov ↗, issued May 2, 2025). By number: 0 the same, 8 changed, 12 not in the overhaul, 1 new.

34.201: Changed (31% alike)

Today: Policy.

This section in plain English

(a) An Earned Value Management System (EVMS) is required for major acquisitions for development, in accordance with OMB Circular A-11. The Government may also require an EVMS for other acquisitions, in accordance with agency procedures.

(b) If the offeror proposes to use a system that has not been determined to be in compliance with the Electronic Industries Alliance Standard 748 (EIA-748), the offeror shall submit a comprehensive plan for compliance with these EVMS standards. Offerors shall not be eliminated from consideration for contract award because they do not have an EVMS that complies with these standards.

(c) As a minimum, contracting officers shall require contractors to submit EVMS monthly reports for those contracts for which an EVMS applies.

(d) EVMS requirements will be applied to subcontractors using the same rules as applied to the prime contractor.

(e) When an offeror is required to provide an EVMS plan as part of its proposal, the contracting officer will determine the adequacy of the proposed EVMS plan prior to contract award.

Overhaul text: Policy.

On acquisition.gov ↗

(a) In accordance with OMB Circular A-11, agencies must require an Earned Value Management System (EVMS) in major acquisitions for development.

(b) For contracts with EVMS requirements, agencies must require contractor submission of monthly EVMS reports.

(c) EVMS requirements apply to subcontractors using the same rules as applied to the prime contractor.

(d) When a solicitation requires a contractor-proposed EVMS plan, agencies will determine adequacy of the plan prior to contract award.

Section by section

SectionTodayOverhaul textStatusWords
34.000Scope of part.noneNot in the overhaul43 → –
34.001Definition.noneNot in the overhaul52 → –
34.002Policy.noneNot in the overhaul112 → –
34.003Responsibilities.noneNot in the overhaul110 → –
34.004Acquisition strategy.noneNot in the overhaul82 → –
34.005General requirements.noneNot in the overhaul0 → –
34.005-1Competition.noneNot in the overhaul103 → –
34.005-2Mission-oriented solicitation.noneNot in the overhaul313 → –
34.005-3Concept exploration contracts.noneNot in the overhaul94 → –
34.005-4Demonstration contracts.noneNot in the overhaul59 → –
34.005-5Full-scale development contracts.noneNot in the overhaul41 → –
34.005-6Full production.noneNot in the overhaul39 → –
34.100Scope of subpart.Testing, Qualification and Use of Industrial Resources Developed Under Title III of the Defense Production Act.Changed · 0% alike66 → 0
34.101Definitions.Scope.Changed · 12% alike59 → 59
34.102Policy.Definitions.Changed · 5% alike50 → 63
34.103Testing and qualification.Policy.Changed · 6% alike180 → 31
34.104Contract clause.Testing and qualification.Changed · 9% alike25 → 148
34.105noneContract clause.New number– → 27
34.201Policy.Policy.Changed · 31% alike170 → 74
34.202Integrated Baseline Reviews.Integrated Baseline Reviews.Changed · 8% alike253 → 13
34.203Solicitation provisions and contract clause.Contract clause.Changed · 33% alike155 → 31