The FAR overhaul, side by side

FAR Part 34: Major System Acquisition

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 20 sections, 2,006 words (Part 34 as in force, eCFR as of Oct 29, 2026). Overhaul text: 9 sections, 446 words (on acquisition.gov ↗, issued May 2, 2025). By number: 0 the same, 8 changed, 12 not in the overhaul, 1 new.

34.005-3: Not in the overhaul

Today: Concept exploration contracts.

This section in plain English

Whenever practicable, contracts to be performed during the concept exploration phase shall be for relatively short periods, at planned dollar levels. These contracts are to refine the proposed concept and to reduce the concept's technical uncertainties. The scope of work for this phase of the program shall be consistent with the Government's planned budget for the phase. Follow-on contracts for such tasks in the exploration phase shall be awarded as long as the concept approach remains promising, the contractor's progress is acceptable, and it is economically practicable to do so.

Overhaul text

No section with this number.

Section by section

SectionTodayOverhaul textStatusWords
34.000Scope of part.noneNot in the overhaul43 → –
34.001Definition.noneNot in the overhaul52 → –
34.002Policy.noneNot in the overhaul112 → –
34.003Responsibilities.noneNot in the overhaul110 → –
34.004Acquisition strategy.noneNot in the overhaul82 → –
34.005General requirements.noneNot in the overhaul0 → –
34.005-1Competition.noneNot in the overhaul103 → –
34.005-2Mission-oriented solicitation.noneNot in the overhaul313 → –
34.005-3Concept exploration contracts.noneNot in the overhaul94 → –
34.005-4Demonstration contracts.noneNot in the overhaul59 → –
34.005-5Full-scale development contracts.noneNot in the overhaul41 → –
34.005-6Full production.noneNot in the overhaul39 → –
34.100Scope of subpart.Testing, Qualification and Use of Industrial Resources Developed Under Title III of the Defense Production Act.Changed · 0% alike66 → 0
34.101Definitions.Scope.Changed · 12% alike59 → 59
34.102Policy.Definitions.Changed · 5% alike50 → 63
34.103Testing and qualification.Policy.Changed · 6% alike180 → 31
34.104Contract clause.Testing and qualification.Changed · 9% alike25 → 148
34.105noneContract clause.New number– → 27
34.201Policy.Policy.Changed · 31% alike170 → 74
34.202Integrated Baseline Reviews.Integrated Baseline Reviews.Changed · 8% alike253 → 13
34.203Solicitation provisions and contract clause.Contract clause.Changed · 33% alike155 → 31