The FAR overhaul, side by side

FAR Part 34: Major System Acquisition

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 20 sections, 2,006 words (Part 34 as in force, eCFR as of Oct 29, 2026). Overhaul text: 9 sections, 446 words (on acquisition.gov ↗, issued May 2, 2025). By number: 0 the same, 8 changed, 12 not in the overhaul, 1 new.

34.203: Changed (33% alike)

Today: Solicitation provisions and contract clause.

This section in plain English

(a) The contracting officer shall insert a provision that is substantially the same as the provision at FAR 52.234-2, Notice of Earned Value Management System—Preaward Integrated Baseline Review , in solicitations for contracts that require the contractor to use an Earned Value Management System (EVMS) and for which the Government requires an Integrated Baseline Review (IBR) prior to award.

(b) The contracting officer shall insert a provision that is substantially the same as the provision at 52.234-3, Notice of Earned Value Management System—Postaward Integrated Baseline Review , in solicitations for contracts that require the contractor to use an Earned Value Management System (EVMS) and for which the Government requires an Integrated Baseline Review (IBR) after contract award.

(c) The contracting officer shall insert a clause that is substantially the same as the clause at FAR 52.234-4, Earned Value Management System, in solicitations and contracts that require a contractor to use an EVMS.

Overhaul text: Contract clause.

On acquisition.gov ↗

Insert a clause that is substantially the same as the clause at FAR 52.234-4, Earned Value Management System, in solicitations and contracts that require a contractor to use an EVMS.

Section by section

SectionTodayOverhaul textStatusWords
34.000Scope of part.noneNot in the overhaul43 → –
34.001Definition.noneNot in the overhaul52 → –
34.002Policy.noneNot in the overhaul112 → –
34.003Responsibilities.noneNot in the overhaul110 → –
34.004Acquisition strategy.noneNot in the overhaul82 → –
34.005General requirements.noneNot in the overhaul0 → –
34.005-1Competition.noneNot in the overhaul103 → –
34.005-2Mission-oriented solicitation.noneNot in the overhaul313 → –
34.005-3Concept exploration contracts.noneNot in the overhaul94 → –
34.005-4Demonstration contracts.noneNot in the overhaul59 → –
34.005-5Full-scale development contracts.noneNot in the overhaul41 → –
34.005-6Full production.noneNot in the overhaul39 → –
34.100Scope of subpart.Testing, Qualification and Use of Industrial Resources Developed Under Title III of the Defense Production Act.Changed · 0% alike66 → 0
34.101Definitions.Scope.Changed · 12% alike59 → 59
34.102Policy.Definitions.Changed · 5% alike50 → 63
34.103Testing and qualification.Policy.Changed · 6% alike180 → 31
34.104Contract clause.Testing and qualification.Changed · 9% alike25 → 148
34.105noneContract clause.New number– → 27
34.201Policy.Policy.Changed · 31% alike170 → 74
34.202Integrated Baseline Reviews.Integrated Baseline Reviews.Changed · 8% alike253 → 13
34.203Solicitation provisions and contract clause.Contract clause.Changed · 33% alike155 → 31