The FAR overhaul, side by side

FAR Part 33: Protests, Disputes, and Appeals

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 23 sections, 7,873 words (Part 33 as in force, eCFR as of Oct 29, 2026). Overhaul text: 32 sections, 5,246 words (on acquisition.gov ↗, issued Aug 21, 2025). By number: 0 the same, 12 changed, 11 not in the overhaul (8 with the same heading under another number), 20 new.

33.102: Changed (8% alike)

Today: General.

This section in plain English

(a) Without regard to the protest venue, contracting officers shall consider all protests and seek legal advice, whether protests are submitted before or after award and whether filed directly with the agency, the Government Accountability Office (GAO), or the U.S. Court of Federal Claims. (See 19.302 for protests of small business status, 19.305 for protests of disadvantaged business status, 19.306 for protests of HUBZone small business status, and 19.307 for protests of service-disabled veteran-owned small business status, and 19.308 for protests of the status of an economically disadvantaged women-owned small business concern or of a women-owned small business concern eligible under the Women-Owned Small Business Program.)

(b) If, in connection with a protest, the head of an agency determines that a solicitation, proposed award, or award does not comply with the requirements of law or regulation, the head of the agency may—

(1) Take any action that could have been recommended by the Comptroller General had the protest been filed with the Government Accountability Office;

(2) Pay appropriate costs as stated in 33.104(h);

(3) Require the awardee to reimburse the Government's costs, as provided in this paragraph, where a postaward protest is sustained as the result of an awardee's intentional or negligent misstatement, misrepresentation, or miscertification. In addition to any other remedy available, and pursuant to the requirements of Subpart 32.6, the Government may collect this debt by offsetting the amount against any payment due the awardee under any contract between the awardee and the Government.

(i) When a protest is sustained by GAO under circumstances that may allow the Government to seek reimbursement for protest costs, the contracting officer will determine whether the protest was sustained based on the awardee's negligent or intentional misrepresentation. If the protest was sustained on several issues, protest costs shall be apportioned according to the costs attributable to the awardee's actions.

(ii) The contracting officer shall review the amount of the debt, degree of the awardee's fault, and costs of collection, to determine whether a demand for reimbursement ought to be made. If it is in the best interests of the Government to seek reimbursement, the contracting officer shall notify the contractor in writing of the nature and amount of the debt, and the intention to collect by offset if necessary. Prior to issuing a final decision, the contracting officer shall afford the contractor an opportunity to inspect and copy agency records pertaining to the debt to the extent permitted by statute and regulation, and to request review of the matter by the head of the contracting activity.

(iii) When appropriate, the contracting officer shall also refer the matter to the agency suspending and debarring official for consideration under subpart 9.4.

(c) In accordance with 31 U.S.C. 1558, with respect to any protest filed with the GAO, if the funds available to the agency for a contract at the time a protest is filed in connection with a solicitation for, proposed award of, or award of such a contract would otherwise expire, such funds shall remain available for obligation for 100 days after the date on which the final ruling is made on the protest. A ruling is considered final on the date on which the time allowed for filing an appeal or request for reconsideration has expired, or the date on which a decision is rendered on such appeal or request, whichever is later.

(d) Protest likely after award. The contracting officer may stay performance of a contract within the time period contained in 33.104(c)(1) if the contracting officer makes a written determination that—

(1) A protest is likely to be filed; and

(2) Delay of performance is, under the circumstances, in the best interests of the United States.

(e) An interested party wishing to protest is encouraged to seek resolution within the agency (see 33.103) before filing a protest with the GAO, but may protest to the GAO in accordance with GAO regulations (4 CFR part 21).

(f) No person may file a protest at GAO for a procurement integrity violation unless that person reported to the contracting officer the information constituting evidence of the violation within 14 days after the person first discovered the possible violation (41 U.S.C. 2106).

Overhaul text: Definitions.

On acquisition.gov ↗

As used in this subpart-

(a) Day means a calendar day, unless otherwise specified. In the computation of any period-

(1) The day of the act, event, or default from which the designated period of time begins to run is not included; and

(2) The last day after the act, event, or default is included. However, if the last day is a Saturday, Sunday, or Federal holiday, or the place for filing is closed for all or part of the last day, then the deadline for filing is the next day the place is open.

Filed means the complete receipt of any document by an agency before its close of business. Documents received after close of business are considered filed as of the next day. Unless otherwise stated, the agency close of business is presumed to be 4:30 p.m., local time.

Interested Party for the purpose of filing a protest means an actual or prospective offeror whose direct economic interest would be affected by the award of a contract or by the failure to award a contract.

Protest means a written objection by an interested party to any of the following:

(1) A solicitation or other request by an agency for offers for a contract for the procurement of property or services.

(2) The cancellation of the solicitation or other request.

(3) An award or proposed award of the contract.

(4) A termination or cancellation of an award of the contract, if the written objection contains an allegation that the termination or cancellation is based in whole or in part on improprieties concerning the award of the contract.

Section by section

SectionTodayOverhaul textStatusWords
33.000Scope of part.Scope of part.Changed · 94% alike16 → 16
33.001General.noneNot in the overhaul54 → –
33.100nonePurpose of the bid protest system.New number– → 251
33.101Definitions.Applicability.Changed · 9% alike326 → 66
33.102General.Definitions.Changed · 8% alike713 → 269
33.103Protests to the agency.General.Changed · 12% alike899 → 461
33.104Protests to GAO.Protests to the agency.Changed · 0% alike2737 → 0
33.104-1noneScope.New number– → 47
33.104-2nonePreaward.New number– → 180
33.104-3nonePostaward.New number– → 101
33.104-4noneOther procedures.New number– → 620
33.105Protests at the U.S. Court of Federal Claims.Protests to GAO.Changed · 0% alike33 → 0
33.105-1noneGAO Bid Protest Regulations.New number– → 15
33.105-2nonePreaward.New number– → 200
33.105-3nonePostaward.New number– → 306
33.105-4noneOther procedures.New number– → 118
33.106Solicitation provision and contract clause.Protests at the U.S. Court of Federal Claims.Changed · 9% alike62 → 31
33.107noneSolicitation provision and contract clause.New number– → 64
33.200noneScope.New number– → 20
33.201Definitions.Definitions.Changed · 95% alike212 → 226
33.202Disputes.Applicability.Changed · 6% alike57 → 226
33.203Applicability.Relationship of the Disputes statute to Pub. L. 85-804.Changed · 14% alike217 → 93
33.204Policy.Policy.Changed · 36% alike118 → 36
33.205Relationship of the Disputes statute to Pub. L. 85-804.Postaward.Changed · 0% alike290 → 0
33.205-1noneContractor claim.New number– → 91
33.205-2noneContractor certification.New number
Same heading as today's 33.207
– → 101
33.205-3noneInterest on claims.New number
Same heading as today's 33.208
– → 170
33.205-4noneSuspected fraudulent claims.New number
Same heading as today's 33.209
– → 48
33.205-5noneContracting officer’s authority.New number
Same heading as today's 33.210
– → 94
33.205-6noneContracting officer’s decision.New number
Same heading as today's 33.211
– → 674
33.205-7noneObligation to continue performance.New number
Same heading as today's 33.213
– → 203
33.205-8noneAlternative dispute resolution (ADR).New number
Same heading as today's 33.214
– → 453
33.205-9noneContract clauses.New number
Same heading as today's 33.215
– → 66
33.206Initiation of a claim.noneNot in the overhaul141 → –
33.207Contractor certification.noneNot in the overhaul
Same heading at 33.205-2
216 → –
33.208Interest on claims.noneNot in the overhaul
Same heading at 33.205-3
202 → –
33.209Suspected fraudulent claims.noneNot in the overhaul
Same heading at 33.205-4
49 → –
33.210Contracting officer's authority.noneNot in the overhaul
Same heading at 33.205-5
103 → –
33.211Contracting officer's decision.noneNot in the overhaul
Same heading at 33.205-6
699 → –
33.212Contracting officer's duties upon appeal.noneNot in the overhaul44 → –
33.213Obligation to continue performance.noneNot in the overhaul
Same heading at 33.205-7
204 → –
33.214Alternative dispute resolution (ADR).noneNot in the overhaul
Same heading at 33.205-8
415 → –
33.215Contract clauses.noneNot in the overhaul
Same heading at 33.205-9
66 → –