The FAR overhaul, side by side
FAR Part 33: Protests, Disputes, and Appeals
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 23 sections, 7,873 words (Part 33 as in force, eCFR as of Oct 29, 2026). Overhaul text: 32 sections, 5,246 words (on acquisition.gov ↗, issued Aug 21, 2025). By number: 0 the same, 12 changed, 11 not in the overhaul (8 with the same heading under another number), 20 new.
33.205-8: New number
Today
No section with this number.
Overhaul text: Alternative dispute resolution (ADR).
(a)
(1) Agencies are encouraged to use ADR procedures as much as possible. Certain factors, however, may make the use of ADR inappropriate (see 5 U.S.C. 572(b)).
(2) Except for arbitration conducted according to the Administrative Dispute Resolution Act (ADRA), (5 U.S.C. 571, et seq.), agencies have authority that is separate from that provided by the ADRA to use ADR procedures to resolve issues in controversy. Agencies may also choose to proceed under the authority and requirements of the ADRA.
(b) The objective of using ADR procedures is to increase the opportunity to relatively quickly and cheaply resolve an issue in controversy. Essential elements of ADR include—
(1) An issue in controversy;
(2) Both parties choose to participate in the ADR process;
(3) Both parties agree on alternative procedures and terms instead of formal litigation; and
(4) Officials of both parties who have the authority to resolve the issue in controversy choose to participate in the process.
(c)
(1) If the contracting officer rejects a contractor's request for ADR proceedings, the contracting officer must give the contractor a written explanation citing one or more of the conditions in 5 U.S.C. 572(b) or such other specific reasons that ADR procedures are inappropriate to resolve the dispute.
(2) If a contractor rejects a request for ADR see 52.233-1(g).
(d) ADR procedures may be used at any time that the contracting officer has authority to resolve the issue in controversy. If a claim has been submitted, ADR procedures may apply to all or a portion of the claim. When ADR procedures are used after a contracting officer has issued their final decision, the contracting officer’s use of ADR procedures does not alter any of the time limitations or procedural requirements for filing an appeal of the contracting officer's final decision. The use of ADR procedures does not constitute a reconsideration of the final decision.
(e) When appropriate, a neutral person may be used to help resolve the issue in controversy using the procedures the parties chose.
(f) The confidentiality of ADR proceedings must be protected consistent with 5 U.S.C. 574.
(g)
(1) A solicitation must not require arbitration as a condition of award, unless arbitration is otherwise required by law.
(2) An agreement to use arbitration must be in writing and must specify a maximum award that the arbitrator may issue, as well as any other conditions limiting the range of possible outcomes.
(h) Binding arbitration, as an ADR procedure, may be agreed to only as specified in agency guidelines. Such guidelines must provide advice on the appropriate use of binding arbitration and when an agency has authority to settle an issue in controversy through binding arbitration.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 33.000 | Scope of part. | Scope of part. | Changed · 94% alike | 16 → 16 |
| 33.001 | General. | none | Not in the overhaul | 54 → – |
| 33.100 | none | Purpose of the bid protest system. | New number | – → 251 |
| 33.101 | Definitions. | Applicability. | Changed · 9% alike | 326 → 66 |
| 33.102 | General. | Definitions. | Changed · 8% alike | 713 → 269 |
| 33.103 | Protests to the agency. | General. | Changed · 12% alike | 899 → 461 |
| 33.104 | Protests to GAO. | Protests to the agency. | Changed · 0% alike | 2737 → 0 |
| 33.104-1 | none | Scope. | New number | – → 47 |
| 33.104-2 | none | Preaward. | New number | – → 180 |
| 33.104-3 | none | Postaward. | New number | – → 101 |
| 33.104-4 | none | Other procedures. | New number | – → 620 |
| 33.105 | Protests at the U.S. Court of Federal Claims. | Protests to GAO. | Changed · 0% alike | 33 → 0 |
| 33.105-1 | none | GAO Bid Protest Regulations. | New number | – → 15 |
| 33.105-2 | none | Preaward. | New number | – → 200 |
| 33.105-3 | none | Postaward. | New number | – → 306 |
| 33.105-4 | none | Other procedures. | New number | – → 118 |
| 33.106 | Solicitation provision and contract clause. | Protests at the U.S. Court of Federal Claims. | Changed · 9% alike | 62 → 31 |
| 33.107 | none | Solicitation provision and contract clause. | New number | – → 64 |
| 33.200 | none | Scope. | New number | – → 20 |
| 33.201 | Definitions. | Definitions. | Changed · 95% alike | 212 → 226 |
| 33.202 | Disputes. | Applicability. | Changed · 6% alike | 57 → 226 |
| 33.203 | Applicability. | Relationship of the Disputes statute to Pub. L. 85-804. | Changed · 14% alike | 217 → 93 |
| 33.204 | Policy. | Policy. | Changed · 36% alike | 118 → 36 |
| 33.205 | Relationship of the Disputes statute to Pub. L. 85-804. | Postaward. | Changed · 0% alike | 290 → 0 |
| 33.205-1 | none | Contractor claim. | New number | – → 91 |
| 33.205-2 | none | Contractor certification. | New number Same heading as today's 33.207 | – → 101 |
| 33.205-3 | none | Interest on claims. | New number Same heading as today's 33.208 | – → 170 |
| 33.205-4 | none | Suspected fraudulent claims. | New number Same heading as today's 33.209 | – → 48 |
| 33.205-5 | none | Contracting officer’s authority. | New number Same heading as today's 33.210 | – → 94 |
| 33.205-6 | none | Contracting officer’s decision. | New number Same heading as today's 33.211 | – → 674 |
| 33.205-7 | none | Obligation to continue performance. | New number Same heading as today's 33.213 | – → 203 |
| 33.205-8 | none | Alternative dispute resolution (ADR). | New number Same heading as today's 33.214 | – → 453 |
| 33.205-9 | none | Contract clauses. | New number Same heading as today's 33.215 | – → 66 |
| 33.206 | Initiation of a claim. | none | Not in the overhaul | 141 → – |
| 33.207 | Contractor certification. | none | Not in the overhaul Same heading at 33.205-2 | 216 → – |
| 33.208 | Interest on claims. | none | Not in the overhaul Same heading at 33.205-3 | 202 → – |
| 33.209 | Suspected fraudulent claims. | none | Not in the overhaul Same heading at 33.205-4 | 49 → – |
| 33.210 | Contracting officer's authority. | none | Not in the overhaul Same heading at 33.205-5 | 103 → – |
| 33.211 | Contracting officer's decision. | none | Not in the overhaul Same heading at 33.205-6 | 699 → – |
| 33.212 | Contracting officer's duties upon appeal. | none | Not in the overhaul | 44 → – |
| 33.213 | Obligation to continue performance. | none | Not in the overhaul Same heading at 33.205-7 | 204 → – |
| 33.214 | Alternative dispute resolution (ADR). | none | Not in the overhaul Same heading at 33.205-8 | 415 → – |
| 33.215 | Contract clauses. | none | Not in the overhaul Same heading at 33.205-9 | 66 → – |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress