The FAR overhaul, side by side

FAR Part 33: Protests, Disputes, and Appeals

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 23 sections, 7,873 words (Part 33 as in force, eCFR as of Oct 29, 2026). Overhaul text: 32 sections, 5,246 words (on acquisition.gov ↗, issued Aug 21, 2025). By number: 0 the same, 12 changed, 11 not in the overhaul (8 with the same heading under another number), 20 new.

33.105-3: New number

Today

No section with this number.

Overhaul text: Postaward.

On acquisition.gov ↗

(a) If a protest is likely after award, then the contracting officer may direct the contractor to stop performance within the time period contained in paragraph (b)(1) of this section if the contracting officer makes a written determination that—

(1) A protest is likely to be filed; and

(2) Delay of performance is, under the circumstances, in the best interests of the United States.

(b)

(1) If the agency receives notice of a protest from the GAO within 10 days after contract award or within 5 days after a debriefing date offered to the protester for any debriefing that is required by 15.505 or 15.506, whichever is later, then the contracting officer must immediately suspend performance or terminate the awarded contract, unless the head of the contracting activity authorizes contract performance.

(2) The head of the contracting activity, on a nondelegable basis, may authorize contract performance, upon a written finding that—

(i) Contract performance will be in the best interests of the United States; or

(ii) Urgent and compelling circumstances that significantly affect the interests of the United States will not permit waiting for the GAO's decision.

(c) An agency must not authorize contact performance until the agency has notified the GAO of the finding in paragraph (b)(2) of this section.

(d) When it is decided to suspend performance or terminate the awarded contract, the contracting officer should attempt to negotiate a mutual agreement on a no-cost basis.

(e) When the agency receives notice of a protest filed with the GAO after the dates contained in subparagraph (b)(1), the contracting officer does not have to suspend contract performance or terminate the awarded contract unless the contracting officer believes that an award may be invalidated and a delay in receiving the supplies or services is not prejudicial to the Government's interest.

Section by section

SectionTodayOverhaul textStatusWords
33.000Scope of part.Scope of part.Changed · 94% alike16 → 16
33.001General.noneNot in the overhaul54 → –
33.100nonePurpose of the bid protest system.New number– → 251
33.101Definitions.Applicability.Changed · 9% alike326 → 66
33.102General.Definitions.Changed · 8% alike713 → 269
33.103Protests to the agency.General.Changed · 12% alike899 → 461
33.104Protests to GAO.Protests to the agency.Changed · 0% alike2737 → 0
33.104-1noneScope.New number– → 47
33.104-2nonePreaward.New number– → 180
33.104-3nonePostaward.New number– → 101
33.104-4noneOther procedures.New number– → 620
33.105Protests at the U.S. Court of Federal Claims.Protests to GAO.Changed · 0% alike33 → 0
33.105-1noneGAO Bid Protest Regulations.New number– → 15
33.105-2nonePreaward.New number– → 200
33.105-3nonePostaward.New number– → 306
33.105-4noneOther procedures.New number– → 118
33.106Solicitation provision and contract clause.Protests at the U.S. Court of Federal Claims.Changed · 9% alike62 → 31
33.107noneSolicitation provision and contract clause.New number– → 64
33.200noneScope.New number– → 20
33.201Definitions.Definitions.Changed · 95% alike212 → 226
33.202Disputes.Applicability.Changed · 6% alike57 → 226
33.203Applicability.Relationship of the Disputes statute to Pub. L. 85-804.Changed · 14% alike217 → 93
33.204Policy.Policy.Changed · 36% alike118 → 36
33.205Relationship of the Disputes statute to Pub. L. 85-804.Postaward.Changed · 0% alike290 → 0
33.205-1noneContractor claim.New number– → 91
33.205-2noneContractor certification.New number
Same heading as today's 33.207
– → 101
33.205-3noneInterest on claims.New number
Same heading as today's 33.208
– → 170
33.205-4noneSuspected fraudulent claims.New number
Same heading as today's 33.209
– → 48
33.205-5noneContracting officer’s authority.New number
Same heading as today's 33.210
– → 94
33.205-6noneContracting officer’s decision.New number
Same heading as today's 33.211
– → 674
33.205-7noneObligation to continue performance.New number
Same heading as today's 33.213
– → 203
33.205-8noneAlternative dispute resolution (ADR).New number
Same heading as today's 33.214
– → 453
33.205-9noneContract clauses.New number
Same heading as today's 33.215
– → 66
33.206Initiation of a claim.noneNot in the overhaul141 → –
33.207Contractor certification.noneNot in the overhaul
Same heading at 33.205-2
216 → –
33.208Interest on claims.noneNot in the overhaul
Same heading at 33.205-3
202 → –
33.209Suspected fraudulent claims.noneNot in the overhaul
Same heading at 33.205-4
49 → –
33.210Contracting officer's authority.noneNot in the overhaul
Same heading at 33.205-5
103 → –
33.211Contracting officer's decision.noneNot in the overhaul
Same heading at 33.205-6
699 → –
33.212Contracting officer's duties upon appeal.noneNot in the overhaul44 → –
33.213Obligation to continue performance.noneNot in the overhaul
Same heading at 33.205-7
204 → –
33.214Alternative dispute resolution (ADR).noneNot in the overhaul
Same heading at 33.205-8
415 → –
33.215Contract clauses.noneNot in the overhaul
Same heading at 33.205-9
66 → –