The FAR overhaul, side by side
FAR Part 33: Protests, Disputes, and Appeals
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 23 sections, 7,873 words (Part 33 as in force, eCFR as of Oct 29, 2026). Overhaul text: 32 sections, 5,246 words (on acquisition.gov ↗, issued Aug 21, 2025). By number: 0 the same, 12 changed, 11 not in the overhaul (8 with the same heading under another number), 20 new.
33.205: Changed (0% alike)
Today: Relationship of the Disputes statute to Pub. L. 85-804.
(a) Requests for relief under Pub. L. 85-804 (50 U.S.C. 1431-1435) are not claims within the Disputes statute or the Disputes clause at 52.233-1, Disputes, and shall be processed under Subpart 50.1, Extraordinary Contractual Actions. However, relief formerly available only under Pub. L. 85-804; i.e., legal entitlement to rescission or reformation for mutual mistake, is now available within the authority of the contracting officer under the Disputes statute and the Disputes clause. In case of a question whether the contracting officer has authority to settle or decide specific types of claims, the contracting officer should seek legal advice.
(b) A contractor's allegation that it is entitled to rescission or reformation of its contract in order to correct or mitigate the effect of a mistake shall be treated as a claim under the Dispute statute. A contract may be reformed or rescinded by the contracting officer if the contractor would be entitled to such remedy or relief under the law of Federal contracts. Due to the complex legal issues likely to be associated with allegations of legal entitlement, contracting officers shall make written decisions, prepared with the advice and assistance of legal counsel, either granting or denying relief in whole or in part.
(c) A claim that is either denied or not approved in its entirety under paragraph (b) above may be cognizable as a request for relief under Pub. L. 85-804 as implemented by subpart 50.1. However, the claim must first be submitted to the contracting officer for consideration under the Disputes statute because the claim is not cognizable under Public Law 85-804, as implemented by subpart 50.1, unless other legal authority in the agency concerned is determined to be lacking or inadequate.
Overhaul text: Postaward.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 33.000 | Scope of part. | Scope of part. | Changed · 94% alike | 16 → 16 |
| 33.001 | General. | none | Not in the overhaul | 54 → – |
| 33.100 | none | Purpose of the bid protest system. | New number | – → 251 |
| 33.101 | Definitions. | Applicability. | Changed · 9% alike | 326 → 66 |
| 33.102 | General. | Definitions. | Changed · 8% alike | 713 → 269 |
| 33.103 | Protests to the agency. | General. | Changed · 12% alike | 899 → 461 |
| 33.104 | Protests to GAO. | Protests to the agency. | Changed · 0% alike | 2737 → 0 |
| 33.104-1 | none | Scope. | New number | – → 47 |
| 33.104-2 | none | Preaward. | New number | – → 180 |
| 33.104-3 | none | Postaward. | New number | – → 101 |
| 33.104-4 | none | Other procedures. | New number | – → 620 |
| 33.105 | Protests at the U.S. Court of Federal Claims. | Protests to GAO. | Changed · 0% alike | 33 → 0 |
| 33.105-1 | none | GAO Bid Protest Regulations. | New number | – → 15 |
| 33.105-2 | none | Preaward. | New number | – → 200 |
| 33.105-3 | none | Postaward. | New number | – → 306 |
| 33.105-4 | none | Other procedures. | New number | – → 118 |
| 33.106 | Solicitation provision and contract clause. | Protests at the U.S. Court of Federal Claims. | Changed · 9% alike | 62 → 31 |
| 33.107 | none | Solicitation provision and contract clause. | New number | – → 64 |
| 33.200 | none | Scope. | New number | – → 20 |
| 33.201 | Definitions. | Definitions. | Changed · 95% alike | 212 → 226 |
| 33.202 | Disputes. | Applicability. | Changed · 6% alike | 57 → 226 |
| 33.203 | Applicability. | Relationship of the Disputes statute to Pub. L. 85-804. | Changed · 14% alike | 217 → 93 |
| 33.204 | Policy. | Policy. | Changed · 36% alike | 118 → 36 |
| 33.205 | Relationship of the Disputes statute to Pub. L. 85-804. | Postaward. | Changed · 0% alike | 290 → 0 |
| 33.205-1 | none | Contractor claim. | New number | – → 91 |
| 33.205-2 | none | Contractor certification. | New number Same heading as today's 33.207 | – → 101 |
| 33.205-3 | none | Interest on claims. | New number Same heading as today's 33.208 | – → 170 |
| 33.205-4 | none | Suspected fraudulent claims. | New number Same heading as today's 33.209 | – → 48 |
| 33.205-5 | none | Contracting officer’s authority. | New number Same heading as today's 33.210 | – → 94 |
| 33.205-6 | none | Contracting officer’s decision. | New number Same heading as today's 33.211 | – → 674 |
| 33.205-7 | none | Obligation to continue performance. | New number Same heading as today's 33.213 | – → 203 |
| 33.205-8 | none | Alternative dispute resolution (ADR). | New number Same heading as today's 33.214 | – → 453 |
| 33.205-9 | none | Contract clauses. | New number Same heading as today's 33.215 | – → 66 |
| 33.206 | Initiation of a claim. | none | Not in the overhaul | 141 → – |
| 33.207 | Contractor certification. | none | Not in the overhaul Same heading at 33.205-2 | 216 → – |
| 33.208 | Interest on claims. | none | Not in the overhaul Same heading at 33.205-3 | 202 → – |
| 33.209 | Suspected fraudulent claims. | none | Not in the overhaul Same heading at 33.205-4 | 49 → – |
| 33.210 | Contracting officer's authority. | none | Not in the overhaul Same heading at 33.205-5 | 103 → – |
| 33.211 | Contracting officer's decision. | none | Not in the overhaul Same heading at 33.205-6 | 699 → – |
| 33.212 | Contracting officer's duties upon appeal. | none | Not in the overhaul | 44 → – |
| 33.213 | Obligation to continue performance. | none | Not in the overhaul Same heading at 33.205-7 | 204 → – |
| 33.214 | Alternative dispute resolution (ADR). | none | Not in the overhaul Same heading at 33.205-8 | 415 → – |
| 33.215 | Contract clauses. | none | Not in the overhaul Same heading at 33.205-9 | 66 → – |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.