The FAR overhaul, side by side

FAR Part 33: Protests, Disputes, and Appeals

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 23 sections, 7,873 words (Part 33 as in force, eCFR as of Oct 29, 2026). Overhaul text: 32 sections, 5,246 words (on acquisition.gov ↗, issued Aug 21, 2025). By number: 0 the same, 12 changed, 11 not in the overhaul (8 with the same heading under another number), 20 new.

33.205-6: New number

Today

No section with this number.

Overhaul text: Contracting officer’s decision.

On acquisition.gov ↗

(a) When a claim by or against a contractor cannot be satisfied or settled by mutual agreement and a decision on the claim is necessary, the contracting officer must—

(1) Review the facts relevant to the claim;

(2) Get help from legal and other advisors;

(3) Coordinate with the contract administration officer or contracting office, as appropriate; and

(4) Prepare a written decision that-

(i) Includes the contracting officer’s decision and supporting rationale for the decision reached;

(ii) Substantially conveys the following:

“This is the final decision of the Contracting Officer. You may appeal this decision to the agency board of contract appeals. If you decide to appeal, you must, within 90 days from the date you receive this decision, mail or otherwise furnish written notice to the agency board of contract appeals and provide a copy to the Contracting Officer from whose decision this appeal is taken. The notice must indicate that an appeal is intended, refer to this decision, and identify the contract by number.

With regard to appeals to the agency board of contract appeals, you may, solely at your election, proceed under the board's—

(A) (1) Small claim procedure for claims of $50,000 or less or, in the case of a small business concern (as defined in the Small Business Act and regulations under that Act), $150,000 or less; or

(B) (2) Accelerated procedure for claims of $100,000 or less.

Instead of appealing to the agency board of contract appeals, you may bring an action directly in the United States Court of Federal Claims (except as provided in 41 U.S.C. 7102(d), regarding Maritime Contracts) within 12 months of the date you receive this decision”; and

(iii) Makes a demand for payment prepared according to 32.604 and 32.605 in all cases where the decision results in a finding that the contractor is indebted to the Government.

(b) The contracting officer must furnish a copy of the decision to the contractor by certified mail, return receipt requested, or by any other method that provides evidence of receipt. This requirement applies to decisions on claims initiated by or against the contractor.

(c) The contracting officer must issue the decision within the following statutory time limitations:

(1) For claims of $100,000 or less, 60 days after receiving a written request from the contractor that a decision be given within that period, or within a reasonable time after receipt of the claim if the contractor does not make such a request.

(2) For claims over $100,000, 60 days after receiving a certified claim; provided, however, that if a decision will not be issued within 60 days, the contracting officer must notify the contractor, within that period, of the time within which a decision will be issued.

(d) The contracting officer must issue a decision within a reasonable time, taking into account-

(1) The size and complexity of the claim;

(2) The adequacy of the contractor’s supporting data; and

(3) Any other relevant factors.

(e) The contracting officer has no obligation to render a final decision on any claim exceeding $100,000 that contains a defective certification, if within 60 days after receiving the claim, the contracting officer notifies the contractor, in writing, of the reasons why any attempted certification was found to be defective.

(f) In the event of undue delay by the contracting officer in providing a decision on a claim, the contractor may request the tribunal concerned to direct the contracting officer to issue a decision in a specified time period that the tribunal decides.

(g) Any failure of the contracting officer to issue a decision within the required time periods will be deemed a decision by the contracting officer denying the claim and will authorize the contractor to file an appeal or suit on the claim.

(h) The amount determined payable under the decision, less any portion already paid, should be paid, if otherwise proper, without awaiting contractor action concerning appeal. Such payment must be without prejudice to the rights of either party.

Section by section

SectionTodayOverhaul textStatusWords
33.000Scope of part.Scope of part.Changed · 94% alike16 → 16
33.001General.noneNot in the overhaul54 → –
33.100nonePurpose of the bid protest system.New number– → 251
33.101Definitions.Applicability.Changed · 9% alike326 → 66
33.102General.Definitions.Changed · 8% alike713 → 269
33.103Protests to the agency.General.Changed · 12% alike899 → 461
33.104Protests to GAO.Protests to the agency.Changed · 0% alike2737 → 0
33.104-1noneScope.New number– → 47
33.104-2nonePreaward.New number– → 180
33.104-3nonePostaward.New number– → 101
33.104-4noneOther procedures.New number– → 620
33.105Protests at the U.S. Court of Federal Claims.Protests to GAO.Changed · 0% alike33 → 0
33.105-1noneGAO Bid Protest Regulations.New number– → 15
33.105-2nonePreaward.New number– → 200
33.105-3nonePostaward.New number– → 306
33.105-4noneOther procedures.New number– → 118
33.106Solicitation provision and contract clause.Protests at the U.S. Court of Federal Claims.Changed · 9% alike62 → 31
33.107noneSolicitation provision and contract clause.New number– → 64
33.200noneScope.New number– → 20
33.201Definitions.Definitions.Changed · 95% alike212 → 226
33.202Disputes.Applicability.Changed · 6% alike57 → 226
33.203Applicability.Relationship of the Disputes statute to Pub. L. 85-804.Changed · 14% alike217 → 93
33.204Policy.Policy.Changed · 36% alike118 → 36
33.205Relationship of the Disputes statute to Pub. L. 85-804.Postaward.Changed · 0% alike290 → 0
33.205-1noneContractor claim.New number– → 91
33.205-2noneContractor certification.New number
Same heading as today's 33.207
– → 101
33.205-3noneInterest on claims.New number
Same heading as today's 33.208
– → 170
33.205-4noneSuspected fraudulent claims.New number
Same heading as today's 33.209
– → 48
33.205-5noneContracting officer’s authority.New number
Same heading as today's 33.210
– → 94
33.205-6noneContracting officer’s decision.New number
Same heading as today's 33.211
– → 674
33.205-7noneObligation to continue performance.New number
Same heading as today's 33.213
– → 203
33.205-8noneAlternative dispute resolution (ADR).New number
Same heading as today's 33.214
– → 453
33.205-9noneContract clauses.New number
Same heading as today's 33.215
– → 66
33.206Initiation of a claim.noneNot in the overhaul141 → –
33.207Contractor certification.noneNot in the overhaul
Same heading at 33.205-2
216 → –
33.208Interest on claims.noneNot in the overhaul
Same heading at 33.205-3
202 → –
33.209Suspected fraudulent claims.noneNot in the overhaul
Same heading at 33.205-4
49 → –
33.210Contracting officer's authority.noneNot in the overhaul
Same heading at 33.205-5
103 → –
33.211Contracting officer's decision.noneNot in the overhaul
Same heading at 33.205-6
699 → –
33.212Contracting officer's duties upon appeal.noneNot in the overhaul44 → –
33.213Obligation to continue performance.noneNot in the overhaul
Same heading at 33.205-7
204 → –
33.214Alternative dispute resolution (ADR).noneNot in the overhaul
Same heading at 33.205-8
415 → –
33.215Contract clauses.noneNot in the overhaul
Same heading at 33.205-9
66 → –