The FAR overhaul, side by side
FAR Part 48: Value Engineering
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 13 sections, 4,334 words (Part 48 as in force, eCFR as of Oct 29, 2026). Overhaul text: 5 sections, 1,454 words (on acquisition.gov ↗, issued Aug 28, 2025). By number: 0 the same, 5 changed, 8 not in the overhaul, 0 new.
48.001: Changed (90% alike)
Today: Definitions.
As used in this subpart—
Acquisition savings means savings resulting from the application of a value engineering change proposal (VECP) to contracts awarded by the same contracting office of its successor for essentially the same unit. Acquisition savings include—
(1) Instant contract savings, that are the net cost reductions on the contract under which the VECP is submitted and accepted, and that are equal to the instant unit cost reduction multiplied by the number of instant contract units affected by the VECP, less the contractor's allowable development and implementation costs;
(2) Concurrent contract savings, that are net reductions in the prices of other contracts that are definitized and ongoing at the time the VECP is accepted; and
(3) Future contract savings, that are the product of the future unit cost reduction multiplied by the number of future contract units in the sharing base. On an instant contract, future contract savings include savings on increases in quantities after VECP acceptance that are due to contract modifications, exercise of options, additional orders, and funding of subsequent year requirements on a multiyear contract.
Collateral costs means agency costs of operation, maintenance logistic support, or Government-furnished property.
Collateral savings means those measurable net reductions resulting from a VECP in the agency's overall projected collateral costs, exclusive of acquisition savings, whether or not the acquisition cost changes.
Contracting office includes any contracting office that the acquisition is transferred to, such as another branch of the agency or another agency's office that is performing a joint acquisition action.
Contractor's development and implementation costs means those costs the contractor incurs on a VECP specifically in developing, testing, preparing, and submitting the VECP, as well as those costs the contractor incurs to make the contractual changes required by Government acceptance of a VECP.
Future unit cost reduction means the instant unit cost reduction adjusted as the contracting officer considers necessary for projected learning or changes in quantity during the sharing period. It is calculated at the time the VECP is accepted and applies either (1) throughout the sharing period, unless the contracting officer decides that recalculation is necessary because conditions are significantly different from those previously anticipated or (2) to the calculation of a lump-sum payment, that cannot later be revised.
Government costs means those agency costs that result directly from developing and implementing the VECP, such as any net increases in the cost of testing, operations, maintenance, and logistics support. The term does not include the normal administrative costs of processing the VECP or any increase in instant contract cost or price resulting from negative instant contract savings, except that for use in 52.248-3, see the definition at 52.248-3(b).
Instant contract means the contract under which the VECP is submitted. It does not include increases in quantities after acceptance of the VECP that are due to contract modifications, exercise of options, or additional orders. If the contract is a multiyear contract, the term does not include quantities funded after VECP acceptance. In a fixed-price contract with prospective price redetermination, the term refers to the period for which firm prices have been established.
Instant unit cost reduction means the amount of the decrease in unit cost of performance (without deducting any contractor's development or implementation costs) resulting from using the VECP on the instant contract. In service contracts, the instant unit cost reduction is normally equal to the number of hours per line-item task saved by using the VECP on the instant contract, multiplied by the appropriate contract labor rate.
Negative instant contract savings means the increase in the instant contract cost or price when the acceptance of a VECP results in an excess of the contractor's allowable development and implementation costs over the product of the instant unit cost reduction multiplied by the number of instant contract units affected.
Net acquisition savings means total acquisition savings, including instant, concurrent, and future contract savings, less Government costs.
Sharing base means the number of affected end items on contracts of the contracting office accepting the VECP.
Sharing period means the period beginning with acceptance of the first unit incorporating the VECP and ending at a calendar date or event determined by the contracting officer for each VECP.
Unit means the item or task to which the contracting officer and the contractor agree the VECP applies.
Value engineering proposal means, in connection with an A-E contract, a change proposal developed by employees of the Federal Government or contractor value engineering personnel under contract to an agency to provide value engineering services for the contract or program.
Overhaul text: Definitions.
As used in this part—
Acquisition savings means savings resulting from the application of a value engineering change proposal (VECP) to contracts awarded by the same contracting office of its successor for essentially the same unit. Acquisition savings include—
(1) Instant contract savings, that are the net cost reductions on the contract under which the VECP is submitted and accepted, and that are equal to the instant unit cost reduction multiplied by the number of instant contract units affected by the VECP, less the contractor’s allowable development and implementation costs;
(2) Concurrent contract savings, that are net reductions in the prices of other contracts that are definitized and ongoing at the time the VECP is accepted; and
(3) Future contract savings, that are the product of the future unit cost reduction multiplied by the number of future contract units in the sharing base. On an instant contract, future contract savings include savings on increases in quantities after VECP acceptance that are due to contract modifications, exercise of options, additional orders, and funding of subsequent year requirements on a multiyear contract.
Collateral costs means agency costs of operation, maintenance, logistic support, or Government-furnished property.
Collateral savings means those measurable net reductions resulting from a VECP in the agency’s overall projected collateral costs, exclusive of acquisition savings, whether or not the acquisition cost changes.
Contracting office includes any contracting office that the acquisition is transferred to, such as another branch of the agency or another agency’s office that is performing a joint acquisition action.
Contractor’s development and implementation costs means those costs the contractor incurs on a VECP specifically in developing, testing, preparing, and submitting the VECP, as well as those costs the contractor incurs to make the contractual changes required by Government acceptance of a VECP.
Future unit cost reduction means the instant unit cost reduction adjusted as the contracting officer considers necessary for projected learning or changes in quantity during the sharing period. It is calculated at the time the VECP is accepted and applies either—
(1) Throughout the sharing period, unless the contracting officer decides that recalculation is necessary because conditions are significantly different from those previously anticipated; or
(2) To the calculation of a lump-sum payment, that cannot later be revised.
Instant contract means the contract under which the VECP is submitted. It does not include increases in quantities after acceptance of the VECP that are due to contract modifications, exercise of options, or additional orders. If the contract is a multiyear contract, the term does not include quantities funded after VECP acceptance. In a fixed-price contract with prospective price redetermination, the term refers to the period for which firm prices have been established.
Instant unit cost reduction means the amount of the decrease in unit cost of performance (without deducting any contractor’s development or implementation costs) resulting from using the VECP on the instant contract. In service contracts, the instant unit cost reduction is normally equal to the number of hours per line-item task saved by using the VECP on the instant contract, multiplied by the appropriate contract labor rate.
Sharing base means the number of affected end items on contracts of the contracting office accepting the VECP.
Sharing period means the period beginning with acceptance of the first unit incorporating the VECP and ending at a calendar date or event determined by the contracting officer for each VECP.
Unit means the item or task to which the contracting officer and the contractor agree the VECP applies.
Value engineering proposal means, in connection with an A-E contract, a change proposal developed by employees of the Federal Government or contractor value engineering personnel under contract to an agency to provide value engineering services for the contract or program.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 48.000 | Scope of part. | none | Not in the overhaul | 15 → – |
| 48.001 | Definitions. | Definitions. | Changed · 90% alike | 771 → 630 |
| 48.101 | General. | General. | Changed · 18% alike | 274 → 36 |
| 48.102 | Policies. | Policies. | Changed · 36% alike | 544 → 173 |
| 48.103 | Processing value engineering change proposals. | none | Not in the overhaul | 314 → – |
| 48.104 | Sharing arrangements. | none | Not in the overhaul | 0 → – |
| 48.104-1 | Determining sharing period. | none | Not in the overhaul | 339 → – |
| 48.104-2 | Sharing acquisition savings. | none | Not in the overhaul | 744 → – |
| 48.104-3 | Sharing collateral savings. | none | Not in the overhaul | 128 → – |
| 48.104-4 | Sharing alternative—no-cost settlement method. | none | Not in the overhaul | 149 → – |
| 48.105 | Relationship to other incentives. | none | Not in the overhaul | 93 → – |
| 48.201 | Clauses for supply or service contracts. | Clauses for supply or service contracts. | Changed · 54% alike | 854 → 551 |
| 48.202 | Clause for construction contracts. | Clause for construction contracts. | Changed · 50% alike | 109 → 64 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress