Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 13 sections, 4,334 words (Part 48 as in force, eCFR as of Oct 29, 2026). Overhaul text: 5 sections, 1,454 words (on acquisition.gov ↗, issued Aug 28, 2025). By number: 0 the same, 5 changed, 8 not in the overhaul, 0 new.
48.201: Changed (54% alike)
Today: Clauses for supply or service contracts.
(a) General. The contracting officer shall insert a value engineering clause in solicitations and contracts when the contract amount is expected to exceed the simplified acquisition threshold, except as specified in subparagraphs (1) through (5) and in paragraph (f) below. A value engineering clause may be included in contracts of lesser value if the contracting officer sees a potential for significant savings. Unless the chief of the contracting office authorizes its inclusion, the contracting officer shall not include a value engineering clause in solicitations and contracts—
(1) For research and development other than full-scale development;
(2) For engineering services from not-for-profit or nonprofit organizations;
(3) For personal services (see subpart 37.1);
(4) Providing for product or component improvement, unless the value engineering incentive application is restricted to areas not covered by provisions for product or component improvement;
(5) For commercial products (see part 11) that do not involve packaging specifications or other special requirements or specifications; or
(6) When the agency head has exempted the contract (or a class of contracts) from the requirements of part 48.
(b) Value engineering incentive. To provide a value engineering incentive, the contracting officer shall insert the clause at 52.248-1, Value Engineering, in solicitations and contracts except as provided in paragraph (a) above (but see subparagraph (e)(1) below).
(c) Value engineering program requirement. (1) If a mandatory value engineering effort is appropriate (i.e., if the contracting officer considers that substantial savings to the Government may result from a sustained value engineering effort of a specified level), the contracting officer shall use the clause with its Alternate I (but see subparagraph (e)(2) below).
(2) The value engineering program requirement may be specified by the Government in the solicitation or, in the case of negotiated contracting, proposed by the contractor as part of its offer and included as a subject for negotiation. The program requirement shall be shown as a separately priced line item in the contract Schedule.
(d) Value engineering incentive and program requirement. (1) If both a value engineering incentive and a mandatory program requirement are appropriate, the contracting officer shall use the clause with its Alternate II (but see subparagraph (e)(3) below).
(2) The contract shall restrict the value engineering program requirement to well-defined areas of performance designated by line item in the contract Schedule. Alternate II applies a value engineering program to the specified areas and a value engineering incentive to the remaining areas of the contract.
(e) Collateral savings computation not cost-effective. If the head of the contracting activity determines for a contract or class of contracts that the cost of computing and tracking collateral savings will exceed the benefits to be derived, the contracting officer shall use the clause with its—
(1) Alternate III if a value engineering incentive is involved;
(2) Alternate III and Alternate I if a value engineering program requirement is involved; or
(3) Alternate III and Alternate II if both an incentive and a program requirement are involved.
(f) Architect-engineering contracts. The contracting officer shall insert the clause at 52.248-2, Value Engineering—Architect-Engineer, in solicitations and contracts whenever the Government requires and pays for a specific value engineering effort in architect-engineer contracts. The clause at 52.248-1, Value Engineering, shall not be used in solicitations and contracts for architect-engineer services.
(g) Engineering-development solicitations and contracts. For engineering-development solicitations and contracts, and solicitations and contracts containing low-rate-initial-production or early production units, the contracting officer must modify the clause at 52.248-1, Value Engineering, by—
(1) Revising paragraph (i)(3)(i) of the clause by substituting “a number equal to the quantity required to be delivered over a period of between 36 and 60 consecutive months (set at the discretion of the Contracting Officer for each VECP) that spans the highest planned production, based on planning and programming or production documentation at the time the VECP is accepted;” for “the number of future contract units scheduled for delivery during the sharing period;” and
(2) Revising the first sentence under paragraph (3) of the definition of “acquisition savings” by substituting “a number equal to the quantity to be delivered over a period of between 36 and 60 consecutive months (set at the discretion of the Contracting Officer for each VECP) that spans the highest planned production, based on planning and programming or production documentation at the time the VECP is accepted.” for “the number of future contract units in the sharing base.”
(h) Extended production period solicitations and contracts. In solicitations and contracts for items requiring an extended period for production (e.g., ship construction, major system acquisition), if agency procedures prescribe sharing of future contract savings on all units to be delivered under contracts awarded during the sharing period (see 48.104-1(c)), the contracting officer must modify the clause at 52.248-1, Value Engineering, by revising paragraph (i)(3)(i) of the clause and the first sentence under paragraph (3) of the definition of “acquisition savings” by substituting “under contracts awarded during the sharing period” for “during the sharing period.”
Overhaul text: Clauses for supply or service contracts.
(a) General. The contracting officer must add a value engineering clause to solicitations and contracts exceeding the simplified acquisition threshold, except as noted in paragraphs (a)(1) through (5) and paragraph (f). Without approval from the chief of the contracting office, a value engineering clause must not be included in solicitations and contracts for:
(1) Research and development except full-scale development;
(2) Engineering services from nonprofit organizations;
(3) Personal services (see part 37);
(4) Product or component improvement, unless the value engineering incentive applies only to areas not covered by improvement provisions;
(5) Commercial products without special packaging or other requirements; or
(6) Contracts exempted by the agency head from part 48 requirements.
(b) Value engineering incentive. To create a value engineering incentive, the contracting officer must add clause 52.248-1, Value Engineering, to solicitations and contracts with exceptions noted in paragraph (a) and considerations in paragraph (e)(1) of this section.
(c) Value engineering program requirement .
(1) For mandatory value engineering efforts (when substantial government savings may result from sustained, specified effort levels), the contracting officer must use the clause with Alternate I, noting considerations in paragraph (e)(2) of this section.
(2) The government may specify the value engineering program requirement in the solicitation. In negotiated contracts, contractors may propose it in their offers as a negotiation topic. The program requirement must appear as a separate line item in the contract Schedule.
(d) Value engineering incentive and program requirement .
(1) When both a value engineering incentive and program requirement are appropriate, the contracting officer must use the clause with Alternate II, noting considerations in paragraph (e)(3) of this section.
(2) The contract must limit the value engineering program to clearly defined performance areas listed by line item. Alternate II applies a value engineering program to those specified areas and a value engineering incentive to all other contract areas.
(e) When calculating collateral savings costs more than the benefits, the head of the contracting activity may determine the contracting officer must use the clause with:
(1) Alternate III for value engineering incentives;
(2) Alternate III and Alternate I for value engineering program requirements; or
(3) Alternate III and Alternate II for combined incentives and program requirements.
(f) Architect-engineer contracts. For contracts requiring specific value engineering effort in architect-engineer work, the contracting officer must add clause 52.248-2, Value Engineering Architect-Engineer. Clause 52.248-1, Value Engineering, must not appear in architect-engineer solicitations and contracts.
(g) For engineering-development contracts and those with early production units, the contracting officer must modify clause 52.248-1 by:
(1) Replacing the text in paragraph (i)(3)(i) of the clause with language about quantities delivered over 36-60 months during peak production; and
(2) Revising the first sentence in paragraph (3) of the definition of "acquisition savings" with similar language about quantities over 36-60 months during peak production.
(h) For extended production periods (like ship construction or major systems), when agency procedures require sharing future contract savings on all units delivered under contracts awarded during the sharing period, the contracting officer must modify clause 52.248-1 by revising its paragraph (i)(3)(i) and the first sentence under paragraph (3) of the definition of "acquisition savings" with language about contracts awarded during the sharing period.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 48.000 | Scope of part. | none | Not in the overhaul | 15 → – |
| 48.001 | Definitions. | Definitions. | Changed · 90% alike | 771 → 630 |
| 48.101 | General. | General. | Changed · 18% alike | 274 → 36 |
| 48.102 | Policies. | Policies. | Changed · 36% alike | 544 → 173 |
| 48.103 | Processing value engineering change proposals. | none | Not in the overhaul | 314 → – |
| 48.104 | Sharing arrangements. | none | Not in the overhaul | 0 → – |
| 48.104-1 | Determining sharing period. | none | Not in the overhaul | 339 → – |
| 48.104-2 | Sharing acquisition savings. | none | Not in the overhaul | 744 → – |
| 48.104-3 | Sharing collateral savings. | none | Not in the overhaul | 128 → – |
| 48.104-4 | Sharing alternative—no-cost settlement method. | none | Not in the overhaul | 149 → – |
| 48.105 | Relationship to other incentives. | none | Not in the overhaul | 93 → – |
| 48.201 | Clauses for supply or service contracts. | Clauses for supply or service contracts. | Changed · 54% alike | 854 → 551 |
| 48.202 | Clause for construction contracts. | Clause for construction contracts. | Changed · 50% alike | 109 → 64 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress