The FAR overhaul, side by side
FAR Part 31: Contract Cost Principles and Procedures
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 87 sections, 30,986 words (Part 31 as in force, eCFR as of Oct 29, 2026). Overhaul text: 89 sections, 29,337 words (on acquisition.gov ↗, issued Jul 17, 2025). By number: 15 the same, 72 changed, 0 not in the overhaul, 2 new.
31.105: Changed (74% alike)
Today: Construction and architect-engineer contracts.
(a) This category includes all contracts and contract modifications negotiated on the basis of cost with organizations other than educational institutions (see 31.104), State and local governments (see 31.107), and nonprofit organizations except those exempted under OMB Uniform Guidance at 2 CFR part 200, appendix VIII (see 31.108) for construction management or construction, alteration or repair of buildings, bridges, roads, or other kinds of real property. It also includes architect-engineer contracts related to construction projects. It does not include contracts for vessels, aircraft, or other kinds of personal property.
(b) Except as otherwise provided in (d) below, the cost principles and procedures in subpart 31.2 shall be used in the pricing of contracts and contract modifications in this category if cost analysis is performed as required by 15.404-1(c).
(c) In addition, the contracting officer shall incorporate the cost principles and procedures in subpart 31.2 (as modified by (d) below) by reference in contracts in this category as the basis for—
(1) Determining reimbursable costs under cost-reimbursement contracts, including cost-reimbursement subcontracts thereunder;
(2) Negotiating indirect cost rates;
(3) Proposing, negotiating, or determining costs under terminated contracts;
(4) Price revision of fixed-price incentive contracts; and
(5) Pricing changes and other contract modifications.
(d) Except as otherwise provided in this paragraph (d), the allowability of costs for construction and architect-engineer contracts shall be determined in accordance with subpart 31.2.
(1) Because of widely varying factors such as the nature, size, duration, and location of the construction project, advance agreements as set forth in 31.109, for such items as home office overhead, partners' compensation, employment of consultants, and equipment usage costs, are particularly important in construction and architect-engineer contracts. When appropriate they serve to express the parties' understanding and avoid possible subsequent disputes or disallowances.
(2) Construction equipment, as used in this section, means equipment (including marine equipment) in sound workable condition, either owned or controlled by the contractor or the subcontractor at any tier, or obtained from a commercial rental source, and furnished for use under Government contracts.
(i) Allowable ownership and operating costs shall be determined as follows:
(A) Actual cost data shall be used when such data can be determined for both ownership and operating costs for each piece of equipment, or groups of similar serial or series equipment, from the contractor's accounting records. When such costs cannot be so determined, the contracting agency may specify the use of a particular schedule of predetermined rates or any part thereof to determine ownership and operating costs of construction equipment (see subdivisions (d)(2)(i)(B) and (C) of this section). However, costs otherwise unallowable under this part shall not become allowable through the use of any schedule (see 31.109(c)). For example, schedules need to be adjusted for Government contract costing purposes if they are based on replacement cost, include unallowable interest costs, or use improper cost of money rates or computations. Contracting officers should review the computations and factors included within the specified schedule and ensure that unallowable or unacceptably computed factors are not allowed in cost submissions.
(B) Predetermined schedules of construction equipment use rates (e.g., the Construction Equipment Ownership and Operating Expense Schedule published by the U.S. Army Corps of Engineers, industry sponsored construction equipment cost guides, or commercially published schedules of construction equipment use cost) provide average ownership and operating rates for construction equipment. The allowance for ownership costs should include the cost of depreciation and may include facilities capital cost of money. The allowance for operating costs may include costs for such items as fuel, filters, oil, and grease; servicing, repairs, and maintenance; and tire wear and repair. Costs of labor, mobilization, demobilization, overhead, and profit are generally not reflected in schedules, and separate consideration may be necessary.
(C) When a schedule of predetermined use rates for construction equipment is used to determine direct costs, all costs of equipment that are included in the cost allowances provided by the schedule shall be identified and eliminated from the contractor's other direct and indirect costs charged to the contract. If the contractor's accounting system provides for site or home office overhead allocations, all costs which are included in the equipment allowances may need to be included in any cost input base before computing the contractor's overhead rate. In periods of suspension of work pursuant to a contract clause, the allowance for equipment ownership shall not exceed an amount for standby cost as determined by the schedule or contract provision.
(ii) Reasonable costs of renting construction equipment are allowable (but see paragraph (C) below).
(A) Costs, such as maintenance and minor or running repairs incident to operating such rented equipment, that are not included in the rental rate are allowable.
(B) Costs incident to major repair and overhaul of rental equipment are unallowable.
(C) The allowability of charges for construction equipment rented from any division, subsidiary, or organization under common control, will be determined in accordance with 31.205-36(b)(3).
(3) Costs incurred at the job site incident to performing the work, such as the cost of superintendence, timekeeping and clerical work, engineering, utility costs, supplies, material handling, restoration and cleanup, etc., are allowable as direct or indirect costs, provided the accounting practice used is in accordance with the contractor's established and consistently followed cost accounting practices for all work.
(4) Rental and any other costs, less any applicable credits incurred in acquiring the temporary use of land, structures, and facilities are allowable. Costs, less any applicable credits, incurred in constructing or fabricating structures and facilities of a temporary nature are allowable.
Overhaul text: Construction and architect-engineer contracts.
(a) This category includes all contracts and contract modifications negotiated on the basis of cost with organizations other than educational institutions (see 31.104), State and local governments (see 31.107), and nonprofit organizations except those exempted under OMB Uniform Guidance at 2 CFR part 200, appendix VIII (see 31.108) for construction management or construction, alteration or repair of buildings, bridges, roads, or other kinds of real property. It also includes architect-engineer contracts related to construction projects. It does not include contracts for vessels, aircraft, or other kinds of personal property.
(b) Definition .
Construction equipment , as used in this section, means equipment (including marine equipment) in sound workable condition, either owned or controlled by the contractor or the subcontractor at any tier, or obtained from a commercial rental source, and furnished for use under Government contracts.
(c) Except as specified in paragraph (d) of this section, the cost principles and procedures in subpart 31.2 must be used in the pricing of contracts and contract modifications in this category if cost analysis is performed as required by 15.404-1(c).
(d) The contracting officer must incorporate by reference the cost principles and procedures in subpart 31.2 (as modified by paragraph (d) of this section) in contracts in this category as the basis for—
(1) Determining reimbursable costs under cost-reimbursement contracts and subcontracts;
(2) Negotiating indirect cost rates;
(3) Proposing, negotiating, or determining costs under terminated contracts;
(4) Price revision of fixed-price incentive contracts; and
(5) Pricing changes and other contract modifications.
(e)
(1) The allowability of costs for construction and architect-engineer contracts must be determined in accordance with subpart 31.2 except as follows:
(i) When an advance agreement is used to address costs, such as home office overhead, partner’s compensation, employment of consultants, and equipment usage costs due to varying factors of construction projects (see 31.110).
(ii) Allowable ownership and operating costs of construction equipment must be determined as follows:
(A) Actual cost data must be used when such data can be determined for both ownership and operating costs for each piece of equipment, or groups of similar serial or series equipment, from the contractor's accounting records.
(B) When actual cost data cannot be determined, the contracting officer may specify the use of a particular schedule of predetermined rates or any part thereof to determine ownership and operating costs of construction equipment.
(C) Costs otherwise unallowable under this part must not become allowable through the use of an advance agreement (see 31.110(c)) (e.g., schedules need to be adjusted for Government contract costing purposes if they are based on replacement cost, include unallowable interest costs, or use improper cost of money rates or computations).
(D) Contracting officers should review the computations and factors included within the specified schedule and ensure that unallowable or unacceptably computed factors are not allowed in cost submissions.
(E) Predetermined schedules of construction equipment use rates (e.g., the Construction Equipment Ownership and Operating Expense Schedule published by the U.S. Army Corps of Engineers, industry sponsored construction equipment cost guides, or commercially published schedules of construction equipment use cost) provide average ownership and operating rates for construction equipment.
(1) The allowance for ownership costs should include the cost of depreciation and may include facilities capital cost of money.
(2) The allowance for operating costs may include costs for such items as fuel, filters, oil, and grease; servicing, repairs, and maintenance; and tire wear and repair.
(3) Costs of labor, mobilization, demobilization, overhead, and profit are generally not reflected in schedules, and separate consideration may be necessary.
(F) When a schedule of predetermined use rates for construction equipment is used to determine direct costs, all costs of equipment that are included in the cost allowances provided by the schedule must be identified and eliminated from the contractor's other direct and indirect costs charged to the contract.
(1) If the contractor's accounting system provides for site or home office overhead allocations, all costs which are included in the equipment allowances may need to be included in any cost input base before computing the contractor's overhead rate.
(2) In periods of suspension of work pursuant to a contract clause, the allowance for equipment ownership must not exceed an amount for standby cost as determined by the schedule or contract provision.
(iii) The following costs of renting construction equipment must be treated as follows:
(A) Costs, such as maintenance and minor or running repairs incident to operating such rented equipment, that are not included in the rental rate are allowable.
(B) Costs incident to major repair and overhaul of rental equipment are unallowable.
(C) The allowability of charges for construction equipment rented from any division, subsidiary, or organization under common control, will be determined in accordance with 31.205-36(b)(3) and (b)(4).
(2) Costs incurred, at the job site, in performance of the work, such as the cost of superintendence, timekeeping and clerical work, engineering, utility costs, supplies, material handling, restoration and cleanup, etc., are allowable as direct or indirect costs, provided the accounting practice used is in accordance with the contractor's established and consistently followed cost accounting practices for all work.
(3) Rental and any other costs, less any applicable credits, incurred in acquiring the temporary use of land, structures, and facilities are allowable.
(4) Costs, less any applicable credits, incurred in constructing or fabricating structures and facilities of a temporary nature are allowable.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 31.000 | Scope of part. | Scope of part. | Same | 44 → 44 |
| 31.001 | Definitions. | Applicability. | Changed · 1% alike | 2375 → 36 |
| 31.002 | Availability of accounting guide. | Definitions. | Changed · 1% alike | 38 → 1901 |
| 31.003 | none | Availability of accounting guide. | New number | – → 32 |
| 31.004 | none | Deviations. | New number | – → 58 |
| 31.100 | Scope of subpart. | Scope of subpart. | Changed · 48% alike | 32 → 52 |
| 31.101 | Objectives. | [Reserved] | Changed · 0% alike | 134 → 0 |
| 31.102 | Fixed-price contracts. | Fixed-price contracts. | Changed · 81% alike | 118 → 95 |
| 31.103 | Contracts with commercial organizations. | Contracts with commercial organizations. | Changed · 91% alike | 221 → 200 |
| 31.104 | Contracts with educational institutions. | Contracts with educational institutions. | Changed · 91% alike | 134 → 129 |
| 31.105 | Construction and architect-engineer contracts. | Construction and architect-engineer contracts. | Changed · 74% alike | 941 → 908 |
| 31.106 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 31.107 | Contracts with State, local, and federally recognized Indian tribal governments. | Contracts with State, local, and federally recognized Indian tribal governments. | Changed · 78% alike | 125 → 95 |
| 31.108 | Contracts with nonprofit organizations. | Contracts with nonprofit organizations. | Changed · 98% alike | 73 → 76 |
| 31.109 | Advance agreements. | Indirect cost rate certification and penalties on unallowable costs. | Changed · 3% alike | 678 → 41 |
| 31.110 | Indirect cost rate certification and penalties on unallowable costs. | Advance agreements. | Changed · 5% alike | 63 → 528 |
| 31.201 | General. | General. | Same | 0 → 0 |
| 31.201-1 | Composition of total cost. | Composition of total cost. | Changed · 93% alike | 111 → 108 |
| 31.201-2 | Determining allowability. | Determining allowability. | Changed · 95% alike | 290 → 292 |
| 31.201-3 | Determining reasonableness. | Determining reasonableness. | Changed · 72% alike | 201 → 186 |
| 31.201-4 | Determining allocability. | Determining allocability. | Changed · 85% alike | 92 → 83 |
| 31.201-5 | Credits. | Credits. | Changed · 55% alike | 60 → 57 |
| 31.201-6 | Accounting for unallowable costs. | Accounting for unallowable costs. | Changed · 93% alike | 765 → 745 |
| 31.201-7 | Construction and architect-engineer contracts. | Construction and architect-engineer contracts. | Changed · 80% alike | 42 → 28 |
| 31.202 | Direct costs. | Direct costs. | Changed · 97% alike | 138 → 141 |
| 31.203 | Indirect costs. | Indirect costs. | Changed · 95% alike | 611 → 608 |
| 31.204 | Application of principles and procedures. | Application of principles and procedures. | Changed · 89% alike | 320 → 288 |
| 31.205 | Selected costs. | Selected costs. | Same | 0 → 0 |
| 31.205-1 | Public relations and advertising costs. | Public relations and advertising costs. | Changed · 95% alike | 726 → 704 |
| 31.205-2 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 31.205-3 | Bad debts. | Bad debts. | Same | 32 → 32 |
| 31.205-4 | Bonding costs. | Bonding costs. | Changed · 90% alike | 105 → 105 |
| 31.205-5 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 31.205-6 | Compensation for personal services. | Compensation for personal services. | Changed · 88% alike | 5911 → 5798 |
| 31.205-7 | Contingencies. | Contingencies. | Changed · 95% alike | 243 → 241 |
| 31.205-8 | Contributions or donations. | Contributions or donations. | Changed · 86% alike | 22 → 20 |
| 31.205-9 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 31.205-10 | Cost of money. | Cost of money. | Changed · 98% alike | 180 → 182 |
| 31.205-11 | Depreciation. | Depreciation. | Changed · 91% alike | 855 → 818 |
| 31.205-12 | Economic planning costs. | Economic planning costs. | Changed · 92% alike | 81 → 84 |
| 31.205-13 | Employee morale, health, welfare, food service, and dormitory costs and credits. | Employee morale, health, welfare, food service, and dormitory costs and credits. | Changed · 96% alike | 500 → 492 |
| 31.205-14 | Entertainment costs. | Entertainment costs. | Changed · 75% alike | 75 → 77 |
| 31.205-15 | Fines, penalties, and mischarging costs. | Fines, penalties, and mischarging costs. | Same | 126 → 126 |
| 31.205-16 | Gains and losses on disposition or impairment of depreciable property or other capital assets. | Gains and losses on disposition or impairment of depreciable property or other capital assets. | Changed · 94% alike | 733 → 737 |
| 31.205-17 | Idle facilities and idle capacity costs. | Idle facilities and idle capacity costs. | Changed · 97% alike | 376 → 383 |
| 31.205-18 | Independent research and development and bid and proposal costs. | Independent research and development and bid and proposal costs. | Changed · 91% alike | 1099 → 1041 |
| 31.205-19 | Insurance and indemnification. | Insurance and indemnification. | Changed · 94% alike | 864 → 824 |
| 31.205-20 | Interest and other financial costs. | Interest and other financial costs. | Changed · 79% alike | 64 → 78 |
| 31.205-21 | Labor relations costs. | Labor relations costs. | Changed · 92% alike | 149 → 127 |
| 31.205-22 | Lobbying and political activity costs. | Lobbying and political activity costs. | Changed · 94% alike | 590 → 563 |
| 31.205-23 | Losses on other contracts. | Losses on other contracts. | Changed · 63% alike | 22 → 16 |
| 31.205-24 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 31.205-25 | Manufacturing and production engineering costs. | Manufacturing and production engineering costs. | Changed · 88% alike | 214 → 183 |
| 31.205-26 | Material costs. | Material costs. | Changed · 97% alike | 409 → 413 |
| 31.205-27 | Organization costs. | Organization costs. | Changed · 94% alike | 193 → 193 |
| 31.205-28 | Other business expenses. | Other business expenses. | Same | 66 → 66 |
| 31.205-29 | Plant protection costs. | Plant protection costs. | Changed · 82% alike | 34 → 32 |
| 31.205-30 | Patent costs. | Patent costs. | Changed · 90% alike | 125 → 116 |
| 31.205-31 | Plant reconversion costs. | Plant reconversion costs. | Changed · 89% alike | 96 → 104 |
| 31.205-32 | Precontract costs. | Precontract costs. | Changed · 97% alike | 61 → 61 |
| 31.205-33 | Professional and consultant service costs. | Professional and consultant service costs. | Changed · 93% alike | 709 → 673 |
| 31.205-34 | Recruitment costs. | Recruitment costs. | Changed · 85% alike | 117 → 110 |
| 31.205-35 | Relocation costs. | Relocation costs. | Changed · 94% alike | 1191 → 1179 |
| 31.205-36 | Rental costs. | Rental costs. | Changed · 94% alike | 295 → 303 |
| 31.205-37 | Royalties and other costs for use of patents. | Royalties and other costs for use of patents. | Changed · 93% alike | 190 → 181 |
| 31.205-38 | Selling costs. | Selling costs. | Changed · 95% alike | 347 → 349 |
| 31.205-39 | Service and warranty costs. | Service and warranty costs. | Changed · 96% alike | 76 → 78 |
| 31.205-40 | Special tooling and special test equipment costs. | Special tooling and special test equipment costs. | Changed · 52% alike | 165 → 129 |
| 31.205-41 | Taxes. | Taxes. | Changed · 87% alike | 786 → 749 |
| 31.205-42 | Termination costs. | Termination costs. | Changed · 91% alike | 943 → 917 |
| 31.205-43 | Trade, business, technical, and professional activity costs. | Trade, business, technical, and professional activity costs. | Changed · 99% alike | 143 → 143 |
| 31.205-44 | Training and education costs. | Training and education costs. | Changed · 97% alike | 207 → 206 |
| 31.205-45 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 31.205-46 | Travel costs. | Travel costs. | Changed · 84% alike | 1235 → 1112 |
| 31.205-47 | Costs related to legal and other proceedings. | Costs related to legal and other proceedings. | Changed · 91% alike | 1460 → 1394 |
| 31.205-48 | Research and development costs. | Research and development costs. | Changed · 95% alike | 63 → 66 |
| 31.205-49 | Goodwill. | Goodwill. | Changed · 94% alike | 81 → 87 |
| 31.205-50 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 31.205-51 | Costs of alcoholic beverages. | Costs of alcoholic beverages. | Same | 6 → 6 |
| 31.205-52 | Asset valuations resulting from business combinations. | Asset valuations resulting from business combinations. | Changed · 98% alike | 104 → 104 |
| 31.301 | Purpose. | Purpose. | Changed · 82% alike | 26 → 23 |
| 31.302 | General. | General. | Changed · 70% alike | 60 → 32 |
| 31.303 | Requirements. | Requirements. | Changed · 84% alike | 96 → 73 |
| 31.601 | Purpose. | Purpose. | Changed · 90% alike | 22 → 27 |
| 31.602 | General. | General. | Same | 68 → 68 |
| 31.603 | Requirements. | Requirements. | Changed · 94% alike | 780 → 758 |
| 31.701 | Purpose. | Definition. | Changed · 84% alike | 110 → 82 |
| 31.702 | General. | General. | Changed · 94% alike | 63 → 56 |
| 31.703 | Requirements. | Requirements. | Changed · 95% alike | 86 → 85 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress