FAR Part 31: Contract Cost Principles and Procedures

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 87 sections, 30,986 words (Part 31 as in force, eCFR as of Oct 29, 2026). Overhaul text: 89 sections, 29,337 words (on acquisition.gov ↗, issued Jul 17, 2025). By number: 15 the same, 72 changed, 0 not in the overhaul, 2 new.

31.205-18: Changed (91% alike)

Today: Independent research and development and bid and proposal costs.

This section in plain English

(a) Definitions. As used in this subsection—

Applied research means that effort which (1) normally follows basic research, but may not be severable from the related basic research, (2) attempts to determine and exploit the potential of scientific discoveries or improvements in technology, materials, processes, methods, devices, or techniques, and (3) attempts to advance the state of the art. Applied research does not include efforts whose principal aim is design, development, or test of specific items or services to be considered for sale; these efforts are within the definition of the term development, defined in this subsection.

Basic research, (See 2.101).

Bid and proposal (B&P) costs means the costs incurred in preparing, submitting, and supporting bids and proposals (whether or not solicited) on potential Government or non-Government contracts. The term does not include the costs of effort sponsored by a grant or cooperative agreement, or required in the performance of a contract.

Company means all divisions, subsidiaries, and affiliates of the contractor under common control.

Development means the systematic use, under whatever name, of scientific and technical knowledge in the design, development, test, or evaluation of a potential new product or service (or of an improvement in an existing product or service) for the purpose of meeting specific performance requirements or objectives. Development includes the functions of design engineering, prototyping, and engineering testing. Development excludes: (1) Subcontracted technical effort which is for the sole purpose of developing an additional source for an existing product, or (2) development effort for manufacturing or production materials, systems, processes, methods, equipment, tools, and techniques not intended for sale.

Independent research and development (IR&D) means a contractor's IR&D cost that consists of projects falling within the four following areas: (1) Basis research, (2) applied research, (3) development, and (4) systems and other concept formulation studies. The term does not include the costs of effort sponsored by a grant or required in the performance of a contract. IR&D effort shall not include technical effort expended in developing and preparing technical data specifically to support submitting a bid or proposal.

Systems and other concept formulation studies means analyses and study efforts either related to specific IR&D efforts or directed toward identifying desirable new systems, equipment or components, or modifications and improvements to existing systems, equipment, or components.

(b) Composition and allocation of costs. The requirements of 48 CFR 9904.420, Accounting for independent research and development costs and bid and proposal costs, are incorporated in their entirety and shall apply as follows—

(1) Fully-CAS-covered contracts. Contracts that are fully-CAS-covered shall be subject to all requirements of 48 CFR 9904.420.

(2) Modified CAS-covered and non-CAS-covered contracts. Contracts that are not CAS-covered or that contain terms or conditions requiring modified CAS coverage shall be subject to all requirements of 48 CFR 9904.420 except 48 CFR 9904.420-50(e)(2) and 48 CFR 9904.420-50(f)(2), which are not then applicable. However, non-CAS-covered or modified CAS-covered contracts awarded at a time the contractor has CAS-covered contracts requiring compliance with 48 CFR 9904.420, shall be subject to all the requirements of 48 CFR 9904.420. When the requirements of 48 CFR 9904.420-50(e)(2) and 48 CFR 9904.420-50(f)(2) are not applicable, the following apply:

(i) IR&D and B&P costs shall be allocated to final cost objectives on the same basis of allocation used for the G&A expense grouping of the profit center (see 31.001) in which the costs are incurred. However, when IR&D and B&P costs clearly benefit other profit centers or benefit the entire company, those costs shall be allocated through the G&A of the other profit centers or through the corporate G&A, as appropriate.

(ii) If allocations of IR&D or B&P through the G&A base do not provide equitable cost allocation, the contracting officer may approve use of a different base.

(c) Allowability. Except as provided in paragraphs (d) and (e) of this subsection, or as provided in agency regulations, costs for IR&D and B&P are allowable as indirect expenses on contracts to the extent that those costs are allocable and reasonable.

(d) Deferred IR&D costs. (1) IR&D costs that were incurred in previous accounting periods are unallowable, except when a contractor has developed a specific product at its own risk in anticipation of recovering the development costs in the sale price of the product provided that—

(i) The total amount of IR&D costs applicable to the product can be identified;

(ii) The proration of such costs to sales of the product is reasonable;

(iii) The contractor had no Government business during the time that the costs were incurred or did not allocate IR&D costs to Government contracts except to prorate the cost of developing a specific product to the sales of that product; and

(iv) No costs of current IR&D programs are allocated to Government work except to prorate the costs of developing a specific product to the sales of that product.

(2) When deferred costs are recognized, the contract (except firm-fixed-price and fixed-price with economic price adjustment) will include a specific provision setting forth the amount of deferred IR&D costs that are allocable to the contract. The negotiation memorandum will state the circumstances pertaining to the case and the reason for accepting the deferred costs.

(e) Cooperative arrangements. (1) IR&D costs may be incurred by contractors working jointly with one or more non-Federal entities pursuant to a cooperative arrangement (for example, joint ventures, limited partnerships, teaming arrangements, and collaboration and consortium arrangements). IR&D costs also may include costs contributed by contractors in performing cooperative research and development agreements, or similar arrangements, entered into under—

(i) Section 12 of the Stevenson-Wydler Technology Transfer Act of 1980 (15 U.S.C. 3710(a));

(ii) Sections 203(c) (5) and (6) of the National Aeronautics and Space Act of 1958, as amended (42 U.S.C. 2473(c) (5) and (6));

(iii) 10 U.S.C. 4021 for the Defense Advanced Research Projects Agency; or

(iv) Other equivalent authority.

(2) IR&D costs incurred by a contractor pursuant to these types of cooperative arrangements should be considered as allowable IR&D costs if the work performed would have been allowed as contractor IR&D had there been no cooperative arrangement.

(3) Costs incurred in preparing, submitting, and supporting offers on potential cooperative arrangements are allowable to the extent they are allocable, reasonable, and not otherwise unallowable.

Overhaul text: Independent research and development and bid and proposal costs.

On acquisition.gov ↗

(a) Definitions. As used in this section—

Applied research means effort that—

(1) Normally follows basic research, but may not be severable from the related basic research;

(2) Attempts to determine and exploit the potential of scientific discoveries or improvements in technology, materials, processes, methods, devices, or techniques; and

(3) Attempts to advance the state of the art. Applied research does not include efforts whose principal aim is design, development, or test of specific items or services to be considered for sale; these efforts are within the definition of the term development, defined in this section.

Bid and proposal (B&P) costs means the costs incurred in preparing, submitting, and supporting bids and proposals (whether or not solicited) on potential Government or non-Government contracts. The term does not include the costs of effort sponsored by a grant or cooperative agreement or required in the performance of a contract.

Company means all divisions, subsidiaries, and affiliates of the contractor under common control.

Development means the systematic use, under whatever name, of scientific and technical knowledge in the design, development, test, or evaluation of a potential new product or service (or of an improvement in an existing product or service) for the purpose of meeting specific performance requirements or objectives. Development includes the functions of design engineering, prototyping, and engineering testing, but excludes—

(1) Subcontracted technical effort that is for the sole purpose of developing an additional source for an existing product; and

(2) Development effort for manufacturing or production materials, systems, processes, methods, equipment, tools, and techniques not intended for sale.

Independent research and development (IR&D) means a contractor's IR&D cost that consists of projects falling within the four following areas:

(1) Basic research,

(2) Applied research,

(3) Development, and

(4) Systems and other concept formulation studies. The term does not include the costs of effort sponsored by a grant or required in the performance of a contract. IR&D effort must not include technical effort expended in developing and preparing technical data specifically to support submitting a bid or proposal.

Systems and other concept formulation studies means analyses and study efforts either related to specific IR&D efforts or directed toward identifying desirable new systems, equipment or components, or modifications and improvements to existing systems, equipment, or components.

(b) Composition and allocation of costs. The requirements of 48 CFR 9904.420 are incorporated in their entirety and must apply as follows—

(1) Fully-CAS-covered contracts. Contracts that are fully-CAS-covered must be subject to all requirements of 48 CFR 9904.420.

(2) Modified CAS-covered and non-CAS-covered contracts.

(i) Non-CAS-covered contracts or contracts that contain terms or conditions requiring modified CAS coverage must be subject to all requirements of 48 CFR 9904.420 except 48 CFR 9904.420-50(e)(2) and 48 CFR 9904.420-50(f)(2).

(ii) Non-CAS-covered contracts or modified CAS-covered contracts awarded when the contractor has CAS-covered contracts requiring compliance with 48 CFR 9904.420, must be subject to all the requirements of 48 CFR 9904.420.

(iii) When the requirements of 48 CFR 9904.420-50(e)(2) and 48 CFR 9904.420-50(f)(2) are not applicable, the following apply:

(A)

(1) IR&D and B&P costs must be allocated to final cost objectives on the same basis of allocation used for the general and administrative (G&A) expense grouping of the profit center (see 31.002) in which the costs are incurred.

(2) When IR&D and B&P costs clearly benefit other profit centers or benefit the entire company, those costs must be allocated through the G&A of the other profit centers or through the corporate G&A, as appropriate.

(B) If allocations of IR&D or B&P through the G&A base do not provide equitable cost allocation, the contracting officer may approve use of a different base.

(c) Allowability. Except as provided in paragraphs (d) and (e) of this section, costs for IR&D and B&P are allowable as indirect expenses on contracts if those costs are allocable and reasonable.

(d) Deferred IR&D costs .

(1) IR&D costs incurred in previous accounting periods are unallowable, except when a contractor has developed a specific product at its own risk in anticipation of recovering the development costs in the sale price of the product and—

(i) The total amount of IR&D costs applicable to the product can be identified;

(ii) The proration of such costs to sales of the product is reasonable;

(iii) The contractor had no Government business during the time that the costs were incurred or did not allocate IR&D costs to Government contracts except to prorate the cost of developing a specific product to the sales of that product; and

(iv) No costs of current IR&D programs are allocated to Government work except to prorate the costs of developing a specific product to the sales of that product.

(2)

(i) When deferred costs are recognized, the contract (except firm-fixed-price and fixed-price with economic price adjustment contracts) will include a specific provision setting forth the amount of deferred IR&D costs that are allocable to the contract.

(ii) The contracting officer must document the circumstances and reason for accepting the deferred costs in the negotiation memorandum.

(e) Cooperative arrangements .

(1) IR&D costs may be incurred by contractors working jointly with one or more non-Federal entities pursuant to a cooperative arrangement (e.g., joint ventures, limited partnerships, teaming arrangements, and collaboration and consortium arrangements).

(2) IR&D costs may include costs contributed by contractors in performing cooperative research and development agreements, or similar arrangements, entered into under—

(i) 15 U.S.C. 3710(a);

(ii) 51 U.S.C. 20113(e) for the National Aeronautics and Space Administration;

(iii) 10 U.S.C. 4021 for DoD; or

(iv) Other equivalent authority.

(3) IR&D costs incurred by a contractor pursuant to these types of cooperative arrangements should be considered as allowable IR&D costs if the work performed would have been allowed as contractor IR&D had there been no cooperative arrangement.

(4) Costs incurred in preparing, submitting, and supporting offers on potential cooperative arrangements are allowable if they are allocable, reasonable, and not otherwise unallowable.

Section by section

SectionTodayOverhaul textStatusWords
31.000Scope of part.Scope of part.Same44 → 44
31.001Definitions.Applicability.Changed · 1% alike2375 → 36
31.002Availability of accounting guide.Definitions.Changed · 1% alike38 → 1901
31.003noneAvailability of accounting guide.New number– → 32
31.004noneDeviations.New number– → 58
31.100Scope of subpart.Scope of subpart.Changed · 48% alike32 → 52
31.101Objectives.[Reserved]Changed · 0% alike134 → 0
31.102Fixed-price contracts.Fixed-price contracts.Changed · 81% alike118 → 95
31.103Contracts with commercial organizations.Contracts with commercial organizations.Changed · 91% alike221 → 200
31.104Contracts with educational institutions.Contracts with educational institutions.Changed · 91% alike134 → 129
31.105Construction and architect-engineer contracts.Construction and architect-engineer contracts.Changed · 74% alike941 → 908
31.106[Reserved][Reserved]Same0 → 0
31.107Contracts with State, local, and federally recognized Indian tribal governments.Contracts with State, local, and federally recognized Indian tribal governments.Changed · 78% alike125 → 95
31.108Contracts with nonprofit organizations.Contracts with nonprofit organizations.Changed · 98% alike73 → 76
31.109Advance agreements.Indirect cost rate certification and penalties on unallowable costs.Changed · 3% alike678 → 41
31.110Indirect cost rate certification and penalties on unallowable costs.Advance agreements.Changed · 5% alike63 → 528
31.201General.General.Same0 → 0
31.201-1Composition of total cost.Composition of total cost.Changed · 93% alike111 → 108
31.201-2Determining allowability.Determining allowability.Changed · 95% alike290 → 292
31.201-3Determining reasonableness.Determining reasonableness.Changed · 72% alike201 → 186
31.201-4Determining allocability.Determining allocability.Changed · 85% alike92 → 83
31.201-5Credits.Credits.Changed · 55% alike60 → 57
31.201-6Accounting for unallowable costs.Accounting for unallowable costs.Changed · 93% alike765 → 745
31.201-7Construction and architect-engineer contracts.Construction and architect-engineer contracts.Changed · 80% alike42 → 28
31.202Direct costs.Direct costs.Changed · 97% alike138 → 141
31.203Indirect costs.Indirect costs.Changed · 95% alike611 → 608
31.204Application of principles and procedures.Application of principles and procedures.Changed · 89% alike320 → 288
31.205Selected costs.Selected costs.Same0 → 0
31.205-1Public relations and advertising costs.Public relations and advertising costs.Changed · 95% alike726 → 704
31.205-2[Reserved][Reserved]Same0 → 0
31.205-3Bad debts.Bad debts.Same32 → 32
31.205-4Bonding costs.Bonding costs.Changed · 90% alike105 → 105
31.205-5[Reserved][Reserved]Same0 → 0
31.205-6Compensation for personal services.Compensation for personal services.Changed · 88% alike5911 → 5798
31.205-7Contingencies.Contingencies.Changed · 95% alike243 → 241
31.205-8Contributions or donations.Contributions or donations.Changed · 86% alike22 → 20
31.205-9[Reserved][Reserved]Same0 → 0
31.205-10Cost of money.Cost of money.Changed · 98% alike180 → 182
31.205-11Depreciation.Depreciation.Changed · 91% alike855 → 818
31.205-12Economic planning costs.Economic planning costs.Changed · 92% alike81 → 84
31.205-13Employee morale, health, welfare, food service, and dormitory costs and credits.Employee morale, health, welfare, food service, and dormitory costs and credits.Changed · 96% alike500 → 492
31.205-14Entertainment costs.Entertainment costs.Changed · 75% alike75 → 77
31.205-15Fines, penalties, and mischarging costs.Fines, penalties, and mischarging costs.Same126 → 126
31.205-16Gains and losses on disposition or impairment of depreciable property or other capital assets.Gains and losses on disposition or impairment of depreciable property or other capital assets.Changed · 94% alike733 → 737
31.205-17Idle facilities and idle capacity costs.Idle facilities and idle capacity costs.Changed · 97% alike376 → 383
31.205-18Independent research and development and bid and proposal costs.Independent research and development and bid and proposal costs.Changed · 91% alike1099 → 1041
31.205-19Insurance and indemnification.Insurance and indemnification.Changed · 94% alike864 → 824
31.205-20Interest and other financial costs.Interest and other financial costs.Changed · 79% alike64 → 78
31.205-21Labor relations costs.Labor relations costs.Changed · 92% alike149 → 127
31.205-22Lobbying and political activity costs.Lobbying and political activity costs.Changed · 94% alike590 → 563
31.205-23Losses on other contracts.Losses on other contracts.Changed · 63% alike22 → 16
31.205-24[Reserved][Reserved]Same0 → 0
31.205-25Manufacturing and production engineering costs.Manufacturing and production engineering costs.Changed · 88% alike214 → 183
31.205-26Material costs.Material costs.Changed · 97% alike409 → 413
31.205-27Organization costs.Organization costs.Changed · 94% alike193 → 193
31.205-28Other business expenses.Other business expenses.Same66 → 66
31.205-29Plant protection costs.Plant protection costs.Changed · 82% alike34 → 32
31.205-30Patent costs.Patent costs.Changed · 90% alike125 → 116
31.205-31Plant reconversion costs.Plant reconversion costs.Changed · 89% alike96 → 104
31.205-32Precontract costs.Precontract costs.Changed · 97% alike61 → 61
31.205-33Professional and consultant service costs.Professional and consultant service costs.Changed · 93% alike709 → 673
31.205-34Recruitment costs.Recruitment costs.Changed · 85% alike117 → 110
31.205-35Relocation costs.Relocation costs.Changed · 94% alike1191 → 1179
31.205-36Rental costs.Rental costs.Changed · 94% alike295 → 303
31.205-37Royalties and other costs for use of patents.Royalties and other costs for use of patents.Changed · 93% alike190 → 181
31.205-38Selling costs.Selling costs.Changed · 95% alike347 → 349
31.205-39Service and warranty costs.Service and warranty costs.Changed · 96% alike76 → 78
31.205-40Special tooling and special test equipment costs.Special tooling and special test equipment costs.Changed · 52% alike165 → 129
31.205-41Taxes.Taxes.Changed · 87% alike786 → 749
31.205-42Termination costs.Termination costs.Changed · 91% alike943 → 917
31.205-43Trade, business, technical, and professional activity costs.Trade, business, technical, and professional activity costs.Changed · 99% alike143 → 143
31.205-44Training and education costs.Training and education costs.Changed · 97% alike207 → 206
31.205-45[Reserved][Reserved]Same0 → 0
31.205-46Travel costs.Travel costs.Changed · 84% alike1235 → 1112
31.205-47Costs related to legal and other proceedings.Costs related to legal and other proceedings.Changed · 91% alike1460 → 1394
31.205-48Research and development costs.Research and development costs.Changed · 95% alike63 → 66
31.205-49Goodwill.Goodwill.Changed · 94% alike81 → 87
31.205-50[Reserved][Reserved]Same0 → 0
31.205-51Costs of alcoholic beverages.Costs of alcoholic beverages.Same6 → 6
31.205-52Asset valuations resulting from business combinations.Asset valuations resulting from business combinations.Changed · 98% alike104 → 104
31.301Purpose.Purpose.Changed · 82% alike26 → 23
31.302General.General.Changed · 70% alike60 → 32
31.303Requirements.Requirements.Changed · 84% alike96 → 73
31.601Purpose.Purpose.Changed · 90% alike22 → 27
31.602General.General.Same68 → 68
31.603Requirements.Requirements.Changed · 94% alike780 → 758
31.701Purpose.Definition.Changed · 84% alike110 → 82
31.702General.General.Changed · 94% alike63 → 56
31.703Requirements.Requirements.Changed · 95% alike86 → 85