The FAR overhaul, side by side

FAR Part 31: Contract Cost Principles and Procedures

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 87 sections, 30,986 words (Part 31 as in force, eCFR as of Oct 29, 2026). Overhaul text: 89 sections, 29,337 words (on acquisition.gov ↗, issued Jul 17, 2025). By number: 15 the same, 72 changed, 0 not in the overhaul, 2 new.

31.204: Changed (89% alike)

Today: Application of principles and procedures.

This section in plain English

(a) Costs are allowable to the extent they are reasonable, allocable, and determined to be allowable under 31.201, 31.202, 31.203, and 31.205. These criteria apply to all of the selected items that follow, even if particular guidance is provided for certain items for emphasis or clarity.

(b)(1) For the following subcontract types, costs incurred as reimbursements or payments to a subcontractor are allowable to the extent the reimbursements or payments are for costs incurred by the subcontractor that are consistent with this part:

(i) Cost-reimbursement.

(ii) Fixed-price incentive.

(iii) Price redeterminable (i.e., fixed-price contracts with prospective price redetermination and fixed-ceiling-price contracts with retroactive price redetermination).

(2) The requirements of paragraph (b)(1) of this section apply to any tier above the first firm-fixed-price subcontract or fixed-price subcontract with economic price adjustment provisions.

(c) Costs incurred as payments under firm-fixed-price subcontracts or fixed-price subcontracts with economic price adjustment provisions or modifications thereto, for which subcontract cost analysis was performed are allowable if the price was negotiated in accordance with 31.102.

(d) Section 31.205 does not cover every element of cost. Failure to include any item of cost does not imply that it is either allowable or unallowable. The determination of allowability shall be based on the principles and standards in this subpart and the treatment of similar or related selected items. When more than one subsection in 31.205 is relevant to a contractor cost, the cost shall be apportioned among the applicable subsections, and the determination of allowability of each portion shall be based on the guidance contained in the applicable subsection. When a cost, to which more than one subsection in 31.205 is relevant, cannot be apportioned, the determination of allowability shall be based on the guidance contained in the subsection that most specifically deals with, or best captures the essential nature of, the cost at issue.

Overhaul text: Application of principles and procedures.

On acquisition.gov ↗

(a) Costs are allowable to the extent they are reasonable, allocable, and determined to be allowable under 31.201, 31.202, 31.203, 31.205.

(b)

(1) For the following subcontract types, costs incurred as reimbursements or payments to a subcontractor are allowable to the extent the reimbursements or payments are for costs incurred by the subcontractor that are consistent with this part:

(i) Cost-reimbursement.

(ii) Fixed-price incentive.

(iii) Price redeterminable ( i.e., fixed-price contracts with prospective price redetermination and fixed-ceiling-price contracts with retroactive price redetermination).

(2) The requirements of paragraph (b)(1) of this section apply to any tier above the first firm-fixed-price subcontract or fixed-price subcontract with economic price adjustment provisions.

(c) Costs incurred as payments under firm-fixed-price subcontracts or fixed-price subcontracts with economic price adjustment provisions or modifications, for which subcontract cost analysis was performed are allowable if the price was negotiated in accordance with 31.102.

(d) Section 31.205 does not cover every element of cost.

(1) Failure to include any item of cost does not imply that it is either allowable or unallowable.

(2) The determination of allowability must be based on the principles and standards in this subpart and the treatment of similar or related selected items.

(3) When more than one section in 31.205 is relevant to a contractor cost, the cost must be apportioned among the applicable sections, and the determination of allowability of each portion must be based on the guidance contained in the applicable section.

(4) When a cost to which more than one section in 31.205 is relevant and cannot be apportioned, the determination of allowability must be based on the guidance contained in the section that addresses the specific cost.

Section by section

SectionTodayOverhaul textStatusWords
31.000Scope of part.Scope of part.Same44 → 44
31.001Definitions.Applicability.Changed · 1% alike2375 → 36
31.002Availability of accounting guide.Definitions.Changed · 1% alike38 → 1901
31.003noneAvailability of accounting guide.New number– → 32
31.004noneDeviations.New number– → 58
31.100Scope of subpart.Scope of subpart.Changed · 48% alike32 → 52
31.101Objectives.[Reserved]Changed · 0% alike134 → 0
31.102Fixed-price contracts.Fixed-price contracts.Changed · 81% alike118 → 95
31.103Contracts with commercial organizations.Contracts with commercial organizations.Changed · 91% alike221 → 200
31.104Contracts with educational institutions.Contracts with educational institutions.Changed · 91% alike134 → 129
31.105Construction and architect-engineer contracts.Construction and architect-engineer contracts.Changed · 74% alike941 → 908
31.106[Reserved][Reserved]Same0 → 0
31.107Contracts with State, local, and federally recognized Indian tribal governments.Contracts with State, local, and federally recognized Indian tribal governments.Changed · 78% alike125 → 95
31.108Contracts with nonprofit organizations.Contracts with nonprofit organizations.Changed · 98% alike73 → 76
31.109Advance agreements.Indirect cost rate certification and penalties on unallowable costs.Changed · 3% alike678 → 41
31.110Indirect cost rate certification and penalties on unallowable costs.Advance agreements.Changed · 5% alike63 → 528
31.201General.General.Same0 → 0
31.201-1Composition of total cost.Composition of total cost.Changed · 93% alike111 → 108
31.201-2Determining allowability.Determining allowability.Changed · 95% alike290 → 292
31.201-3Determining reasonableness.Determining reasonableness.Changed · 72% alike201 → 186
31.201-4Determining allocability.Determining allocability.Changed · 85% alike92 → 83
31.201-5Credits.Credits.Changed · 55% alike60 → 57
31.201-6Accounting for unallowable costs.Accounting for unallowable costs.Changed · 93% alike765 → 745
31.201-7Construction and architect-engineer contracts.Construction and architect-engineer contracts.Changed · 80% alike42 → 28
31.202Direct costs.Direct costs.Changed · 97% alike138 → 141
31.203Indirect costs.Indirect costs.Changed · 95% alike611 → 608
31.204Application of principles and procedures.Application of principles and procedures.Changed · 89% alike320 → 288
31.205Selected costs.Selected costs.Same0 → 0
31.205-1Public relations and advertising costs.Public relations and advertising costs.Changed · 95% alike726 → 704
31.205-2[Reserved][Reserved]Same0 → 0
31.205-3Bad debts.Bad debts.Same32 → 32
31.205-4Bonding costs.Bonding costs.Changed · 90% alike105 → 105
31.205-5[Reserved][Reserved]Same0 → 0
31.205-6Compensation for personal services.Compensation for personal services.Changed · 88% alike5911 → 5798
31.205-7Contingencies.Contingencies.Changed · 95% alike243 → 241
31.205-8Contributions or donations.Contributions or donations.Changed · 86% alike22 → 20
31.205-9[Reserved][Reserved]Same0 → 0
31.205-10Cost of money.Cost of money.Changed · 98% alike180 → 182
31.205-11Depreciation.Depreciation.Changed · 91% alike855 → 818
31.205-12Economic planning costs.Economic planning costs.Changed · 92% alike81 → 84
31.205-13Employee morale, health, welfare, food service, and dormitory costs and credits.Employee morale, health, welfare, food service, and dormitory costs and credits.Changed · 96% alike500 → 492
31.205-14Entertainment costs.Entertainment costs.Changed · 75% alike75 → 77
31.205-15Fines, penalties, and mischarging costs.Fines, penalties, and mischarging costs.Same126 → 126
31.205-16Gains and losses on disposition or impairment of depreciable property or other capital assets.Gains and losses on disposition or impairment of depreciable property or other capital assets.Changed · 94% alike733 → 737
31.205-17Idle facilities and idle capacity costs.Idle facilities and idle capacity costs.Changed · 97% alike376 → 383
31.205-18Independent research and development and bid and proposal costs.Independent research and development and bid and proposal costs.Changed · 91% alike1099 → 1041
31.205-19Insurance and indemnification.Insurance and indemnification.Changed · 94% alike864 → 824
31.205-20Interest and other financial costs.Interest and other financial costs.Changed · 79% alike64 → 78
31.205-21Labor relations costs.Labor relations costs.Changed · 92% alike149 → 127
31.205-22Lobbying and political activity costs.Lobbying and political activity costs.Changed · 94% alike590 → 563
31.205-23Losses on other contracts.Losses on other contracts.Changed · 63% alike22 → 16
31.205-24[Reserved][Reserved]Same0 → 0
31.205-25Manufacturing and production engineering costs.Manufacturing and production engineering costs.Changed · 88% alike214 → 183
31.205-26Material costs.Material costs.Changed · 97% alike409 → 413
31.205-27Organization costs.Organization costs.Changed · 94% alike193 → 193
31.205-28Other business expenses.Other business expenses.Same66 → 66
31.205-29Plant protection costs.Plant protection costs.Changed · 82% alike34 → 32
31.205-30Patent costs.Patent costs.Changed · 90% alike125 → 116
31.205-31Plant reconversion costs.Plant reconversion costs.Changed · 89% alike96 → 104
31.205-32Precontract costs.Precontract costs.Changed · 97% alike61 → 61
31.205-33Professional and consultant service costs.Professional and consultant service costs.Changed · 93% alike709 → 673
31.205-34Recruitment costs.Recruitment costs.Changed · 85% alike117 → 110
31.205-35Relocation costs.Relocation costs.Changed · 94% alike1191 → 1179
31.205-36Rental costs.Rental costs.Changed · 94% alike295 → 303
31.205-37Royalties and other costs for use of patents.Royalties and other costs for use of patents.Changed · 93% alike190 → 181
31.205-38Selling costs.Selling costs.Changed · 95% alike347 → 349
31.205-39Service and warranty costs.Service and warranty costs.Changed · 96% alike76 → 78
31.205-40Special tooling and special test equipment costs.Special tooling and special test equipment costs.Changed · 52% alike165 → 129
31.205-41Taxes.Taxes.Changed · 87% alike786 → 749
31.205-42Termination costs.Termination costs.Changed · 91% alike943 → 917
31.205-43Trade, business, technical, and professional activity costs.Trade, business, technical, and professional activity costs.Changed · 99% alike143 → 143
31.205-44Training and education costs.Training and education costs.Changed · 97% alike207 → 206
31.205-45[Reserved][Reserved]Same0 → 0
31.205-46Travel costs.Travel costs.Changed · 84% alike1235 → 1112
31.205-47Costs related to legal and other proceedings.Costs related to legal and other proceedings.Changed · 91% alike1460 → 1394
31.205-48Research and development costs.Research and development costs.Changed · 95% alike63 → 66
31.205-49Goodwill.Goodwill.Changed · 94% alike81 → 87
31.205-50[Reserved][Reserved]Same0 → 0
31.205-51Costs of alcoholic beverages.Costs of alcoholic beverages.Same6 → 6
31.205-52Asset valuations resulting from business combinations.Asset valuations resulting from business combinations.Changed · 98% alike104 → 104
31.301Purpose.Purpose.Changed · 82% alike26 → 23
31.302General.General.Changed · 70% alike60 → 32
31.303Requirements.Requirements.Changed · 84% alike96 → 73
31.601Purpose.Purpose.Changed · 90% alike22 → 27
31.602General.General.Same68 → 68
31.603Requirements.Requirements.Changed · 94% alike780 → 758
31.701Purpose.Definition.Changed · 84% alike110 → 82
31.702General.General.Changed · 94% alike63 → 56
31.703Requirements.Requirements.Changed · 95% alike86 → 85