The FAR overhaul, side by side

FAR Part 31: Contract Cost Principles and Procedures

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 87 sections, 30,986 words (Part 31 as in force, eCFR as of Oct 29, 2026). Overhaul text: 89 sections, 29,337 words (on acquisition.gov ↗, issued Jul 17, 2025). By number: 15 the same, 72 changed, 0 not in the overhaul, 2 new.

31.201-6: Changed (93% alike)

Today: Accounting for unallowable costs.

This section in plain English

(a) Costs that are expressly unallowable or mutually agreed to be unallowable, including mutually agreed to be unallowable directly associated costs, shall be identified and excluded from any billing, claim, or proposal applicable to a Government contract. A directly associated cost is any cost that is generated solely as a result of incurring another cost, and that would not have been incurred had the other cost not been incurred. When an unallowable cost is incurred, its directly associated costs are also unallowable.

(b) Costs that specifically become designated as unallowable or as unallowable directly associated costs of unallowable costs as a result of a written decision furnished by a contracting officer shall be identified if included in or used in computing any billing, claim, or proposal applicable to a Government contract. This identification requirement applies also to any costs incurred for the same purpose under like circumstances as the costs specifically identified as unallowable under either this paragraph or paragraph (a) above.

(c)(1) The practices for accounting for and presentation of unallowable costs must be those described in 48 CFR 9904.405, Accounting for Unallowable Costs.

(2) Statistical sampling is an acceptable practice for contractors to follow in accounting for and presenting unallowable costs provided the following criteria in paragraphs (c)(2)(i), (c)(2)(ii), and (c)(2)(iii) of this subsection are met:

(i) The statistical sampling results in an unbiased sample that is a reasonable representation of the sampling universe.

(ii) Any large dollar value or high risk transaction is separately reviewed for unallowable costs and excluded from the sampling process.

(iii) The statistical sampling permits audit verification.

(3) For any indirect cost in the selected sample that is subject to the penalty provisions at 42.709, the amount projected to the sampling universe from that sampled cost is also subject to the same penalty provisions.

(4) Use of statistical sampling methods for identifying and segregating unallowable costs should be the subject of an advance agreement under the provisions of 31.109 between the contractor and the cognizant administrative contracting officer or Federal official. The advance agreement should specify the basic characteristics of the sampling process. The cognizant administrative contracting officer or Federal official shall request input from the cognizant auditor before entering into any such agreements.

(5) In the absence of an advance agreement, if an initial review of the facts results in a challenge of the statistical sampling methods by the contracting officer or the contracting officer's representative, the burden of proof shall be on the contractor to establish that such a method meets the criteria in paragraph (c)(2) of this subsection.

(d) If a directly associated cost is included in a cost pool that is allocated over a base that includes the unallowable cost with which it is associated, the directly associated cost shall remain in the cost pool. Since the unallowable costs will attract their allocable share of costs from the cost pool, no further action is required to assure disallowance of the directly associated costs. In all other cases, the directly associated costs, if material in amount, must be purged from the cost pool as unallowable costs.

(e)(1) In determining the materiality of a directly associated cost, consideration should be given to the significance of (i) the actual dollar amount, (ii) the cumulative effect of all directly associated costs in a cost pool, and (iii) the ultimate effect on the cost of Government contracts.

(2) Salary expenses of employees who participate in activities that generate unallowable costs shall be treated as directly associated costs to the extent of the time spent on the proscribed activity, provided the costs are material in accordance with subparagraph (e)(1) above (except when such salary expenses are, themselves, unallowable). The time spent in proscribed activities should be compared to total time spent on company activities to determine if the costs are material. Time spent by employees outside the normal working hours should not be considered except when it is evident that an employee engages so frequently in company activities during periods outside normal working hours as to indicate that such activities are a part of the employee's regular duties.

(3) When a selected item of cost under 31.205 provides that directly associated costs be unallowable, such directly associated costs are unallowable only if determined to be material in amount in accordance with the criteria provided in paragraphs (e)(1) and (e)(2) of this subsection, except in those situations where allowance of any of the directly associated costs involved would be considered to be contrary to public policy.

Overhaul text: Accounting for unallowable costs.

On acquisition.gov ↗

(a) Expressly unallowable costs or mutually agreed to be unallowable costs (including mutually agreed to be unallowable directly associated costs) must be identified and excluded from any billing, claim, or proposal applicable to a Government contract.

(1) A directly associated cost is any cost that is generated solely as a result of incurring another cost, and that would not have been incurred had the other cost not been incurred.

(2) When an unallowable cost is incurred, its directly associated costs are also unallowable.

(b)

(1) Costs that specifically become designated as unallowable or as unallowable directly associated costs of unallowable costs as a result of a written decision furnished by a contracting officer must be identified if included in or used in computing any billing, claim, or proposal applicable to a Government contract.

(2) This identification requirement also applies to any costs incurred for the same purpose under like circumstances as the costs specifically identified as unallowable under paragraph (a) or (b) of this section.

(c)

(1) The practices for accounting for and the presentation of unallowable costs must be in accordance with those described in 48 CFR 9904.405.

(2) Statistical sampling is an acceptable practice for contractors to follow in accounting for and presenting unallowable costs, provided the following criteria are met:

(i) The statistical sampling results in an unbiased sample that is a reasonable representation of the sampling universe.

(ii) Any large dollar value or high risk transaction is separately reviewed for unallowable costs and excluded from the sampling process.

(iii) The statistical sampling permits audit verification.

(3) For any indirect cost in the selected sample that is subject to the penalty provisions at 42.709, the amount projected to the sampling universe from that sampled cost is also subject to the same penalty provisions.

(4) Use of statistical sampling methods for identifying and segregating unallowable costs should be the subject of an advance agreement (see 31.110).

(i) The advance agreement should specify the basic characteristics of the sampling process.

(ii) The cognizant administrative contracting officer (ACO) or Federal official must request input from the cognizant auditor before entering into any such agreements.

(5) In the absence of an advance agreement, if an initial review of the facts results in a challenge of the statistical sampling methods by the contracting officer or the contracting officer’s representative, the burden of proof must be on the contractor to establish that such a method meets the criteria in paragraph (c)(2) of this section.

(d) If a directly associated cost is included in a cost pool that is allocated over a base that includes the unallowable cost with which it is associated, the directly associated cost must remain in the cost pool.

(1) Since the unallowable costs will attract their allocable share of costs from the cost pool, no further action is required to assure disallowance of the directly associated costs.

(2) In all other cases, the directly associated costs, if material in amount, must be purged from the cost pool as unallowable costs.

(e)

(1) In determining the materiality of a directly associated cost, consideration should be given to the significance of the—

(i) Actual dollar amount;

(ii) Cumulative effect of all directly associated costs in a cost pool; and

(iii) Ultimate effect on the cost of Government contracts.

(2) Salary expenses of employees who participate in activities that generate unallowable costs must be treated as directly associated costs to the extent of the time spent on the proscribed activity, provided the costs are material in accordance with paragraph (e)(1) of this section (except when such salary expenses are unallowable).

(i) The time spent on proscribed activities should be compared to total time spent on company activities to determine if the costs are material.

(ii) Time spent by employees outside the normal working hours should not be considered except when it is evident that an employee engages so frequently in company activities during periods outside normal working hours as to indicate that such activities are a part of the employee's regular duties.

(3) When a selected item of cost at 31.205 provides that directly associated costs be unallowable, such directly associated costs are unallowable only if determined to be material in amount in accordance with the criteria provided in paragraphs (e)(1) and (e)(2) of this section, except in those situations where allowance of any of the directly associated costs involved would be considered to be contrary to public policy.

Section by section

SectionTodayOverhaul textStatusWords
31.000Scope of part.Scope of part.Same44 → 44
31.001Definitions.Applicability.Changed · 1% alike2375 → 36
31.002Availability of accounting guide.Definitions.Changed · 1% alike38 → 1901
31.003noneAvailability of accounting guide.New number– → 32
31.004noneDeviations.New number– → 58
31.100Scope of subpart.Scope of subpart.Changed · 48% alike32 → 52
31.101Objectives.[Reserved]Changed · 0% alike134 → 0
31.102Fixed-price contracts.Fixed-price contracts.Changed · 81% alike118 → 95
31.103Contracts with commercial organizations.Contracts with commercial organizations.Changed · 91% alike221 → 200
31.104Contracts with educational institutions.Contracts with educational institutions.Changed · 91% alike134 → 129
31.105Construction and architect-engineer contracts.Construction and architect-engineer contracts.Changed · 74% alike941 → 908
31.106[Reserved][Reserved]Same0 → 0
31.107Contracts with State, local, and federally recognized Indian tribal governments.Contracts with State, local, and federally recognized Indian tribal governments.Changed · 78% alike125 → 95
31.108Contracts with nonprofit organizations.Contracts with nonprofit organizations.Changed · 98% alike73 → 76
31.109Advance agreements.Indirect cost rate certification and penalties on unallowable costs.Changed · 3% alike678 → 41
31.110Indirect cost rate certification and penalties on unallowable costs.Advance agreements.Changed · 5% alike63 → 528
31.201General.General.Same0 → 0
31.201-1Composition of total cost.Composition of total cost.Changed · 93% alike111 → 108
31.201-2Determining allowability.Determining allowability.Changed · 95% alike290 → 292
31.201-3Determining reasonableness.Determining reasonableness.Changed · 72% alike201 → 186
31.201-4Determining allocability.Determining allocability.Changed · 85% alike92 → 83
31.201-5Credits.Credits.Changed · 55% alike60 → 57
31.201-6Accounting for unallowable costs.Accounting for unallowable costs.Changed · 93% alike765 → 745
31.201-7Construction and architect-engineer contracts.Construction and architect-engineer contracts.Changed · 80% alike42 → 28
31.202Direct costs.Direct costs.Changed · 97% alike138 → 141
31.203Indirect costs.Indirect costs.Changed · 95% alike611 → 608
31.204Application of principles and procedures.Application of principles and procedures.Changed · 89% alike320 → 288
31.205Selected costs.Selected costs.Same0 → 0
31.205-1Public relations and advertising costs.Public relations and advertising costs.Changed · 95% alike726 → 704
31.205-2[Reserved][Reserved]Same0 → 0
31.205-3Bad debts.Bad debts.Same32 → 32
31.205-4Bonding costs.Bonding costs.Changed · 90% alike105 → 105
31.205-5[Reserved][Reserved]Same0 → 0
31.205-6Compensation for personal services.Compensation for personal services.Changed · 88% alike5911 → 5798
31.205-7Contingencies.Contingencies.Changed · 95% alike243 → 241
31.205-8Contributions or donations.Contributions or donations.Changed · 86% alike22 → 20
31.205-9[Reserved][Reserved]Same0 → 0
31.205-10Cost of money.Cost of money.Changed · 98% alike180 → 182
31.205-11Depreciation.Depreciation.Changed · 91% alike855 → 818
31.205-12Economic planning costs.Economic planning costs.Changed · 92% alike81 → 84
31.205-13Employee morale, health, welfare, food service, and dormitory costs and credits.Employee morale, health, welfare, food service, and dormitory costs and credits.Changed · 96% alike500 → 492
31.205-14Entertainment costs.Entertainment costs.Changed · 75% alike75 → 77
31.205-15Fines, penalties, and mischarging costs.Fines, penalties, and mischarging costs.Same126 → 126
31.205-16Gains and losses on disposition or impairment of depreciable property or other capital assets.Gains and losses on disposition or impairment of depreciable property or other capital assets.Changed · 94% alike733 → 737
31.205-17Idle facilities and idle capacity costs.Idle facilities and idle capacity costs.Changed · 97% alike376 → 383
31.205-18Independent research and development and bid and proposal costs.Independent research and development and bid and proposal costs.Changed · 91% alike1099 → 1041
31.205-19Insurance and indemnification.Insurance and indemnification.Changed · 94% alike864 → 824
31.205-20Interest and other financial costs.Interest and other financial costs.Changed · 79% alike64 → 78
31.205-21Labor relations costs.Labor relations costs.Changed · 92% alike149 → 127
31.205-22Lobbying and political activity costs.Lobbying and political activity costs.Changed · 94% alike590 → 563
31.205-23Losses on other contracts.Losses on other contracts.Changed · 63% alike22 → 16
31.205-24[Reserved][Reserved]Same0 → 0
31.205-25Manufacturing and production engineering costs.Manufacturing and production engineering costs.Changed · 88% alike214 → 183
31.205-26Material costs.Material costs.Changed · 97% alike409 → 413
31.205-27Organization costs.Organization costs.Changed · 94% alike193 → 193
31.205-28Other business expenses.Other business expenses.Same66 → 66
31.205-29Plant protection costs.Plant protection costs.Changed · 82% alike34 → 32
31.205-30Patent costs.Patent costs.Changed · 90% alike125 → 116
31.205-31Plant reconversion costs.Plant reconversion costs.Changed · 89% alike96 → 104
31.205-32Precontract costs.Precontract costs.Changed · 97% alike61 → 61
31.205-33Professional and consultant service costs.Professional and consultant service costs.Changed · 93% alike709 → 673
31.205-34Recruitment costs.Recruitment costs.Changed · 85% alike117 → 110
31.205-35Relocation costs.Relocation costs.Changed · 94% alike1191 → 1179
31.205-36Rental costs.Rental costs.Changed · 94% alike295 → 303
31.205-37Royalties and other costs for use of patents.Royalties and other costs for use of patents.Changed · 93% alike190 → 181
31.205-38Selling costs.Selling costs.Changed · 95% alike347 → 349
31.205-39Service and warranty costs.Service and warranty costs.Changed · 96% alike76 → 78
31.205-40Special tooling and special test equipment costs.Special tooling and special test equipment costs.Changed · 52% alike165 → 129
31.205-41Taxes.Taxes.Changed · 87% alike786 → 749
31.205-42Termination costs.Termination costs.Changed · 91% alike943 → 917
31.205-43Trade, business, technical, and professional activity costs.Trade, business, technical, and professional activity costs.Changed · 99% alike143 → 143
31.205-44Training and education costs.Training and education costs.Changed · 97% alike207 → 206
31.205-45[Reserved][Reserved]Same0 → 0
31.205-46Travel costs.Travel costs.Changed · 84% alike1235 → 1112
31.205-47Costs related to legal and other proceedings.Costs related to legal and other proceedings.Changed · 91% alike1460 → 1394
31.205-48Research and development costs.Research and development costs.Changed · 95% alike63 → 66
31.205-49Goodwill.Goodwill.Changed · 94% alike81 → 87
31.205-50[Reserved][Reserved]Same0 → 0
31.205-51Costs of alcoholic beverages.Costs of alcoholic beverages.Same6 → 6
31.205-52Asset valuations resulting from business combinations.Asset valuations resulting from business combinations.Changed · 98% alike104 → 104
31.301Purpose.Purpose.Changed · 82% alike26 → 23
31.302General.General.Changed · 70% alike60 → 32
31.303Requirements.Requirements.Changed · 84% alike96 → 73
31.601Purpose.Purpose.Changed · 90% alike22 → 27
31.602General.General.Same68 → 68
31.603Requirements.Requirements.Changed · 94% alike780 → 758
31.701Purpose.Definition.Changed · 84% alike110 → 82
31.702General.General.Changed · 94% alike63 → 56
31.703Requirements.Requirements.Changed · 95% alike86 → 85