The FAR overhaul, side by side

FAR Part 31: Contract Cost Principles and Procedures

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 87 sections, 30,986 words (Part 31 as in force, eCFR as of Oct 29, 2026). Overhaul text: 89 sections, 29,337 words (on acquisition.gov ↗, issued Jul 17, 2025). By number: 15 the same, 72 changed, 0 not in the overhaul, 2 new.

31.109: Changed (3% alike)

Today: Advance agreements.

This section in plain English

(a) The extent of allowability of the costs covered in this part applies broadly to many accounting systems in varying contract situations. Thus, the reasonableness, the allocability and the allowability under the specific cost principles at subparts 31.2, 31.3, 31.6, and 31.7 of certain costs may be difficult to determine. To avoid possible subsequent disallowance or dispute based on unreasonableness, unallocability or unallowability under the specific cost principles at subparts 31.2, 31.3, 31.6, and 31.7, contracting officers and contractors should seek advance agreement on the treatment of special or unusual costs and on statistical sampling methodologies at 31.201-6(c). However, an advance agreement is not an absolute requirement and the absence of an advance agreement on any cost will not, in itself, affect the reasonableness, allocability or the allowability under the specific cost principles at subparts 31.2, 31.3, 31.6, and 31.7 of that cost.

(b) Advance agreements may be negotiated either before or during a contract but should be negotiated before incurrence of the costs involved. The agreements must be in writing, executed by both contracting parties, and incorporated into applicable current and future contracts. An advance agreement shall contain a statement of its applicability and duration.

(c) The contracting officer is not authorized by this 31.109 to agree to a treatment of costs inconsistent with this part. For example, an advance agreement may not provide that, notwithstanding 31.205-20, interest is allowable.

(d) Advance agreements may be negotiated with a particular contractor for a single contract, a group of contracts, or all the contracts of a contracting office, an agency, or several agencies.

(e) The cognizant administrative contracting officer (ACO), or other contracting officer established in part 42, shall negotiate advance agreements except that an advance agreement affecting only one contract, or class of contracts from a single contracting office, shall be negotiated by a contracting officer in the contracting office, or an ACO when delegated by the contracting officer. When the negotiation authority is delegated, the ACO shall coordinate the proposed agreement with the contracting officer before executing the advance agreement.

(f) Before negotiating an advance agreement, the Government negotiator shall—

(1) Determine if other contracting offices inside the agency or in other agencies have a significant unliquidated dollar balance in contracts with the same contractor;

(2) Inform any such office or agency of the matters under consideration for negotiation; and

(3) As appropriate, invite the office or agency and the responsible audit agency to participate in prenegotiation discussions and/or in the subsequent negotiations.

(g) Upon completion of the negotiation, the sponsor shall prepare and distribute to other interested agencies and offices, including the audit agency, copies of the executed agreement and a memorandum providing the information specified in 15.406-3, as applicable.

(h) Examples for which advance agreements may be particularly important are—

(1) Compensation for personal services, including but not limited to allowances for off-site pay, incentive pay, location allowances, hardship pay, cost of living differential, and termination of defined benefit pension plans;

(2) Use charges for fully depreciated assets;

(3) Deferred maintenance costs;

(4) Precontract costs;

(5) Independent research and development and bid and proposal costs;

(6) Royalties and other costs for use of patents;

(7) Selling and distribution costs;

(8) Travel and relocation costs, as related to special or mass personnel movements, as related to travel via contractor-owned, -leased, or -chartered aircraft, or as related to maximum per diem rates;

(9) Costs of idle facilities and idle capacity;

(10) Severance pay to employees on support service contracts;

(11) Plant reconversion;

(12) Professional services (e.g., legal, accounting, and engineering);

(13) General and administrative costs (e.g., corporate, division, or branch allocations) attributable to the general management, supervision, and conduct of the contractor's business as a whole. These costs are particularly significant in construction, job-site, architect-engineer, facilities, and Government-owned contractor operated (GOCO) plant contracts (see 31.203(h));

(14) Costs of construction plant and equipment (see 31.105(d)).

(15) Costs of public relations and advertising; and

(16) Statistical sampling methods (see 31.201-6(c)(4).

Overhaul text: Indirect cost rate certification and penalties on unallowable costs.

On acquisition.gov ↗

(a) Certain contracts require certification of the indirect cost rates proposed for final payment purposes (see 42.703-2).

(b) If unallowable costs are included in final indirect cost settlement proposals, penalties may be assessed (see 42.703-2 and 42.709).

Section by section

SectionTodayOverhaul textStatusWords
31.000Scope of part.Scope of part.Same44 → 44
31.001Definitions.Applicability.Changed · 1% alike2375 → 36
31.002Availability of accounting guide.Definitions.Changed · 1% alike38 → 1901
31.003noneAvailability of accounting guide.New number– → 32
31.004noneDeviations.New number– → 58
31.100Scope of subpart.Scope of subpart.Changed · 48% alike32 → 52
31.101Objectives.[Reserved]Changed · 0% alike134 → 0
31.102Fixed-price contracts.Fixed-price contracts.Changed · 81% alike118 → 95
31.103Contracts with commercial organizations.Contracts with commercial organizations.Changed · 91% alike221 → 200
31.104Contracts with educational institutions.Contracts with educational institutions.Changed · 91% alike134 → 129
31.105Construction and architect-engineer contracts.Construction and architect-engineer contracts.Changed · 74% alike941 → 908
31.106[Reserved][Reserved]Same0 → 0
31.107Contracts with State, local, and federally recognized Indian tribal governments.Contracts with State, local, and federally recognized Indian tribal governments.Changed · 78% alike125 → 95
31.108Contracts with nonprofit organizations.Contracts with nonprofit organizations.Changed · 98% alike73 → 76
31.109Advance agreements.Indirect cost rate certification and penalties on unallowable costs.Changed · 3% alike678 → 41
31.110Indirect cost rate certification and penalties on unallowable costs.Advance agreements.Changed · 5% alike63 → 528
31.201General.General.Same0 → 0
31.201-1Composition of total cost.Composition of total cost.Changed · 93% alike111 → 108
31.201-2Determining allowability.Determining allowability.Changed · 95% alike290 → 292
31.201-3Determining reasonableness.Determining reasonableness.Changed · 72% alike201 → 186
31.201-4Determining allocability.Determining allocability.Changed · 85% alike92 → 83
31.201-5Credits.Credits.Changed · 55% alike60 → 57
31.201-6Accounting for unallowable costs.Accounting for unallowable costs.Changed · 93% alike765 → 745
31.201-7Construction and architect-engineer contracts.Construction and architect-engineer contracts.Changed · 80% alike42 → 28
31.202Direct costs.Direct costs.Changed · 97% alike138 → 141
31.203Indirect costs.Indirect costs.Changed · 95% alike611 → 608
31.204Application of principles and procedures.Application of principles and procedures.Changed · 89% alike320 → 288
31.205Selected costs.Selected costs.Same0 → 0
31.205-1Public relations and advertising costs.Public relations and advertising costs.Changed · 95% alike726 → 704
31.205-2[Reserved][Reserved]Same0 → 0
31.205-3Bad debts.Bad debts.Same32 → 32
31.205-4Bonding costs.Bonding costs.Changed · 90% alike105 → 105
31.205-5[Reserved][Reserved]Same0 → 0
31.205-6Compensation for personal services.Compensation for personal services.Changed · 88% alike5911 → 5798
31.205-7Contingencies.Contingencies.Changed · 95% alike243 → 241
31.205-8Contributions or donations.Contributions or donations.Changed · 86% alike22 → 20
31.205-9[Reserved][Reserved]Same0 → 0
31.205-10Cost of money.Cost of money.Changed · 98% alike180 → 182
31.205-11Depreciation.Depreciation.Changed · 91% alike855 → 818
31.205-12Economic planning costs.Economic planning costs.Changed · 92% alike81 → 84
31.205-13Employee morale, health, welfare, food service, and dormitory costs and credits.Employee morale, health, welfare, food service, and dormitory costs and credits.Changed · 96% alike500 → 492
31.205-14Entertainment costs.Entertainment costs.Changed · 75% alike75 → 77
31.205-15Fines, penalties, and mischarging costs.Fines, penalties, and mischarging costs.Same126 → 126
31.205-16Gains and losses on disposition or impairment of depreciable property or other capital assets.Gains and losses on disposition or impairment of depreciable property or other capital assets.Changed · 94% alike733 → 737
31.205-17Idle facilities and idle capacity costs.Idle facilities and idle capacity costs.Changed · 97% alike376 → 383
31.205-18Independent research and development and bid and proposal costs.Independent research and development and bid and proposal costs.Changed · 91% alike1099 → 1041
31.205-19Insurance and indemnification.Insurance and indemnification.Changed · 94% alike864 → 824
31.205-20Interest and other financial costs.Interest and other financial costs.Changed · 79% alike64 → 78
31.205-21Labor relations costs.Labor relations costs.Changed · 92% alike149 → 127
31.205-22Lobbying and political activity costs.Lobbying and political activity costs.Changed · 94% alike590 → 563
31.205-23Losses on other contracts.Losses on other contracts.Changed · 63% alike22 → 16
31.205-24[Reserved][Reserved]Same0 → 0
31.205-25Manufacturing and production engineering costs.Manufacturing and production engineering costs.Changed · 88% alike214 → 183
31.205-26Material costs.Material costs.Changed · 97% alike409 → 413
31.205-27Organization costs.Organization costs.Changed · 94% alike193 → 193
31.205-28Other business expenses.Other business expenses.Same66 → 66
31.205-29Plant protection costs.Plant protection costs.Changed · 82% alike34 → 32
31.205-30Patent costs.Patent costs.Changed · 90% alike125 → 116
31.205-31Plant reconversion costs.Plant reconversion costs.Changed · 89% alike96 → 104
31.205-32Precontract costs.Precontract costs.Changed · 97% alike61 → 61
31.205-33Professional and consultant service costs.Professional and consultant service costs.Changed · 93% alike709 → 673
31.205-34Recruitment costs.Recruitment costs.Changed · 85% alike117 → 110
31.205-35Relocation costs.Relocation costs.Changed · 94% alike1191 → 1179
31.205-36Rental costs.Rental costs.Changed · 94% alike295 → 303
31.205-37Royalties and other costs for use of patents.Royalties and other costs for use of patents.Changed · 93% alike190 → 181
31.205-38Selling costs.Selling costs.Changed · 95% alike347 → 349
31.205-39Service and warranty costs.Service and warranty costs.Changed · 96% alike76 → 78
31.205-40Special tooling and special test equipment costs.Special tooling and special test equipment costs.Changed · 52% alike165 → 129
31.205-41Taxes.Taxes.Changed · 87% alike786 → 749
31.205-42Termination costs.Termination costs.Changed · 91% alike943 → 917
31.205-43Trade, business, technical, and professional activity costs.Trade, business, technical, and professional activity costs.Changed · 99% alike143 → 143
31.205-44Training and education costs.Training and education costs.Changed · 97% alike207 → 206
31.205-45[Reserved][Reserved]Same0 → 0
31.205-46Travel costs.Travel costs.Changed · 84% alike1235 → 1112
31.205-47Costs related to legal and other proceedings.Costs related to legal and other proceedings.Changed · 91% alike1460 → 1394
31.205-48Research and development costs.Research and development costs.Changed · 95% alike63 → 66
31.205-49Goodwill.Goodwill.Changed · 94% alike81 → 87
31.205-50[Reserved][Reserved]Same0 → 0
31.205-51Costs of alcoholic beverages.Costs of alcoholic beverages.Same6 → 6
31.205-52Asset valuations resulting from business combinations.Asset valuations resulting from business combinations.Changed · 98% alike104 → 104
31.301Purpose.Purpose.Changed · 82% alike26 → 23
31.302General.General.Changed · 70% alike60 → 32
31.303Requirements.Requirements.Changed · 84% alike96 → 73
31.601Purpose.Purpose.Changed · 90% alike22 → 27
31.602General.General.Same68 → 68
31.603Requirements.Requirements.Changed · 94% alike780 → 758
31.701Purpose.Definition.Changed · 84% alike110 → 82
31.702General.General.Changed · 94% alike63 → 56
31.703Requirements.Requirements.Changed · 95% alike86 → 85