The FAR overhaul, side by side
FAR Part 49: Termination of Contracts
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 108 sections, 25,216 words (Part 49 as in force, eCFR as of Oct 29, 2026). Overhaul text: 103 sections, 22,632 words (on acquisition.gov ↗, issued Aug 21, 2025). By number: 16 the same, 87 changed, 5 not in the overhaul, 0 new.
49.108-4: Changed (82% alike)
Today: Authorization for subcontract settlements without approval or ratification.
(a)(1) The TCO may, upon written request, give written authorization to the prime contractor to conclude settlements of subcontracts terminated in whole or in part without approval or ratification when the amount of settlement (see 49.002(d)) is $100,000 or less, if—
(i) The TCO is satisfied with the adequacy of the procedures used by the contractor in settling settlement proposals, including proposals for retention, sale, or other disposal of termination inventory of the immediate and lower tier subcontractors (the TCO shall obtain the advice and recommendations of (A) the appropriate audit agency relating to the adequacy of the contractor's audit administration, including personnel, and (B) the cognizant plant clearance officer relating to the adequacy of the contractor's procedures and personnel for the administration of property disposal matters);
(ii) Any termination inventory included in determining the amount of the settlement will be disposed of as directed by the prime contractor, except that the disposition of the inventory shall not be subject to—
(A) Review by the TCO under 49.108-3(c); or
(B) The screening requirements in 45.602-3; and
(iii) A certificate similar to the certificate in the settlement proposal form in 49.602-1(a) will accompany the settlement.
(2) Except as provided in subparagraph (4) below, authority granted to a prime contractor under subparagraph (1) above by any TCO shall apply to all Executive agencies' prime contracts that are terminated, or modified by change orders.
(3) Except as provided in subparagraph (4) below, the TCO shall accept, as part of the prime contractor's settlement proposal, settlements of terminated lower tier subcontracts concluded by any of the prime contractor's immediate or lower tier subcontractors who have been granted authority as prime contractors to settle subcontracts; provided, that the settlement is within the limit of the authority. Authorization to settle proposals of lower tier subcontractors shall not be granted directly to subcontractors. However, a prime contractor authorized to approve subcontractor settlements may also exercise this authority in its capacity as a subcontractor, with respect to its terminated subcontracts and orders. When exercising this authority as a subcontractor, the contractor shall notify the purchaser.
(4) The provisions of subparagraphs (1), (2), and (3) above shall not apply to contracts under the administration of any contracting officer if the contracting officer so notifies the prime contractor concerned. This notice shall (i) be in writing, and (ii) if subparagraph (3) above is involved, specify any subcontractor affected.
(b) Section 45.602 shall apply to disposal of completed end items allocable to the terminated subcontract. However, these items may be disposed of without review by the TCO under 49.108-3 and without screening under 45.602-3, if the items do not require demilitarization and the total amount (at the subcontract price) when added to the amount of the settlement does not exceed the amount authorized under this subsection.
(c) A TCO granting the authorization in subparagraph (a)(1) above shall periodically (at least annually) make a selective review of settlements and settlement procedures to determine if the contractor is making adequate reviews and fair settlements, and whether the authorization should remain in effect. The TCO shall obtain the advice and recommendations of the appropriate audit agency and the cognizant plant clearance officer. When it is determined that the contractor's procedures are not adequate, or that improper settlements are being made, or when the authority has not been used in the preceding 2 years, the TCO shall revoke the authorization by written notice to the contractor, effective on the date of receipt.
(d) The contractor may make any number of separate settlements with a single subcontractor but shall not divide settlement proposals solely to bring them under an authorization limit. Separate settlement proposals that would normally be included in a single proposal, such as those based on a series of separate orders for the same item under one contract, shall be consolidated whenever possible.
(e) Upon written request of the contractor, the TCO may increase an authorization granted under subparagraph (a)(1) of this subsection to authorize the contractor to conclude settlements under a particular prime contract. The TCO may limit the increased authorization to specific subcontracts or classes of subcontracts.
(f) Authorizations granted under this 49.108-4 shall not authorize the settlement of requisitions or orders placed with any unit within the contractor's corporate entity.
(g) Recommended formats for a request to settle subcontractor settlement proposals and the TCO's letter of authorization to the contractor are in 49.605 and 49.606, respectively.
Overhaul text: Authorization for subcontract settlements without approval or ratification.
(a)
(1) The TCO may give written authorization to the prime contractor to complete settlements of subcontracts terminated in whole or in part without approval or ratification when the settlement amount (see 49.002(d)) is $100,000 or less. This requires a written request from the contractor. The TCO may grant this authorization if—
(i) The TCO is satisfied with the adequacy of the procedures used by the contractor in settling settlement proposals, including proposals for keeping, selling, or otherwise disposing of termination inventory of the immediate and lower tier subcontractors. The TCO must obtain advice and recommendations from—
(A) The appropriate audit agency about the adequacy of the contractor's audit administration, including personnel; and
(B) The cognizant plant clearance officer about the adequacy of the contractor's procedures and personnel for handling property disposal matters;
(ii) Any termination inventory included in determining the settlement amount will be disposed of as directed by the prime contractor, except that disposing of the inventory will not be subject to-
(A) Review by the TCO under 49.108-3(c); or
(B) The screening requirements in 45.602-3; and
(iii) A certificate similar to the certificate in the settlement proposal form in 49.602-1(a) will accompany the settlement.
(2) Except as stated in paragraph (a)(4) of this section, authority granted to a prime contractor under paragraph (a)(1) of this section by any TCO must apply to all Executive agencies' prime contracts that are terminated or modified by change orders.
(3) Except as stated in paragraph (a)(4) of this section, the TCO must accept settlements of terminated lower tier subcontracts as part of the prime contractor's settlement proposal. This applies when the settlements are completed by any of the prime contractor's immediate or lower-tier subcontractors who have been granted authority as prime contractors to settle subcontracts, provided that the settlement is within the limit of the authority. Authorization to settle proposals of lower-tier subcontractors must not be granted directly to subcontractors. However, a prime contractor authorized to approve subcontractor settlements may also exercise this authority when acting as a subcontractor for its terminated subcontracts and orders. When exercising this authority as a subcontractor, the contractor must notify the purchaser.
(4) The provisions of paragraphs (a)(1), (2), and (3) of this section do not apply to contracts under the administration of any contracting officer if the contracting officer notifies the prime contractor concerned. This notice must—
(i) Be in writing; and
(ii) If paragraph (a)(3) of this section is involved, specify any subcontractor affected.
(b) Section 45.602 must apply to disposal of completed end items allocable to the terminated subcontract. However, these items may be disposed of without review by the TCO under 49.108-3 and without screening under 45.602-3, if the items do not require demilitarization and the total amount (at the subcontract price) when added to the settlement amount does not exceed the amount authorized under this section.
(c) A TCO granting the authorization in paragraph (a)(1) of this section must periodically (at least annually) make a selective review of settlements and settlement procedures. This review determines if the contractor is making adequate reviews and fair settlements, and whether the authorization should remain in effect. The TCO must obtain advice and recommendations from the appropriate audit agency and the cognizant plant clearance officer. The TCO must revoke the authorization by written notice to the contractor, effective on the date of receipt, when—
(1) The contractor's procedures are not adequate;
(2) Improper settlements are being made; or
(3) The authority has not been used in the preceding 2 years.
(d) The contractor may make any number of separate settlements with a single subcontractor but must not divide settlement proposals solely to bring them under an authorization limit. Separate settlement proposals that would normally be included in a single proposal, such as those based on a series of separate orders for the same item under one contract, must be consolidated whenever possible.
(e) Upon written request of the contractor, the TCO may increase an authorization granted under paragraph (a)(1) of this section to authorize the contractor to conclude settlements under a particular prime contract. The TCO may limit the increased authorization to specific subcontracts or classes of subcontracts.
(f) Authorizations granted under 49.108-4 do not authorize the settlement of requisitions or orders placed with any unit within the contractor's corporate entity.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 49.000 | Scope of part. | Scope of part. | Changed · 49% alike | 43 → 59 |
| 49.001 | Definitions. | Definitions. | Changed · 58% alike | 199 → 185 |
| 49.002 | Applicability. | Applicability. | Changed · 46% alike | 278 → 226 |
| 49.100 | Scope of subpart. | Scope of subpart. | Changed · 46% alike | 99 → 76 |
| 49.101 | Authorities and responsibilities. | Authorities and responsibilities. | Changed · 51% alike | 278 → 246 |
| 49.102 | Notice of termination. | Notice of termination. | Changed · 66% alike | 328 → 274 |
| 49.103 | Methods of settlement. | Methods of settlement. | Changed · 93% alike | 89 → 91 |
| 49.104 | Duties of prime contractor after receipt of notice of termination. | Duties of prime contractor after receipt of notice of termination. | Changed · 83% alike | 233 → 228 |
| 49.105 | Duties of termination contracting officer after issuance of notice of termination. | Duties of termination contracting officer after issuance of notice of termination. | Changed · 64% alike | 521 → 495 |
| 49.105-1 | Termination status reports. | Release of excess funds. | Changed · 17% alike | 34 → 107 |
| 49.105-2 | Release of excess funds. | Cleanup of construction site. | Changed · 8% alike | 138 → 33 |
| 49.105-3 | Termination case file. | none | Not in the overhaul | 34 → – |
| 49.105-4 | Cleanup of construction site. | none | Not in the overhaul | 38 → – |
| 49.106 | Fraud or other criminal conduct. | Fraud or other criminal conduct. | Same | 29 → 29 |
| 49.107 | Audit of prime contract settlement proposals and subcontract settlements. | Audit of prime contract settlement proposals and subcontract settlements. | Changed · 63% alike | 529 → 420 |
| 49.108 | Settlement of subcontract settlement proposals. | Settlement of subcontract settlement proposals. | Same | 0 → 0 |
| 49.108-1 | Subcontractor's rights. | Subcontractor’s rights. | Changed · 72% alike | 59 → 55 |
| 49.108-2 | Prime contractor's rights and obligations. | Prime contractor’s rights and obligations. | Changed · 57% alike | 196 → 146 |
| 49.108-3 | Settlement procedure. | Settlement procedure. | Changed · 69% alike | 301 → 275 |
| 49.108-4 | Authorization for subcontract settlements without approval or ratification. | Authorization for subcontract settlements without approval or ratification. | Changed · 82% alike | 755 → 742 |
| 49.108-5 | Recognition of judgments and arbitration awards. | Recognition of judgments and arbitration awards. | Changed · 77% alike | 300 → 275 |
| 49.108-6 | Delay in settling subcontractor settlement proposals. | Delay in settling subcontractor settlement proposals. | Changed · 83% alike | 58 → 51 |
| 49.108-7 | Government assistance in settling subcontracts. | Assignment of rights under subcontracts. | Changed · 16% alike | 82 → 162 |
| 49.108-8 | Assignment of rights under subcontracts. | none | Not in the overhaul | 208 → – |
| 49.109 | Settlement agreements. | Settlement agreements. | Same | 0 → 0 |
| 49.109-1 | General. | General. | Changed · 91% alike | 80 → 79 |
| 49.109-2 | Reservations. | Reservations. | Changed · 90% alike | 120 → 112 |
| 49.109-3 | Government property. | Government property. | Changed · 75% alike | 60 → 60 |
| 49.109-4 | No-cost settlement. | No-cost settlement. | Changed · 94% alike | 54 → 52 |
| 49.109-5 | Partial settlements. | Partial settlements. | Changed · 68% alike | 109 → 88 |
| 49.109-6 | Joint settlement of two or more settlement proposals. | Joint settlement of two or more settlement proposals. | Changed · 83% alike | 147 → 134 |
| 49.109-7 | Settlement by determination. | Settlement by determination. | Changed · 94% alike | 599 → 595 |
| 49.110 | Settlement negotiation memorandum. | Settlement negotiation memorandum. | Changed · 91% alike | 153 → 147 |
| 49.111 | Review of proposed settlements. | Review of proposed settlements. | Changed · 85% alike | 37 → 36 |
| 49.112 | Payment. | Payment. | Same | 0 → 0 |
| 49.112-1 | Partial payments. | Partial payments. | Changed · 93% alike | 791 → 754 |
| 49.112-2 | Final payment. | Final payment. | Changed · 96% alike | 245 → 245 |
| 49.113 | Cost principles. | Unsettled contract changes. | Changed · 8% alike | 65 → 85 |
| 49.114 | Unsettled contract changes. | Settlement of terminated incentive contracts. | Changed · 7% alike | 80 → 346 |
| 49.115 | Settlement of terminated incentive contracts. | none | Not in the overhaul | 407 → – |
| 49.201 | General. | General. | Changed · 36% alike | 188 → 143 |
| 49.202 | Profit. | Profit. | Changed · 37% alike | 395 → 365 |
| 49.203 | Adjustment for loss. | Adjustment for loss. | Changed · 70% alike | 320 → 284 |
| 49.204 | Deductions. | Deductions. | Changed · 62% alike | 117 → 85 |
| 49.205 | Completed end items. | Completed end items. | Changed · 66% alike | 148 → 142 |
| 49.206 | Settlement proposals. | Settlement proposals. | Same | 0 → 0 |
| 49.206-1 | Submission of settlement proposals. | Submission of settlement proposals. | Changed · 67% alike | 380 → 333 |
| 49.206-2 | Bases for settlement proposals. | Bases for settlement proposals. | Changed · 78% alike | 539 → 493 |
| 49.206-3 | Submission of inventory disposal schedules. | Submission of inventory disposal schedules. | Changed · 53% alike | 81 → 50 |
| 49.207 | Limitation on settlements. | Limitation on settlements. | Changed · 82% alike | 38 → 40 |
| 49.208 | Equitable adjustment after partial termination. | Equitable adjustment after partial termination. | Changed · 76% alike | 125 → 124 |
| 49.301 | General. | General. | Changed · 38% alike | 30 → 18 |
| 49.302 | Discontinuance of vouchers. | Discontinuance of vouchers. | Changed · 75% alike | 154 → 127 |
| 49.303 | Procedure after discontinuing vouchers. | Procedure after discontinuing vouchers. | Same | 0 → 0 |
| 49.303-1 | Submission of settlement proposal. | Submission of settlement proposal. | Changed · 42% alike | 83 → 56 |
| 49.303-2 | Submission of inventory disposal schedules. | Submission of inventory disposal schedules. | Changed · 43% alike | 82 → 48 |
| 49.303-3 | Audit of settlement proposal. | Audit of settlement proposal. | Changed · 26% alike | 37 → 16 |
| 49.303-4 | Adjustment of indirect costs. | Adjustment of indirect costs. | Changed · 43% alike | 152 → 79 |
| 49.303-5 | Final settlement. | Final settlement. | Changed · 39% alike | 138 → 103 |
| 49.304 | Procedure for partial termination. | Procedure for partial termination. | Same | 0 → 0 |
| 49.304-1 | General. | General. | Changed · 63% alike | 106 → 74 |
| 49.304-2 | Submission of settlement proposal (fee only). | Submission of settlement proposal (fee only). | Changed · 57% alike | 72 → 51 |
| 49.304-3 | Submission of vouchers. | Submission of vouchers. | Changed · 63% alike | 58 → 47 |
| 49.305 | Adjustment of fee. | Adjustment of fee. | Same | 0 → 0 |
| 49.305-1 | General. | General. | Changed · 54% alike | 184 → 124 |
| 49.305-2 | Construction contracts. | Construction contracts. | Changed · 54% alike | 198 → 153 |
| 49.401 | General. | General. | Changed · 66% alike | 214 → 183 |
| 49.402 | Termination of fixed-price contracts for default. | Termination of fixed-price contracts for default. | Same | 0 → 0 |
| 49.402-1 | The Government's right. | The Government’s right. | Changed · 89% alike | 73 → 69 |
| 49.402-2 | Effect of termination for default. | Effect of termination for default. | Changed · 58% alike | 430 → 275 |
| 49.402-3 | Procedure for default. | Procedure for default. | Changed · 53% alike | 1216 → 875 |
| 49.402-4 | Procedure in lieu of termination for default. | Procedure in lieu of termination for default. | Changed · 53% alike | 128 → 103 |
| 49.402-5 | Memorandum by the contracting officer. | Memorandum by the contracting officer. | Changed · 79% alike | 34 → 34 |
| 49.402-6 | Repurchase against contractor's account. | Repurchase against contractor’s account. | Changed · 40% alike | 316 → 199 |
| 49.402-7 | Other damages. | Other damages. | Changed · 76% alike | 109 → 88 |
| 49.402-8 | Reporting information. | Reporting information. | Changed · 54% alike | 39 → 39 |
| 49.403 | Termination of cost-reimbursement contracts for default. | Termination of cost-reimbursement contracts for default. | Changed · 68% alike | 198 → 155 |
| 49.404 | Surety-takeover agreements. | Surety-takeover agreements. | Changed · 61% alike | 493 → 353 |
| 49.405 | Completion by another contractor. | Liquidation of liability. | Changed · 20% alike | 67 → 61 |
| 49.406 | Liquidation of liability. | none | Not in the overhaul | 82 → – |
| 49.501 | General. | General. | Changed · 91% alike | 52 → 53 |
| 49.502 | Termination for convenience of the Government. | Termination for convenience of the Government. | Changed · 84% alike | 865 → 840 |
| 49.503 | Termination for convenience of the Government and default. | Termination for convenience of the Government and default. | Changed · 86% alike | 303 → 291 |
| 49.504 | Termination of fixed-price contracts for default. | Termination of fixed-price contracts for default. | Changed · 92% alike | 352 → 311 |
| 49.505 | Other termination clauses. | Other termination clauses. | Changed · 66% alike | 135 → 88 |
| 49.601 | Notice of termination for convenience. | Notice of termination for convenience. | Same | 10 → 10 |
| 49.601-1 | Electronic notice. | Electronic notice. | Changed · 93% alike | 337 → 328 |
| 49.601-2 | Letter notice. | Letter notice. | Changed · 99% alike | 1137 → 1148 |
| 49.602 | Forms for settlement of terminated contracts. | Forms for settlement of terminated contracts. | Same | 40 → 40 |
| 49.602-1 | Termination settlement proposal forms. | Termination settlement proposal forms. | Same | 142 → 142 |
| 49.602-2 | Inventory forms. | Inventory forms. | Same | 34 → 34 |
| 49.602-3 | Schedule of accounting information. | Schedule of accounting information. | Same | 34 → 34 |
| 49.602-4 | Partial payments. | Partial payments. | Changed · 97% alike | 19 → 18 |
| 49.602-5 | Settlement agreement. | Settlement agreement. | Changed · 91% alike | 23 → 21 |
| 49.603 | Formats for termination for convenience settlement agreements. | Formats for termination for convenience settlement agreements. | Same | 54 → 54 |
| 49.603-1 | Fixed-price contracts—complete termination. | Fixed price contracts-complete termination. | Changed · 98% alike | 1135 → 1149 |
| 49.603-2 | Fixed-price contracts—partial termination. | Fixed-price contracts-partial termination. | Changed · 99% alike | 1058 → 1066 |
| 49.603-3 | Cost-reimbursement contracts—complete termination, if settlement includes cost. | Cost reimbursement contracts-complete termination, if settlement includes cost. | Changed · 98% alike | 1421 → 1437 |
| 49.603-4 | Cost-reimbursement contracts—complete termination, with settlement limited to fee. | Cost-reimbursement contracts-complete termination, with settlement limited to fee. | Changed · 99% alike | 623 → 628 |
| 49.603-5 | Cost-reimbursement contracts—partial termination. | Cost-reimbursement contracts-partial termination. | Changed · 99% alike | 188 → 186 |
| 49.603-6 | No-cost settlement agreement—complete termination. | No-cost settlement agreement-complete termination. | Same | 132 → 132 |
| 49.603-7 | No-cost settlement agreement—partial termination. | No-cost settlement agreement-partial termination. | Changed · 99% alike | 218 → 217 |
| 49.603-8 | Fixed-price contracts—settlements with subcontractors only. | Fixed-price contracts-settlements with subcontractors only. | Changed · 99% alike | 497 → 499 |
| 49.603-9 | Settlement of reservations. | Settlement of reservations. | Changed · 93% alike | 153 → 153 |
| 49.604 | Release of excess funds under terminated contracts. | Release of excess funds under terminated contracts. | Changed · 96% alike | 197 → 198 |
| 49.605 | Request to settle subcontractor settlement proposals. | Request to settle subcontractor settlement proposals. | Changed · 96% alike | 204 → 204 |
| 49.606 | Granting subcontract settlement authorization. | Granting subcontract settlement authorization. | Changed · 100% alike | 574 → 574 |
| 49.607 | Delinquency notices. | Delinquency notices. | Changed · 99% alike | 479 → 480 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress