The FAR overhaul, side by side
FAR Part 49: Termination of Contracts
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 108 sections, 25,216 words (Part 49 as in force, eCFR as of Oct 29, 2026). Overhaul text: 103 sections, 22,632 words (on acquisition.gov ↗, issued Aug 21, 2025). By number: 16 the same, 87 changed, 5 not in the overhaul, 0 new.
49.203: Changed (70% alike)
Today: Adjustment for loss.
(a) In the negotiation or determination of any settlement, the TCO shall not allow profit if it appears that the contractor would have incurred a loss had the entire contract been completed. The TCO shall negotiate or determine the amount of loss and make an adjustment in the amount of settlement as specified in paragraph (b) or (c) below. In estimating the cost to complete, the TCO shall consider expected production efficiencies and other factors affecting the cost to complete.
(b) If the settlement is on an inventory basis (see 49.206-2(a)), the contractor shall not be paid more than the total of the amounts in subparagraphs (1), (2), and (3) below, less all disposal credits and all unliquidated advance and progress payments previously made under the contract:
(1) The amount negotiated or determined for settlement expenses.
(2) The contract price, as adjusted, for acceptable completed end items (see 49.205).
(3) The remainder of the settlement amount otherwise agreed upon or determined (including the allocable portion of initial costs (see 31.205-42(c)), reduced by multiplying the remainder by the ratio of (i) the total contract price to (ii) the total cost incurred before termination plus the estimated cost to complete the entire contract.
(c) If the settlement is on a total cost basis (see 49.206-2(b)), the contractor shall not be paid more than the total of the amounts in subparagraphs (1) and (2) below, less all disposal and other credits, all advance and progress payments, and all other amounts previously paid under the contract:
(1) The amount negotiated or determined for settlement expenses.
(2) The remainder of the total settlement amount otherwise agreed upon or determined (lines 7 and 14 of SF 1436, Settlement Proposal (Total Cost Basis)) reduced by multiplying the remainder by the ratio of (i) the total contract price to (ii) the remainder plus the estimated cost to complete the entire contract.
Overhaul text: Adjustment for loss.
(a) When settling a terminated contract, the TCO must not allow profit if the contractor would have lost money completing the full contract. The TCO must—
(1) Figure out how much the contractor would have lost;
(2) Adjust the settlement payment accordingly using the methods in paragraph (b) or (c) of this section; and
(3) Consider factors like production efficiency when estimating completion costs.
(b) For inventory-based settlements payment is limited to the sum of items in paragraphs (b)(1), (2), and (3) of this section, minus all disposal credits and minus all unliquidated previous advance and progress payments previously made—
(1) The settlement expenses.
(2) The contract price for acceptable completed items.
(3) The remainder of the settlement amount otherwise agreed upon or determined (including the allocable portion of initial costs (see part 31), reduced by multiplying the remainder by the ratio of (i) the total contract price to (ii) the total cost incurred before termination plus the estimated cost to complete the entire contract.
(c) If the settlement is on a total cost basis (see 49.206-2(b)), the contractor must not be paid more than the total of the amounts in paragraphs (c)(1) and (2) of this section, minus all disposal and other credits, all advanced and progress payments, and all other amounts previously paid under the contract—
(1) The amount negotiated or determined for settlement expenses.
(2) The remainder of the total settlement amount otherwise agreed upon or determined (lines 7 and 14 of SF 1436, Settlement Proposal (Total Cost Basis)) reduced by multiplying the remainder by the ratio of (i) the total contract price to (ii) the remainder plus the estimated cost to complete the entire contract.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 49.000 | Scope of part. | Scope of part. | Changed · 49% alike | 43 → 59 |
| 49.001 | Definitions. | Definitions. | Changed · 58% alike | 199 → 185 |
| 49.002 | Applicability. | Applicability. | Changed · 46% alike | 278 → 226 |
| 49.100 | Scope of subpart. | Scope of subpart. | Changed · 46% alike | 99 → 76 |
| 49.101 | Authorities and responsibilities. | Authorities and responsibilities. | Changed · 51% alike | 278 → 246 |
| 49.102 | Notice of termination. | Notice of termination. | Changed · 66% alike | 328 → 274 |
| 49.103 | Methods of settlement. | Methods of settlement. | Changed · 93% alike | 89 → 91 |
| 49.104 | Duties of prime contractor after receipt of notice of termination. | Duties of prime contractor after receipt of notice of termination. | Changed · 83% alike | 233 → 228 |
| 49.105 | Duties of termination contracting officer after issuance of notice of termination. | Duties of termination contracting officer after issuance of notice of termination. | Changed · 64% alike | 521 → 495 |
| 49.105-1 | Termination status reports. | Release of excess funds. | Changed · 17% alike | 34 → 107 |
| 49.105-2 | Release of excess funds. | Cleanup of construction site. | Changed · 8% alike | 138 → 33 |
| 49.105-3 | Termination case file. | none | Not in the overhaul | 34 → – |
| 49.105-4 | Cleanup of construction site. | none | Not in the overhaul | 38 → – |
| 49.106 | Fraud or other criminal conduct. | Fraud or other criminal conduct. | Same | 29 → 29 |
| 49.107 | Audit of prime contract settlement proposals and subcontract settlements. | Audit of prime contract settlement proposals and subcontract settlements. | Changed · 63% alike | 529 → 420 |
| 49.108 | Settlement of subcontract settlement proposals. | Settlement of subcontract settlement proposals. | Same | 0 → 0 |
| 49.108-1 | Subcontractor's rights. | Subcontractor’s rights. | Changed · 72% alike | 59 → 55 |
| 49.108-2 | Prime contractor's rights and obligations. | Prime contractor’s rights and obligations. | Changed · 57% alike | 196 → 146 |
| 49.108-3 | Settlement procedure. | Settlement procedure. | Changed · 69% alike | 301 → 275 |
| 49.108-4 | Authorization for subcontract settlements without approval or ratification. | Authorization for subcontract settlements without approval or ratification. | Changed · 82% alike | 755 → 742 |
| 49.108-5 | Recognition of judgments and arbitration awards. | Recognition of judgments and arbitration awards. | Changed · 77% alike | 300 → 275 |
| 49.108-6 | Delay in settling subcontractor settlement proposals. | Delay in settling subcontractor settlement proposals. | Changed · 83% alike | 58 → 51 |
| 49.108-7 | Government assistance in settling subcontracts. | Assignment of rights under subcontracts. | Changed · 16% alike | 82 → 162 |
| 49.108-8 | Assignment of rights under subcontracts. | none | Not in the overhaul | 208 → – |
| 49.109 | Settlement agreements. | Settlement agreements. | Same | 0 → 0 |
| 49.109-1 | General. | General. | Changed · 91% alike | 80 → 79 |
| 49.109-2 | Reservations. | Reservations. | Changed · 90% alike | 120 → 112 |
| 49.109-3 | Government property. | Government property. | Changed · 75% alike | 60 → 60 |
| 49.109-4 | No-cost settlement. | No-cost settlement. | Changed · 94% alike | 54 → 52 |
| 49.109-5 | Partial settlements. | Partial settlements. | Changed · 68% alike | 109 → 88 |
| 49.109-6 | Joint settlement of two or more settlement proposals. | Joint settlement of two or more settlement proposals. | Changed · 83% alike | 147 → 134 |
| 49.109-7 | Settlement by determination. | Settlement by determination. | Changed · 94% alike | 599 → 595 |
| 49.110 | Settlement negotiation memorandum. | Settlement negotiation memorandum. | Changed · 91% alike | 153 → 147 |
| 49.111 | Review of proposed settlements. | Review of proposed settlements. | Changed · 85% alike | 37 → 36 |
| 49.112 | Payment. | Payment. | Same | 0 → 0 |
| 49.112-1 | Partial payments. | Partial payments. | Changed · 93% alike | 791 → 754 |
| 49.112-2 | Final payment. | Final payment. | Changed · 96% alike | 245 → 245 |
| 49.113 | Cost principles. | Unsettled contract changes. | Changed · 8% alike | 65 → 85 |
| 49.114 | Unsettled contract changes. | Settlement of terminated incentive contracts. | Changed · 7% alike | 80 → 346 |
| 49.115 | Settlement of terminated incentive contracts. | none | Not in the overhaul | 407 → – |
| 49.201 | General. | General. | Changed · 36% alike | 188 → 143 |
| 49.202 | Profit. | Profit. | Changed · 37% alike | 395 → 365 |
| 49.203 | Adjustment for loss. | Adjustment for loss. | Changed · 70% alike | 320 → 284 |
| 49.204 | Deductions. | Deductions. | Changed · 62% alike | 117 → 85 |
| 49.205 | Completed end items. | Completed end items. | Changed · 66% alike | 148 → 142 |
| 49.206 | Settlement proposals. | Settlement proposals. | Same | 0 → 0 |
| 49.206-1 | Submission of settlement proposals. | Submission of settlement proposals. | Changed · 67% alike | 380 → 333 |
| 49.206-2 | Bases for settlement proposals. | Bases for settlement proposals. | Changed · 78% alike | 539 → 493 |
| 49.206-3 | Submission of inventory disposal schedules. | Submission of inventory disposal schedules. | Changed · 53% alike | 81 → 50 |
| 49.207 | Limitation on settlements. | Limitation on settlements. | Changed · 82% alike | 38 → 40 |
| 49.208 | Equitable adjustment after partial termination. | Equitable adjustment after partial termination. | Changed · 76% alike | 125 → 124 |
| 49.301 | General. | General. | Changed · 38% alike | 30 → 18 |
| 49.302 | Discontinuance of vouchers. | Discontinuance of vouchers. | Changed · 75% alike | 154 → 127 |
| 49.303 | Procedure after discontinuing vouchers. | Procedure after discontinuing vouchers. | Same | 0 → 0 |
| 49.303-1 | Submission of settlement proposal. | Submission of settlement proposal. | Changed · 42% alike | 83 → 56 |
| 49.303-2 | Submission of inventory disposal schedules. | Submission of inventory disposal schedules. | Changed · 43% alike | 82 → 48 |
| 49.303-3 | Audit of settlement proposal. | Audit of settlement proposal. | Changed · 26% alike | 37 → 16 |
| 49.303-4 | Adjustment of indirect costs. | Adjustment of indirect costs. | Changed · 43% alike | 152 → 79 |
| 49.303-5 | Final settlement. | Final settlement. | Changed · 39% alike | 138 → 103 |
| 49.304 | Procedure for partial termination. | Procedure for partial termination. | Same | 0 → 0 |
| 49.304-1 | General. | General. | Changed · 63% alike | 106 → 74 |
| 49.304-2 | Submission of settlement proposal (fee only). | Submission of settlement proposal (fee only). | Changed · 57% alike | 72 → 51 |
| 49.304-3 | Submission of vouchers. | Submission of vouchers. | Changed · 63% alike | 58 → 47 |
| 49.305 | Adjustment of fee. | Adjustment of fee. | Same | 0 → 0 |
| 49.305-1 | General. | General. | Changed · 54% alike | 184 → 124 |
| 49.305-2 | Construction contracts. | Construction contracts. | Changed · 54% alike | 198 → 153 |
| 49.401 | General. | General. | Changed · 66% alike | 214 → 183 |
| 49.402 | Termination of fixed-price contracts for default. | Termination of fixed-price contracts for default. | Same | 0 → 0 |
| 49.402-1 | The Government's right. | The Government’s right. | Changed · 89% alike | 73 → 69 |
| 49.402-2 | Effect of termination for default. | Effect of termination for default. | Changed · 58% alike | 430 → 275 |
| 49.402-3 | Procedure for default. | Procedure for default. | Changed · 53% alike | 1216 → 875 |
| 49.402-4 | Procedure in lieu of termination for default. | Procedure in lieu of termination for default. | Changed · 53% alike | 128 → 103 |
| 49.402-5 | Memorandum by the contracting officer. | Memorandum by the contracting officer. | Changed · 79% alike | 34 → 34 |
| 49.402-6 | Repurchase against contractor's account. | Repurchase against contractor’s account. | Changed · 40% alike | 316 → 199 |
| 49.402-7 | Other damages. | Other damages. | Changed · 76% alike | 109 → 88 |
| 49.402-8 | Reporting information. | Reporting information. | Changed · 54% alike | 39 → 39 |
| 49.403 | Termination of cost-reimbursement contracts for default. | Termination of cost-reimbursement contracts for default. | Changed · 68% alike | 198 → 155 |
| 49.404 | Surety-takeover agreements. | Surety-takeover agreements. | Changed · 61% alike | 493 → 353 |
| 49.405 | Completion by another contractor. | Liquidation of liability. | Changed · 20% alike | 67 → 61 |
| 49.406 | Liquidation of liability. | none | Not in the overhaul | 82 → – |
| 49.501 | General. | General. | Changed · 91% alike | 52 → 53 |
| 49.502 | Termination for convenience of the Government. | Termination for convenience of the Government. | Changed · 84% alike | 865 → 840 |
| 49.503 | Termination for convenience of the Government and default. | Termination for convenience of the Government and default. | Changed · 86% alike | 303 → 291 |
| 49.504 | Termination of fixed-price contracts for default. | Termination of fixed-price contracts for default. | Changed · 92% alike | 352 → 311 |
| 49.505 | Other termination clauses. | Other termination clauses. | Changed · 66% alike | 135 → 88 |
| 49.601 | Notice of termination for convenience. | Notice of termination for convenience. | Same | 10 → 10 |
| 49.601-1 | Electronic notice. | Electronic notice. | Changed · 93% alike | 337 → 328 |
| 49.601-2 | Letter notice. | Letter notice. | Changed · 99% alike | 1137 → 1148 |
| 49.602 | Forms for settlement of terminated contracts. | Forms for settlement of terminated contracts. | Same | 40 → 40 |
| 49.602-1 | Termination settlement proposal forms. | Termination settlement proposal forms. | Same | 142 → 142 |
| 49.602-2 | Inventory forms. | Inventory forms. | Same | 34 → 34 |
| 49.602-3 | Schedule of accounting information. | Schedule of accounting information. | Same | 34 → 34 |
| 49.602-4 | Partial payments. | Partial payments. | Changed · 97% alike | 19 → 18 |
| 49.602-5 | Settlement agreement. | Settlement agreement. | Changed · 91% alike | 23 → 21 |
| 49.603 | Formats for termination for convenience settlement agreements. | Formats for termination for convenience settlement agreements. | Same | 54 → 54 |
| 49.603-1 | Fixed-price contracts—complete termination. | Fixed price contracts-complete termination. | Changed · 98% alike | 1135 → 1149 |
| 49.603-2 | Fixed-price contracts—partial termination. | Fixed-price contracts-partial termination. | Changed · 99% alike | 1058 → 1066 |
| 49.603-3 | Cost-reimbursement contracts—complete termination, if settlement includes cost. | Cost reimbursement contracts-complete termination, if settlement includes cost. | Changed · 98% alike | 1421 → 1437 |
| 49.603-4 | Cost-reimbursement contracts—complete termination, with settlement limited to fee. | Cost-reimbursement contracts-complete termination, with settlement limited to fee. | Changed · 99% alike | 623 → 628 |
| 49.603-5 | Cost-reimbursement contracts—partial termination. | Cost-reimbursement contracts-partial termination. | Changed · 99% alike | 188 → 186 |
| 49.603-6 | No-cost settlement agreement—complete termination. | No-cost settlement agreement-complete termination. | Same | 132 → 132 |
| 49.603-7 | No-cost settlement agreement—partial termination. | No-cost settlement agreement-partial termination. | Changed · 99% alike | 218 → 217 |
| 49.603-8 | Fixed-price contracts—settlements with subcontractors only. | Fixed-price contracts-settlements with subcontractors only. | Changed · 99% alike | 497 → 499 |
| 49.603-9 | Settlement of reservations. | Settlement of reservations. | Changed · 93% alike | 153 → 153 |
| 49.604 | Release of excess funds under terminated contracts. | Release of excess funds under terminated contracts. | Changed · 96% alike | 197 → 198 |
| 49.605 | Request to settle subcontractor settlement proposals. | Request to settle subcontractor settlement proposals. | Changed · 96% alike | 204 → 204 |
| 49.606 | Granting subcontract settlement authorization. | Granting subcontract settlement authorization. | Changed · 100% alike | 574 → 574 |
| 49.607 | Delinquency notices. | Delinquency notices. | Changed · 99% alike | 479 → 480 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress