The FAR overhaul, side by side
FAR Part 49: Termination of Contracts
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 108 sections, 25,216 words (Part 49 as in force, eCFR as of Oct 29, 2026). Overhaul text: 103 sections, 22,632 words (on acquisition.gov ↗, issued Aug 21, 2025). By number: 16 the same, 87 changed, 5 not in the overhaul, 0 new.
49.305-2: Changed (54% alike)
Today: Construction contracts.
(a) The percentage of completion basis refers to the contractor's total effort and not solely to the actual construction work. Generally, the effort of a contractor under a cost-reimbursement construction or professional services contract can be segregated into factors such as (1) mobilization including organization, (2) use of finances, (3) contracting for and receipt of materials, (4) placement of subcontracts, (5) preparation of shop drawings, (6) work in place performed by own forces, (7) supervision of subcontractors' work (8) job administration, and (9) demobilization.
(b) Each of the applicable factors in paragraph (a) above shall be assigned a weighted value depending on its importance and difficulty. The total weight value of all factors should be easily divisible (e.g., by 100) to determine percentages. The percentage of completion of each factor must be established based upon the specific facts of each contract. When totaled, the percentage of completion of each factor applied to the weighted value of each factor results in the overall percentage of contract completion. The percentage of completion is then applied to the total contract fee or to the fee applicable to the terminated portion of the contract to arrive at an equitable adjustment.
Overhaul text: Construction contracts.
(a) The percentage of completion basis includes all contractor effort, not just the actual construction work. It includes such factors as—
(1) Mobilization including organization;
(2) Use of finances;
(3) Ordering and receiving materials;
(4) Placing subcontracts;
(5) Creating shop drawings;
(6) Performing work in place by own personnel;
(7) Supervising subcontractors;
(8) Managing the job; and
(9) Closing down the project;
(b) Calculate the fee adjustment as follows:
(1) Assign a weighted value to each factor based on importance and difficulty.
(2) The total weighted value should be easily divisible (e.g., by 100) to determine percentages.
(3) Determine the percentage complete of each factor based on specific facts of each contract.
(4) Multiply the completion percentage by the importance value for each factor.
(5) Add these values for overall completion percentage.
(6) Apply this percentage to the total fee applicable to the terminated portion of the contract to calculate the equitable adjustment.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 49.000 | Scope of part. | Scope of part. | Changed · 49% alike | 43 → 59 |
| 49.001 | Definitions. | Definitions. | Changed · 58% alike | 199 → 185 |
| 49.002 | Applicability. | Applicability. | Changed · 46% alike | 278 → 226 |
| 49.100 | Scope of subpart. | Scope of subpart. | Changed · 46% alike | 99 → 76 |
| 49.101 | Authorities and responsibilities. | Authorities and responsibilities. | Changed · 51% alike | 278 → 246 |
| 49.102 | Notice of termination. | Notice of termination. | Changed · 66% alike | 328 → 274 |
| 49.103 | Methods of settlement. | Methods of settlement. | Changed · 93% alike | 89 → 91 |
| 49.104 | Duties of prime contractor after receipt of notice of termination. | Duties of prime contractor after receipt of notice of termination. | Changed · 83% alike | 233 → 228 |
| 49.105 | Duties of termination contracting officer after issuance of notice of termination. | Duties of termination contracting officer after issuance of notice of termination. | Changed · 64% alike | 521 → 495 |
| 49.105-1 | Termination status reports. | Release of excess funds. | Changed · 17% alike | 34 → 107 |
| 49.105-2 | Release of excess funds. | Cleanup of construction site. | Changed · 8% alike | 138 → 33 |
| 49.105-3 | Termination case file. | none | Not in the overhaul | 34 → – |
| 49.105-4 | Cleanup of construction site. | none | Not in the overhaul | 38 → – |
| 49.106 | Fraud or other criminal conduct. | Fraud or other criminal conduct. | Same | 29 → 29 |
| 49.107 | Audit of prime contract settlement proposals and subcontract settlements. | Audit of prime contract settlement proposals and subcontract settlements. | Changed · 63% alike | 529 → 420 |
| 49.108 | Settlement of subcontract settlement proposals. | Settlement of subcontract settlement proposals. | Same | 0 → 0 |
| 49.108-1 | Subcontractor's rights. | Subcontractor’s rights. | Changed · 72% alike | 59 → 55 |
| 49.108-2 | Prime contractor's rights and obligations. | Prime contractor’s rights and obligations. | Changed · 57% alike | 196 → 146 |
| 49.108-3 | Settlement procedure. | Settlement procedure. | Changed · 69% alike | 301 → 275 |
| 49.108-4 | Authorization for subcontract settlements without approval or ratification. | Authorization for subcontract settlements without approval or ratification. | Changed · 82% alike | 755 → 742 |
| 49.108-5 | Recognition of judgments and arbitration awards. | Recognition of judgments and arbitration awards. | Changed · 77% alike | 300 → 275 |
| 49.108-6 | Delay in settling subcontractor settlement proposals. | Delay in settling subcontractor settlement proposals. | Changed · 83% alike | 58 → 51 |
| 49.108-7 | Government assistance in settling subcontracts. | Assignment of rights under subcontracts. | Changed · 16% alike | 82 → 162 |
| 49.108-8 | Assignment of rights under subcontracts. | none | Not in the overhaul | 208 → – |
| 49.109 | Settlement agreements. | Settlement agreements. | Same | 0 → 0 |
| 49.109-1 | General. | General. | Changed · 91% alike | 80 → 79 |
| 49.109-2 | Reservations. | Reservations. | Changed · 90% alike | 120 → 112 |
| 49.109-3 | Government property. | Government property. | Changed · 75% alike | 60 → 60 |
| 49.109-4 | No-cost settlement. | No-cost settlement. | Changed · 94% alike | 54 → 52 |
| 49.109-5 | Partial settlements. | Partial settlements. | Changed · 68% alike | 109 → 88 |
| 49.109-6 | Joint settlement of two or more settlement proposals. | Joint settlement of two or more settlement proposals. | Changed · 83% alike | 147 → 134 |
| 49.109-7 | Settlement by determination. | Settlement by determination. | Changed · 94% alike | 599 → 595 |
| 49.110 | Settlement negotiation memorandum. | Settlement negotiation memorandum. | Changed · 91% alike | 153 → 147 |
| 49.111 | Review of proposed settlements. | Review of proposed settlements. | Changed · 85% alike | 37 → 36 |
| 49.112 | Payment. | Payment. | Same | 0 → 0 |
| 49.112-1 | Partial payments. | Partial payments. | Changed · 93% alike | 791 → 754 |
| 49.112-2 | Final payment. | Final payment. | Changed · 96% alike | 245 → 245 |
| 49.113 | Cost principles. | Unsettled contract changes. | Changed · 8% alike | 65 → 85 |
| 49.114 | Unsettled contract changes. | Settlement of terminated incentive contracts. | Changed · 7% alike | 80 → 346 |
| 49.115 | Settlement of terminated incentive contracts. | none | Not in the overhaul | 407 → – |
| 49.201 | General. | General. | Changed · 36% alike | 188 → 143 |
| 49.202 | Profit. | Profit. | Changed · 37% alike | 395 → 365 |
| 49.203 | Adjustment for loss. | Adjustment for loss. | Changed · 70% alike | 320 → 284 |
| 49.204 | Deductions. | Deductions. | Changed · 62% alike | 117 → 85 |
| 49.205 | Completed end items. | Completed end items. | Changed · 66% alike | 148 → 142 |
| 49.206 | Settlement proposals. | Settlement proposals. | Same | 0 → 0 |
| 49.206-1 | Submission of settlement proposals. | Submission of settlement proposals. | Changed · 67% alike | 380 → 333 |
| 49.206-2 | Bases for settlement proposals. | Bases for settlement proposals. | Changed · 78% alike | 539 → 493 |
| 49.206-3 | Submission of inventory disposal schedules. | Submission of inventory disposal schedules. | Changed · 53% alike | 81 → 50 |
| 49.207 | Limitation on settlements. | Limitation on settlements. | Changed · 82% alike | 38 → 40 |
| 49.208 | Equitable adjustment after partial termination. | Equitable adjustment after partial termination. | Changed · 76% alike | 125 → 124 |
| 49.301 | General. | General. | Changed · 38% alike | 30 → 18 |
| 49.302 | Discontinuance of vouchers. | Discontinuance of vouchers. | Changed · 75% alike | 154 → 127 |
| 49.303 | Procedure after discontinuing vouchers. | Procedure after discontinuing vouchers. | Same | 0 → 0 |
| 49.303-1 | Submission of settlement proposal. | Submission of settlement proposal. | Changed · 42% alike | 83 → 56 |
| 49.303-2 | Submission of inventory disposal schedules. | Submission of inventory disposal schedules. | Changed · 43% alike | 82 → 48 |
| 49.303-3 | Audit of settlement proposal. | Audit of settlement proposal. | Changed · 26% alike | 37 → 16 |
| 49.303-4 | Adjustment of indirect costs. | Adjustment of indirect costs. | Changed · 43% alike | 152 → 79 |
| 49.303-5 | Final settlement. | Final settlement. | Changed · 39% alike | 138 → 103 |
| 49.304 | Procedure for partial termination. | Procedure for partial termination. | Same | 0 → 0 |
| 49.304-1 | General. | General. | Changed · 63% alike | 106 → 74 |
| 49.304-2 | Submission of settlement proposal (fee only). | Submission of settlement proposal (fee only). | Changed · 57% alike | 72 → 51 |
| 49.304-3 | Submission of vouchers. | Submission of vouchers. | Changed · 63% alike | 58 → 47 |
| 49.305 | Adjustment of fee. | Adjustment of fee. | Same | 0 → 0 |
| 49.305-1 | General. | General. | Changed · 54% alike | 184 → 124 |
| 49.305-2 | Construction contracts. | Construction contracts. | Changed · 54% alike | 198 → 153 |
| 49.401 | General. | General. | Changed · 66% alike | 214 → 183 |
| 49.402 | Termination of fixed-price contracts for default. | Termination of fixed-price contracts for default. | Same | 0 → 0 |
| 49.402-1 | The Government's right. | The Government’s right. | Changed · 89% alike | 73 → 69 |
| 49.402-2 | Effect of termination for default. | Effect of termination for default. | Changed · 58% alike | 430 → 275 |
| 49.402-3 | Procedure for default. | Procedure for default. | Changed · 53% alike | 1216 → 875 |
| 49.402-4 | Procedure in lieu of termination for default. | Procedure in lieu of termination for default. | Changed · 53% alike | 128 → 103 |
| 49.402-5 | Memorandum by the contracting officer. | Memorandum by the contracting officer. | Changed · 79% alike | 34 → 34 |
| 49.402-6 | Repurchase against contractor's account. | Repurchase against contractor’s account. | Changed · 40% alike | 316 → 199 |
| 49.402-7 | Other damages. | Other damages. | Changed · 76% alike | 109 → 88 |
| 49.402-8 | Reporting information. | Reporting information. | Changed · 54% alike | 39 → 39 |
| 49.403 | Termination of cost-reimbursement contracts for default. | Termination of cost-reimbursement contracts for default. | Changed · 68% alike | 198 → 155 |
| 49.404 | Surety-takeover agreements. | Surety-takeover agreements. | Changed · 61% alike | 493 → 353 |
| 49.405 | Completion by another contractor. | Liquidation of liability. | Changed · 20% alike | 67 → 61 |
| 49.406 | Liquidation of liability. | none | Not in the overhaul | 82 → – |
| 49.501 | General. | General. | Changed · 91% alike | 52 → 53 |
| 49.502 | Termination for convenience of the Government. | Termination for convenience of the Government. | Changed · 84% alike | 865 → 840 |
| 49.503 | Termination for convenience of the Government and default. | Termination for convenience of the Government and default. | Changed · 86% alike | 303 → 291 |
| 49.504 | Termination of fixed-price contracts for default. | Termination of fixed-price contracts for default. | Changed · 92% alike | 352 → 311 |
| 49.505 | Other termination clauses. | Other termination clauses. | Changed · 66% alike | 135 → 88 |
| 49.601 | Notice of termination for convenience. | Notice of termination for convenience. | Same | 10 → 10 |
| 49.601-1 | Electronic notice. | Electronic notice. | Changed · 93% alike | 337 → 328 |
| 49.601-2 | Letter notice. | Letter notice. | Changed · 99% alike | 1137 → 1148 |
| 49.602 | Forms for settlement of terminated contracts. | Forms for settlement of terminated contracts. | Same | 40 → 40 |
| 49.602-1 | Termination settlement proposal forms. | Termination settlement proposal forms. | Same | 142 → 142 |
| 49.602-2 | Inventory forms. | Inventory forms. | Same | 34 → 34 |
| 49.602-3 | Schedule of accounting information. | Schedule of accounting information. | Same | 34 → 34 |
| 49.602-4 | Partial payments. | Partial payments. | Changed · 97% alike | 19 → 18 |
| 49.602-5 | Settlement agreement. | Settlement agreement. | Changed · 91% alike | 23 → 21 |
| 49.603 | Formats for termination for convenience settlement agreements. | Formats for termination for convenience settlement agreements. | Same | 54 → 54 |
| 49.603-1 | Fixed-price contracts—complete termination. | Fixed price contracts-complete termination. | Changed · 98% alike | 1135 → 1149 |
| 49.603-2 | Fixed-price contracts—partial termination. | Fixed-price contracts-partial termination. | Changed · 99% alike | 1058 → 1066 |
| 49.603-3 | Cost-reimbursement contracts—complete termination, if settlement includes cost. | Cost reimbursement contracts-complete termination, if settlement includes cost. | Changed · 98% alike | 1421 → 1437 |
| 49.603-4 | Cost-reimbursement contracts—complete termination, with settlement limited to fee. | Cost-reimbursement contracts-complete termination, with settlement limited to fee. | Changed · 99% alike | 623 → 628 |
| 49.603-5 | Cost-reimbursement contracts—partial termination. | Cost-reimbursement contracts-partial termination. | Changed · 99% alike | 188 → 186 |
| 49.603-6 | No-cost settlement agreement—complete termination. | No-cost settlement agreement-complete termination. | Same | 132 → 132 |
| 49.603-7 | No-cost settlement agreement—partial termination. | No-cost settlement agreement-partial termination. | Changed · 99% alike | 218 → 217 |
| 49.603-8 | Fixed-price contracts—settlements with subcontractors only. | Fixed-price contracts-settlements with subcontractors only. | Changed · 99% alike | 497 → 499 |
| 49.603-9 | Settlement of reservations. | Settlement of reservations. | Changed · 93% alike | 153 → 153 |
| 49.604 | Release of excess funds under terminated contracts. | Release of excess funds under terminated contracts. | Changed · 96% alike | 197 → 198 |
| 49.605 | Request to settle subcontractor settlement proposals. | Request to settle subcontractor settlement proposals. | Changed · 96% alike | 204 → 204 |
| 49.606 | Granting subcontract settlement authorization. | Granting subcontract settlement authorization. | Changed · 100% alike | 574 → 574 |
| 49.607 | Delinquency notices. | Delinquency notices. | Changed · 99% alike | 479 → 480 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress