FAR Part 49: Termination of Contracts

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 108 sections, 25,216 words (Part 49 as in force, eCFR as of Oct 29, 2026). Overhaul text: 103 sections, 22,632 words (on acquisition.gov ↗, issued Aug 21, 2025). By number: 16 the same, 87 changed, 5 not in the overhaul, 0 new.

49.402-3: Changed (53% alike)

Today: Procedure for default.

This section in plain English

(a) When a default termination is being considered, the Government shall decide which type of termination action to take (i.e., default, convenience, or no-cost cancellation) only after review by contracting and technical personnel, and by counsel, to ensure the propriety of the proposed action.

(b) The administrative contracting officer shall not issue a show cause notice or cure notice without the prior approval of the contracting office, which should be obtained by the most expeditious means.

(c) Subdivision (a)(1)(i) of the Default clause covers situations when the contractor has defaulted by failure to make delivery of the supplies or to perform the services within the specified time. In these situations, no notice of failure or of the possibility of termination for default is required to be sent to the contractor before the actual notice of termination (but see paragraph (e) below). However, if the Government has taken any action that might be construed as a waiver of the contract delivery or performance date, the contracting officer shall send a notice to the contractor setting a new date for the contractor to make delivery or complete performance. The notice shall reserve the Government's rights under the Default clause.

(d) Subdivisions (a)(1)(ii) and (a)(1)(iii) of the Default clause cover situations when the contractor fails to perform some of the other provisions of the contract (such as not furnishing a required performance bond) or so fails to make progress as to endanger performance of the contract. If the termination is predicated upon this type of failure, the contracting officer shall give the contractor written notice specifying the failure and providing a period of 10 days (or longer period as necessary) in which to cure the failure. When appropriate, this notice may be made a part of the notice described in subparagraph (e)(1) below. Upon expiration of the 10 days (or longer period), the contracting officer may issue a notice of termination for default unless it is determined that the failure to perform has been cured. A format for a cure notice is in 49.607.

(e)(1) If termination for default appears appropriate, the contracting officer should, if practicable, notify the contractor in writing of the possibility of the termination. This notice shall call the contractor's attention to the contractual liabilities if the contract is terminated for default, and request the contractor to show cause why the contract should not be terminated for default. The notice may further state that failure of the contractor to present an explanation may be taken as an admission that no valid explanation exists. When appropriate, the notice may invite the contractor to discuss the matter at a conference. A format for a show cause notice is in 49.607.

(2) When a termination for default appears imminent, the contracting officer shall provide a written notification to the surety. If the contractor is subsequently terminated for default, a copy of the notice of default shall be sent to the surety.

(3) If requested by the surety, and agreed to by the contractor and any assignees, arrangements may be made to have future checks mailed to the contractor in care of the surety. In this case, the contractor must forward a written request to the designated disbursing officer specifically directing a change in address for mailing checks.

(4) If the contractor is a small business firm, the contracting officer shall immediately provide a copy of any cure notice or show cause notice to the contracting office's small business specialist and the Small Business Administration Area Office nearest the contractor. The contracting officer should, whenever practicable, consult with the small business specialist before proceeding with a default termination (see also 49.402-4).

(f) The contracting officer shall consider the following factors in determining whether to terminate a contract for default:

(1) The terms of the contract and applicable laws and regulations.

(2) The specific failure of the contractor and the excuses for the failure.

(3) The availability of the supplies or services from other sources.

(4) The urgency of the need for the supplies or services and the period of time required to obtain them from other sources, as compared with the time delivery could be obtained from the delinquent contractor.

(5) The degree of essentiality of the contractor in the Government acquisition program and the effect of a termination for default upon the contractor's capability as a supplier under other contracts.

(6) The effect of a termination for default on the ability of the contractor to liquidate guaranteed loans, progress payments, or advance payments.

(7) Any other pertinent facts and circumstances.

(g) If, after compliance with the procedures in paragraphs (a) through (f) of this 49.402-3, the contracting officer determines that a termination for default is proper, the contracting officer shall issue a notice of termination stating—

(1) The contract number and date;

(2) The acts or omissions constituting the default;

(3) That the contractor's right to proceed further under the contract (or a specified portion of the contract) is terminated;

(4) That the supplies or services terminated may be purchased against the contractor's account, and that the contractor will be held liable for any excess costs;

(5) If the contracting officer has determined that the failure to perform is not excusable, that the notice of termination constitutes such decision, and that the contractor has the right to appeal such decision under the Disputes clause;

(6) That the Government reserves all rights and remedies provided by law or under the contract, in addition to charging excess costs; and

(7) That the notice constitutes a decision that the contractor is in default as specified and that the contractor has the right to appeal under the Disputes clause.

(h) The contracting officer shall make the same distribution of the termination notice as was made of the contract. A copy shall also be furnished to the contractor's surety, if any, when the notice is furnished to the contractor. The surety should be requested to advise if it desires to arrange for completion of the work. In addition, the contracting officer shall notify the disbursing officer to withhold further payments under the terminated contract, pending further advice, which should be furnished at the earliest practicable time.

(i) In the case of a construction contract, promptly after issuance of the termination notice, the contracting officer shall determine the manner in which the work is to be completed and whether the materials, appliances, and plant that are on the site will be needed.

(j) If the contracting officer determines before issuing the termination notice that the failure to perform is excusable, the contract shall not be terminated for default. If termination is in the Government's interest, the contracting officer may terminate the contract for the convenience of the Government.

(k) If the contracting officer has not been able to determine, before issuance of the notice of termination whether the contractor's failure to perform is excusable, the contracting officer shall make a written decision on that point as soon as practicable after issuance of the notice of termination. The decision shall be delivered promptly to the contractor with a notification that the contractor has the right to appeal as specified in the Disputes clause.

Overhaul text: Procedure for default.

On acquisition.gov ↗

(a) Before deciding on default termination, the Government must review the situation (i.e., default, convenience, or no-cost cancellation) with contracting and technical personnel, as well as legal counsel, to ensure the action is appropriate.

(b) The administrative contracting officer must get prior approval from the contracting office before issuing a show cause notice or cure notice. This approval should be obtained quickly.

(c) When the contractor fails to deliver supplies or perform services within the specified time (Default clause paragraph (a)(1)), no advance notice of termination is required. However, if the Government has taken actions that might suggest it waived the contract deadlines, the contracting officer must send a notice setting a new deadline. This notice must state that the Government reserves its rights under the Default clause.

(d) For failures covered under Default clause paragraph (a)(1) - such as not providing a required performance bond or endangering contract performance - the contracting officer must-

(1) Give the contractor written notice specifying the failure;

(2) Allow 10 days (or longer if necessary) to cure the failure;

(3) When appropriate, include this notice in the show cause notice; and

(4) After the time period expires, decide whether to terminate the contract or accept the resolution.

(e) A sample cure notice format appears in 49.607.

(f) Show cause notice procedures are as follows:

(1) If default termination seems appropriate, the contracting officer should, when practical, notify the contractor in writing about-

(i) The possible termination;

(ii) The contractual liabilities involved;

(iii) Why the contract might be terminated;

(iv) The opportunity to explain why termination should not occur;

(v) That a lack of response may be taken as an admission by the contractor that no valid explanation exists; and

(vi) When appropriate, a suggested discussion.

(2) A sample show cause notice appears in 49.607.

(g)

(1) When default termination is likely, the contracting officer must notify the surety in writing. If the contractor is later terminated for default, the contracting officer must send the surety a copy of the default notice.

(2) If the surety requests it and the contractor and any assignees agree, arrangements can be made to send checks to the contractor through the surety. The contractor must submit a written request to the disbursing officer specifically directing this change in payment address.

(h) For small business contractors-

(1) The contracting officer must immediately send copies of any cure notice or show cause notice to the contracting office's small business specialist and Small Business Administration Area Office nearest the contractor;

(2) When possible, the contracting officer should consult with the small business specialist before proceeding with default termination.

(i) The contracting officer must consider these factors when deciding whether to terminate a contract for default:

(1) The contract terms and relevant laws and regulations.

(2) The specific failure and any explanations provided.

(3) Whether the supplies or services can be obtained from other sources.

(4) How urgently the items are needed and how long it would take to get them from other sources compared to the original contractor.

(5) How essential the contractor is to Government acquisition programs and how termination might affect their ability to supply other contracts.

(6) How termination might affect the contractor's ability to repay guaranteed loans, progress payments, or advance payments.

(7) Any other relevant facts and circumstances.

(j) After following procedures in paragraphs (a) through (i), if the contracting officer decides termination is proper, the contracting officer must issue a notice of termination stating-

(1) The contract number and date;

(2) What specific actions or failures constitute the default;

(3) That the contractor's right to proceed with the contract (or a specified portion) is terminated;

(4) That the Government may purchase similar supplies or services and charge any excess costs to the contractor;

(5) If the failure is determined not excusable, that the notice serves as this decision, and the contractor may appeal under the Disputes clause;

(6) That the Government reserves all other legal rights and remedies; and

(7) That this notice is a decision that the contractor is in default and has the right to appeal under the Disputes clause.

(k) The contracting officer must-

(1) Distribute the termination notice to all parties who received the original contract;

(2) Send a copy to the contractor's surety and ask if they want to arrange for completion of the work; and

(3) Tell the disbursing officer to stop payments under the terminated contract until further notice.

(l) For construction contracts, promptly after issuing the termination notice, the contracting officer must determine-

(1) How the work will be completed; and

(2) Whether materials, equipment, and plant that are on the site will be needed.

(m) If the contracting officer determines before issuing the termination notice that the failure was excusable, they must not terminate for default. If termination is still in the Government's interest, they may terminate for convenience.

(n) If the contracting officer cannot determine before issuing the notice whether the failure was excusable, they must-

(1) Make a written decision on this issue as soon as possible after issuing the notice;

(2) Deliver the decision promptly to the contractor; and

(3) Notify the contractor of their right to appeal under the Disputes clause.

Section by section

SectionTodayOverhaul textStatusWords
49.000Scope of part.Scope of part.Changed · 49% alike43 → 59
49.001Definitions.Definitions.Changed · 58% alike199 → 185
49.002Applicability.Applicability.Changed · 46% alike278 → 226
49.100Scope of subpart.Scope of subpart.Changed · 46% alike99 → 76
49.101Authorities and responsibilities.Authorities and responsibilities.Changed · 51% alike278 → 246
49.102Notice of termination.Notice of termination.Changed · 66% alike328 → 274
49.103Methods of settlement.Methods of settlement.Changed · 93% alike89 → 91
49.104Duties of prime contractor after receipt of notice of termination.Duties of prime contractor after receipt of notice of termination.Changed · 83% alike233 → 228
49.105Duties of termination contracting officer after issuance of notice of termination.Duties of termination contracting officer after issuance of notice of termination.Changed · 64% alike521 → 495
49.105-1Termination status reports.Release of excess funds.Changed · 17% alike34 → 107
49.105-2Release of excess funds.Cleanup of construction site.Changed · 8% alike138 → 33
49.105-3Termination case file.noneNot in the overhaul34 → –
49.105-4Cleanup of construction site.noneNot in the overhaul38 → –
49.106Fraud or other criminal conduct.Fraud or other criminal conduct.Same29 → 29
49.107Audit of prime contract settlement proposals and subcontract settlements.Audit of prime contract settlement proposals and subcontract settlements.Changed · 63% alike529 → 420
49.108Settlement of subcontract settlement proposals.Settlement of subcontract settlement proposals.Same0 → 0
49.108-1Subcontractor's rights.Subcontractor’s rights.Changed · 72% alike59 → 55
49.108-2Prime contractor's rights and obligations.Prime contractor’s rights and obligations.Changed · 57% alike196 → 146
49.108-3Settlement procedure.Settlement procedure.Changed · 69% alike301 → 275
49.108-4Authorization for subcontract settlements without approval or ratification.Authorization for subcontract settlements without approval or ratification.Changed · 82% alike755 → 742
49.108-5Recognition of judgments and arbitration awards.Recognition of judgments and arbitration awards.Changed · 77% alike300 → 275
49.108-6Delay in settling subcontractor settlement proposals.Delay in settling subcontractor settlement proposals.Changed · 83% alike58 → 51
49.108-7Government assistance in settling subcontracts.Assignment of rights under subcontracts.Changed · 16% alike82 → 162
49.108-8Assignment of rights under subcontracts.noneNot in the overhaul208 → –
49.109Settlement agreements.Settlement agreements.Same0 → 0
49.109-1General.General.Changed · 91% alike80 → 79
49.109-2Reservations.Reservations.Changed · 90% alike120 → 112
49.109-3Government property.Government property.Changed · 75% alike60 → 60
49.109-4No-cost settlement.No-cost settlement.Changed · 94% alike54 → 52
49.109-5Partial settlements.Partial settlements.Changed · 68% alike109 → 88
49.109-6Joint settlement of two or more settlement proposals.Joint settlement of two or more settlement proposals.Changed · 83% alike147 → 134
49.109-7Settlement by determination.Settlement by determination.Changed · 94% alike599 → 595
49.110Settlement negotiation memorandum.Settlement negotiation memorandum.Changed · 91% alike153 → 147
49.111Review of proposed settlements.Review of proposed settlements.Changed · 85% alike37 → 36
49.112Payment.Payment.Same0 → 0
49.112-1Partial payments.Partial payments.Changed · 93% alike791 → 754
49.112-2Final payment.Final payment.Changed · 96% alike245 → 245
49.113Cost principles.Unsettled contract changes.Changed · 8% alike65 → 85
49.114Unsettled contract changes.Settlement of terminated incentive contracts.Changed · 7% alike80 → 346
49.115Settlement of terminated incentive contracts.noneNot in the overhaul407 → –
49.201General.General.Changed · 36% alike188 → 143
49.202Profit.Profit.Changed · 37% alike395 → 365
49.203Adjustment for loss.Adjustment for loss.Changed · 70% alike320 → 284
49.204Deductions.Deductions.Changed · 62% alike117 → 85
49.205Completed end items.Completed end items.Changed · 66% alike148 → 142
49.206Settlement proposals.Settlement proposals.Same0 → 0
49.206-1Submission of settlement proposals.Submission of settlement proposals.Changed · 67% alike380 → 333
49.206-2Bases for settlement proposals.Bases for settlement proposals.Changed · 78% alike539 → 493
49.206-3Submission of inventory disposal schedules.Submission of inventory disposal schedules.Changed · 53% alike81 → 50
49.207Limitation on settlements.Limitation on settlements.Changed · 82% alike38 → 40
49.208Equitable adjustment after partial termination.Equitable adjustment after partial termination.Changed · 76% alike125 → 124
49.301General.General.Changed · 38% alike30 → 18
49.302Discontinuance of vouchers.Discontinuance of vouchers.Changed · 75% alike154 → 127
49.303Procedure after discontinuing vouchers.Procedure after discontinuing vouchers.Same0 → 0
49.303-1Submission of settlement proposal.Submission of settlement proposal.Changed · 42% alike83 → 56
49.303-2Submission of inventory disposal schedules.Submission of inventory disposal schedules.Changed · 43% alike82 → 48
49.303-3Audit of settlement proposal.Audit of settlement proposal.Changed · 26% alike37 → 16
49.303-4Adjustment of indirect costs.Adjustment of indirect costs.Changed · 43% alike152 → 79
49.303-5Final settlement.Final settlement.Changed · 39% alike138 → 103
49.304Procedure for partial termination.Procedure for partial termination.Same0 → 0
49.304-1General.General.Changed · 63% alike106 → 74
49.304-2Submission of settlement proposal (fee only).Submission of settlement proposal (fee only).Changed · 57% alike72 → 51
49.304-3Submission of vouchers.Submission of vouchers.Changed · 63% alike58 → 47
49.305Adjustment of fee.Adjustment of fee.Same0 → 0
49.305-1General.General.Changed · 54% alike184 → 124
49.305-2Construction contracts.Construction contracts.Changed · 54% alike198 → 153
49.401General.General.Changed · 66% alike214 → 183
49.402Termination of fixed-price contracts for default.Termination of fixed-price contracts for default.Same0 → 0
49.402-1The Government's right.The Government’s right.Changed · 89% alike73 → 69
49.402-2Effect of termination for default.Effect of termination for default.Changed · 58% alike430 → 275
49.402-3Procedure for default.Procedure for default.Changed · 53% alike1216 → 875
49.402-4Procedure in lieu of termination for default.Procedure in lieu of termination for default.Changed · 53% alike128 → 103
49.402-5Memorandum by the contracting officer.Memorandum by the contracting officer.Changed · 79% alike34 → 34
49.402-6Repurchase against contractor's account.Repurchase against contractor’s account.Changed · 40% alike316 → 199
49.402-7Other damages.Other damages.Changed · 76% alike109 → 88
49.402-8Reporting information.Reporting information.Changed · 54% alike39 → 39
49.403Termination of cost-reimbursement contracts for default.Termination of cost-reimbursement contracts for default.Changed · 68% alike198 → 155
49.404Surety-takeover agreements.Surety-takeover agreements.Changed · 61% alike493 → 353
49.405Completion by another contractor.Liquidation of liability.Changed · 20% alike67 → 61
49.406Liquidation of liability.noneNot in the overhaul82 → –
49.501General.General.Changed · 91% alike52 → 53
49.502Termination for convenience of the Government.Termination for convenience of the Government.Changed · 84% alike865 → 840
49.503Termination for convenience of the Government and default.Termination for convenience of the Government and default.Changed · 86% alike303 → 291
49.504Termination of fixed-price contracts for default.Termination of fixed-price contracts for default.Changed · 92% alike352 → 311
49.505Other termination clauses.Other termination clauses.Changed · 66% alike135 → 88
49.601Notice of termination for convenience.Notice of termination for convenience.Same10 → 10
49.601-1Electronic notice.Electronic notice.Changed · 93% alike337 → 328
49.601-2Letter notice.Letter notice.Changed · 99% alike1137 → 1148
49.602Forms for settlement of terminated contracts.Forms for settlement of terminated contracts.Same40 → 40
49.602-1Termination settlement proposal forms.Termination settlement proposal forms.Same142 → 142
49.602-2Inventory forms.Inventory forms.Same34 → 34
49.602-3Schedule of accounting information.Schedule of accounting information.Same34 → 34
49.602-4Partial payments.Partial payments.Changed · 97% alike19 → 18
49.602-5Settlement agreement.Settlement agreement.Changed · 91% alike23 → 21
49.603Formats for termination for convenience settlement agreements.Formats for termination for convenience settlement agreements.Same54 → 54
49.603-1Fixed-price contracts—complete termination.Fixed price contracts-complete termination.Changed · 98% alike1135 → 1149
49.603-2Fixed-price contracts—partial termination.Fixed-price contracts-partial termination.Changed · 99% alike1058 → 1066
49.603-3Cost-reimbursement contracts—complete termination, if settlement includes cost.Cost reimbursement contracts-complete termination, if settlement includes cost.Changed · 98% alike1421 → 1437
49.603-4Cost-reimbursement contracts—complete termination, with settlement limited to fee.Cost-reimbursement contracts-complete termination, with settlement limited to fee.Changed · 99% alike623 → 628
49.603-5Cost-reimbursement contracts—partial termination.Cost-reimbursement contracts-partial termination.Changed · 99% alike188 → 186
49.603-6No-cost settlement agreement—complete termination.No-cost settlement agreement-complete termination.Same132 → 132
49.603-7No-cost settlement agreement—partial termination.No-cost settlement agreement-partial termination.Changed · 99% alike218 → 217
49.603-8Fixed-price contracts—settlements with subcontractors only.Fixed-price contracts-settlements with subcontractors only.Changed · 99% alike497 → 499
49.603-9Settlement of reservations.Settlement of reservations.Changed · 93% alike153 → 153
49.604Release of excess funds under terminated contracts.Release of excess funds under terminated contracts.Changed · 96% alike197 → 198
49.605Request to settle subcontractor settlement proposals.Request to settle subcontractor settlement proposals.Changed · 96% alike204 → 204
49.606Granting subcontract settlement authorization.Granting subcontract settlement authorization.Changed · 100% alike574 → 574
49.607Delinquency notices.Delinquency notices.Changed · 99% alike479 → 480