The FAR overhaul, side by side
FAR Part 49: Termination of Contracts
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 108 sections, 25,216 words (Part 49 as in force, eCFR as of Oct 29, 2026). Overhaul text: 103 sections, 22,632 words (on acquisition.gov ↗, issued Aug 21, 2025). By number: 16 the same, 87 changed, 5 not in the overhaul, 0 new.
49.603-4: Changed (99% alike)
Today: Cost-reimbursement contracts—complete termination, with settlement limited to fee.
[Insert the following in Block 14 of SF 30 for settlement of cost-reimbursement contracts that are completely terminated, if settlement is limited to fee.]
(a) This supplemental agreement settles the amount of fee due under the contract, terminated in its entirety by Notice of Termination dated __________.
(b) The parties agree to the following:
(1) The Contractor has received $__________ on account of its fee under the contract before the effective date of termination.
(2) The Government agrees to pay to the Contractor or its assignee, upon presentation of a proper invoice or voucher, $__________ [insert net amount to be paid on account of fee]. This sum, with sums previously paid, constitutes payment in full and complete settlement of the amount due the Contractor on account of its fee under the contract.
(3) The Contractor's allowable costs under the contract will be paid under the terms and conditions of the contract and parts 31 and 49 of the Federal Acquisition Regulation.
[Insert subparagraph (3) only if there are costs to be vouchered out (see 49.302) or if there are costs to be covered later by a separate settlement agreement.]
(4) Regardless of any other provision of this agreement, the following rights and liabilities of the parties under the contract are reserved:
[The following list of reserved or excepted rights and liabilities is intended to cover those that should most frequently be reserved and that should be scrutinized at the time a settlement agreement is negotiated (see 49.109-2). The suggested language of the excepted items on the list may be varied at the discretion of the contracting officer. If accuracy or completeness can be achieved by referencing the number of a contract clause or provision covering the matter in question, then follow that method of enumerating reserved rights and liabilities. Omit any of the following that are not applicable and add any additional exceptions or reservations required.]
(i) All rights and liabilities, if any, of the parties, as to matters covered by any renegotiation authority.
(ii) All rights and liabilities, if any, of the parties under those clauses inserted in the contract because of the requirements of Acts of Congress and Executive Orders, including, without limitation, any applicable clauses relating to: labor law, contingent fees, domestic articles, and employment of aliens. [If the contract contains clauses of this character inserted for reasons other than requirements of Acts of Congress or Executive Orders, the suggested language should be appropriately modified.]
(iii) All rights and liabilities of the parties arising under the contract and relating to reproduction rights, patent infringements, inventions, or applications for patents, including rights to assignments, invention reports, licenses, covenants of indemnity against patent risks, and bonds for patent indemnity obligations, together with all rights and liabilities under the bonds.
(iv) All rights and liabilities of the parties, arising under the contract or otherwise, and concerning defects, guarantees, or warranties relating to any articles or component parts furnished to the Government by the Contractor under the contract or this agreement.
(v) All rights and liabilities of the parties under agreements relating to the future care and disposition by the Contractor of Government-owned property remaining in the Contractor's custody.
(vi) All rights and liabilities of the parties relating to Government property furnished to, or acquired by, the Contractor for the performance of the contract.
(vii) All rights and liabilities of the parties under the contract relating to options (except options to continue or increase the work under the contract), covenants not to compete, and covenants of indemnity.
(viii) All rights and liabilities, if any, of the parties under those clauses of the contract relating to price reductions for defective certified cost or pricing data.
(End of agreement)
Overhaul text: Cost-reimbursement contracts-complete termination, with settlement limited to fee.
[ Insert the following in Block 14 of SF 30 for settlement of cost-reimbursement contracts that are completely terminated, if settlement is limited to fee .]
(a) This supplemental agreement settles the amount of fee due under the contract, terminated in its entirety by Notice of Termination dated ______.
(b) The parties agree to the following:
(1) The Contractor has received $______ on account of its fee under the contract before the effective date of termination.
(2) The Government agrees to pay to the Contractor or its assignee, upon presentation of a proper invoice or voucher, $______ [ insert net amount to be paid on account of fee ]. This sum, with sums previously paid, constitutes payment in full and complete settlement of the amount due the Contractor on account of its fee under the contract.
(3) The Contractor’s allowable costs under the contract will be paid under the terms and conditions of the contract and parts 31 and 49 of the Federal Acquisition Regulation. [ Insert paragraph (b)(3) of this agreement only if there are costs to be vouchered out (see 49.302) or if there are costs to be covered later by a separate settlement agreement .]
(4) Regardless of any other provision of this agreement, the following rights and liabilities of the parties under the contract are reserved: [ The following list of reserved or excepted rights and liabilities is intended to cover those that should most frequently be reserved and that should be scrutinized at the time a settlement agreement is negotiated (see 49.109). The suggested language of the excepted items on the list may be varied at the discretion of the contracting officer. If accuracy or completeness can be achieved by referencing the number of a contract clause or provision covering the matter in question, then follow that method of enumerating reserved rights and liabilities. Omit any of the following that are not applicable and add any additional exceptions or reservations required. ]
(i) All rights and liabilities, if any, of the parties, as to matters covered by any renegotiation authority.
(ii) All rights and liabilities, if any, of the parties under those clauses inserted in the contract because of the requirements of Acts of Congress and Executive orders, including, without limitation, any applicable clauses relating to: labor law, contingent fees, domestic articles, and employment of aliens. [ If the contract contains clauses of this character inserted for reasons other than requirements of Acts of Congress or Executive orders, the suggested language should be appropriately modified. ]
(iii) All rights and liabilities of the parties arising under the contract and relating to reproduction rights, patent infringements, inventions, or applications for patents, including rights to assignments, invention reports, licenses, covenants of indemnity against patent risks, and bonds for patent indemnity obligations, together with all rights and liabilities under the bonds.
(iv) All rights and liabilities of the parties, arising under the contract or otherwise, and concerning defects, guarantees, or warranties relating to any articles or component parts furnished to the Government by the Contractor under the contract or this agreement.
(v) All rights and liabilities of the parties under agreements relating to the future care and disposition by the Contractor of Government-owned property remaining in the Contractor’s custody.
(vi) All rights and liabilities of the parties relating to Government property furnished to, or acquired by, the Contractor for the performance of the contract.
(vii) All rights and liabilities of the parties under the contract relating to options (except options to continue or increase the work under the contract), covenants not to compete, and covenants of indemnity.
(viii) All rights and liabilities, if any, of the parties under those clauses of the contract relating to price reductions for defective certified cost or pricing data.
(End of agreement)
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 49.000 | Scope of part. | Scope of part. | Changed · 49% alike | 43 → 59 |
| 49.001 | Definitions. | Definitions. | Changed · 58% alike | 199 → 185 |
| 49.002 | Applicability. | Applicability. | Changed · 46% alike | 278 → 226 |
| 49.100 | Scope of subpart. | Scope of subpart. | Changed · 46% alike | 99 → 76 |
| 49.101 | Authorities and responsibilities. | Authorities and responsibilities. | Changed · 51% alike | 278 → 246 |
| 49.102 | Notice of termination. | Notice of termination. | Changed · 66% alike | 328 → 274 |
| 49.103 | Methods of settlement. | Methods of settlement. | Changed · 93% alike | 89 → 91 |
| 49.104 | Duties of prime contractor after receipt of notice of termination. | Duties of prime contractor after receipt of notice of termination. | Changed · 83% alike | 233 → 228 |
| 49.105 | Duties of termination contracting officer after issuance of notice of termination. | Duties of termination contracting officer after issuance of notice of termination. | Changed · 64% alike | 521 → 495 |
| 49.105-1 | Termination status reports. | Release of excess funds. | Changed · 17% alike | 34 → 107 |
| 49.105-2 | Release of excess funds. | Cleanup of construction site. | Changed · 8% alike | 138 → 33 |
| 49.105-3 | Termination case file. | none | Not in the overhaul | 34 → – |
| 49.105-4 | Cleanup of construction site. | none | Not in the overhaul | 38 → – |
| 49.106 | Fraud or other criminal conduct. | Fraud or other criminal conduct. | Same | 29 → 29 |
| 49.107 | Audit of prime contract settlement proposals and subcontract settlements. | Audit of prime contract settlement proposals and subcontract settlements. | Changed · 63% alike | 529 → 420 |
| 49.108 | Settlement of subcontract settlement proposals. | Settlement of subcontract settlement proposals. | Same | 0 → 0 |
| 49.108-1 | Subcontractor's rights. | Subcontractor’s rights. | Changed · 72% alike | 59 → 55 |
| 49.108-2 | Prime contractor's rights and obligations. | Prime contractor’s rights and obligations. | Changed · 57% alike | 196 → 146 |
| 49.108-3 | Settlement procedure. | Settlement procedure. | Changed · 69% alike | 301 → 275 |
| 49.108-4 | Authorization for subcontract settlements without approval or ratification. | Authorization for subcontract settlements without approval or ratification. | Changed · 82% alike | 755 → 742 |
| 49.108-5 | Recognition of judgments and arbitration awards. | Recognition of judgments and arbitration awards. | Changed · 77% alike | 300 → 275 |
| 49.108-6 | Delay in settling subcontractor settlement proposals. | Delay in settling subcontractor settlement proposals. | Changed · 83% alike | 58 → 51 |
| 49.108-7 | Government assistance in settling subcontracts. | Assignment of rights under subcontracts. | Changed · 16% alike | 82 → 162 |
| 49.108-8 | Assignment of rights under subcontracts. | none | Not in the overhaul | 208 → – |
| 49.109 | Settlement agreements. | Settlement agreements. | Same | 0 → 0 |
| 49.109-1 | General. | General. | Changed · 91% alike | 80 → 79 |
| 49.109-2 | Reservations. | Reservations. | Changed · 90% alike | 120 → 112 |
| 49.109-3 | Government property. | Government property. | Changed · 75% alike | 60 → 60 |
| 49.109-4 | No-cost settlement. | No-cost settlement. | Changed · 94% alike | 54 → 52 |
| 49.109-5 | Partial settlements. | Partial settlements. | Changed · 68% alike | 109 → 88 |
| 49.109-6 | Joint settlement of two or more settlement proposals. | Joint settlement of two or more settlement proposals. | Changed · 83% alike | 147 → 134 |
| 49.109-7 | Settlement by determination. | Settlement by determination. | Changed · 94% alike | 599 → 595 |
| 49.110 | Settlement negotiation memorandum. | Settlement negotiation memorandum. | Changed · 91% alike | 153 → 147 |
| 49.111 | Review of proposed settlements. | Review of proposed settlements. | Changed · 85% alike | 37 → 36 |
| 49.112 | Payment. | Payment. | Same | 0 → 0 |
| 49.112-1 | Partial payments. | Partial payments. | Changed · 93% alike | 791 → 754 |
| 49.112-2 | Final payment. | Final payment. | Changed · 96% alike | 245 → 245 |
| 49.113 | Cost principles. | Unsettled contract changes. | Changed · 8% alike | 65 → 85 |
| 49.114 | Unsettled contract changes. | Settlement of terminated incentive contracts. | Changed · 7% alike | 80 → 346 |
| 49.115 | Settlement of terminated incentive contracts. | none | Not in the overhaul | 407 → – |
| 49.201 | General. | General. | Changed · 36% alike | 188 → 143 |
| 49.202 | Profit. | Profit. | Changed · 37% alike | 395 → 365 |
| 49.203 | Adjustment for loss. | Adjustment for loss. | Changed · 70% alike | 320 → 284 |
| 49.204 | Deductions. | Deductions. | Changed · 62% alike | 117 → 85 |
| 49.205 | Completed end items. | Completed end items. | Changed · 66% alike | 148 → 142 |
| 49.206 | Settlement proposals. | Settlement proposals. | Same | 0 → 0 |
| 49.206-1 | Submission of settlement proposals. | Submission of settlement proposals. | Changed · 67% alike | 380 → 333 |
| 49.206-2 | Bases for settlement proposals. | Bases for settlement proposals. | Changed · 78% alike | 539 → 493 |
| 49.206-3 | Submission of inventory disposal schedules. | Submission of inventory disposal schedules. | Changed · 53% alike | 81 → 50 |
| 49.207 | Limitation on settlements. | Limitation on settlements. | Changed · 82% alike | 38 → 40 |
| 49.208 | Equitable adjustment after partial termination. | Equitable adjustment after partial termination. | Changed · 76% alike | 125 → 124 |
| 49.301 | General. | General. | Changed · 38% alike | 30 → 18 |
| 49.302 | Discontinuance of vouchers. | Discontinuance of vouchers. | Changed · 75% alike | 154 → 127 |
| 49.303 | Procedure after discontinuing vouchers. | Procedure after discontinuing vouchers. | Same | 0 → 0 |
| 49.303-1 | Submission of settlement proposal. | Submission of settlement proposal. | Changed · 42% alike | 83 → 56 |
| 49.303-2 | Submission of inventory disposal schedules. | Submission of inventory disposal schedules. | Changed · 43% alike | 82 → 48 |
| 49.303-3 | Audit of settlement proposal. | Audit of settlement proposal. | Changed · 26% alike | 37 → 16 |
| 49.303-4 | Adjustment of indirect costs. | Adjustment of indirect costs. | Changed · 43% alike | 152 → 79 |
| 49.303-5 | Final settlement. | Final settlement. | Changed · 39% alike | 138 → 103 |
| 49.304 | Procedure for partial termination. | Procedure for partial termination. | Same | 0 → 0 |
| 49.304-1 | General. | General. | Changed · 63% alike | 106 → 74 |
| 49.304-2 | Submission of settlement proposal (fee only). | Submission of settlement proposal (fee only). | Changed · 57% alike | 72 → 51 |
| 49.304-3 | Submission of vouchers. | Submission of vouchers. | Changed · 63% alike | 58 → 47 |
| 49.305 | Adjustment of fee. | Adjustment of fee. | Same | 0 → 0 |
| 49.305-1 | General. | General. | Changed · 54% alike | 184 → 124 |
| 49.305-2 | Construction contracts. | Construction contracts. | Changed · 54% alike | 198 → 153 |
| 49.401 | General. | General. | Changed · 66% alike | 214 → 183 |
| 49.402 | Termination of fixed-price contracts for default. | Termination of fixed-price contracts for default. | Same | 0 → 0 |
| 49.402-1 | The Government's right. | The Government’s right. | Changed · 89% alike | 73 → 69 |
| 49.402-2 | Effect of termination for default. | Effect of termination for default. | Changed · 58% alike | 430 → 275 |
| 49.402-3 | Procedure for default. | Procedure for default. | Changed · 53% alike | 1216 → 875 |
| 49.402-4 | Procedure in lieu of termination for default. | Procedure in lieu of termination for default. | Changed · 53% alike | 128 → 103 |
| 49.402-5 | Memorandum by the contracting officer. | Memorandum by the contracting officer. | Changed · 79% alike | 34 → 34 |
| 49.402-6 | Repurchase against contractor's account. | Repurchase against contractor’s account. | Changed · 40% alike | 316 → 199 |
| 49.402-7 | Other damages. | Other damages. | Changed · 76% alike | 109 → 88 |
| 49.402-8 | Reporting information. | Reporting information. | Changed · 54% alike | 39 → 39 |
| 49.403 | Termination of cost-reimbursement contracts for default. | Termination of cost-reimbursement contracts for default. | Changed · 68% alike | 198 → 155 |
| 49.404 | Surety-takeover agreements. | Surety-takeover agreements. | Changed · 61% alike | 493 → 353 |
| 49.405 | Completion by another contractor. | Liquidation of liability. | Changed · 20% alike | 67 → 61 |
| 49.406 | Liquidation of liability. | none | Not in the overhaul | 82 → – |
| 49.501 | General. | General. | Changed · 91% alike | 52 → 53 |
| 49.502 | Termination for convenience of the Government. | Termination for convenience of the Government. | Changed · 84% alike | 865 → 840 |
| 49.503 | Termination for convenience of the Government and default. | Termination for convenience of the Government and default. | Changed · 86% alike | 303 → 291 |
| 49.504 | Termination of fixed-price contracts for default. | Termination of fixed-price contracts for default. | Changed · 92% alike | 352 → 311 |
| 49.505 | Other termination clauses. | Other termination clauses. | Changed · 66% alike | 135 → 88 |
| 49.601 | Notice of termination for convenience. | Notice of termination for convenience. | Same | 10 → 10 |
| 49.601-1 | Electronic notice. | Electronic notice. | Changed · 93% alike | 337 → 328 |
| 49.601-2 | Letter notice. | Letter notice. | Changed · 99% alike | 1137 → 1148 |
| 49.602 | Forms for settlement of terminated contracts. | Forms for settlement of terminated contracts. | Same | 40 → 40 |
| 49.602-1 | Termination settlement proposal forms. | Termination settlement proposal forms. | Same | 142 → 142 |
| 49.602-2 | Inventory forms. | Inventory forms. | Same | 34 → 34 |
| 49.602-3 | Schedule of accounting information. | Schedule of accounting information. | Same | 34 → 34 |
| 49.602-4 | Partial payments. | Partial payments. | Changed · 97% alike | 19 → 18 |
| 49.602-5 | Settlement agreement. | Settlement agreement. | Changed · 91% alike | 23 → 21 |
| 49.603 | Formats for termination for convenience settlement agreements. | Formats for termination for convenience settlement agreements. | Same | 54 → 54 |
| 49.603-1 | Fixed-price contracts—complete termination. | Fixed price contracts-complete termination. | Changed · 98% alike | 1135 → 1149 |
| 49.603-2 | Fixed-price contracts—partial termination. | Fixed-price contracts-partial termination. | Changed · 99% alike | 1058 → 1066 |
| 49.603-3 | Cost-reimbursement contracts—complete termination, if settlement includes cost. | Cost reimbursement contracts-complete termination, if settlement includes cost. | Changed · 98% alike | 1421 → 1437 |
| 49.603-4 | Cost-reimbursement contracts—complete termination, with settlement limited to fee. | Cost-reimbursement contracts-complete termination, with settlement limited to fee. | Changed · 99% alike | 623 → 628 |
| 49.603-5 | Cost-reimbursement contracts—partial termination. | Cost-reimbursement contracts-partial termination. | Changed · 99% alike | 188 → 186 |
| 49.603-6 | No-cost settlement agreement—complete termination. | No-cost settlement agreement-complete termination. | Same | 132 → 132 |
| 49.603-7 | No-cost settlement agreement—partial termination. | No-cost settlement agreement-partial termination. | Changed · 99% alike | 218 → 217 |
| 49.603-8 | Fixed-price contracts—settlements with subcontractors only. | Fixed-price contracts-settlements with subcontractors only. | Changed · 99% alike | 497 → 499 |
| 49.603-9 | Settlement of reservations. | Settlement of reservations. | Changed · 93% alike | 153 → 153 |
| 49.604 | Release of excess funds under terminated contracts. | Release of excess funds under terminated contracts. | Changed · 96% alike | 197 → 198 |
| 49.605 | Request to settle subcontractor settlement proposals. | Request to settle subcontractor settlement proposals. | Changed · 96% alike | 204 → 204 |
| 49.606 | Granting subcontract settlement authorization. | Granting subcontract settlement authorization. | Changed · 100% alike | 574 → 574 |
| 49.607 | Delinquency notices. | Delinquency notices. | Changed · 99% alike | 479 → 480 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress