FAR Part 49: Termination of Contracts

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 108 sections, 25,216 words (Part 49 as in force, eCFR as of Oct 29, 2026). Overhaul text: 103 sections, 22,632 words (on acquisition.gov ↗, issued Aug 21, 2025). By number: 16 the same, 87 changed, 5 not in the overhaul, 0 new.

49.404: Changed (61% alike)

Today: Surety-takeover agreements.

This section in plain English

(a) The procedures in this section apply primarily, but not solely, to fixed-price construction contracts terminated for default.

(b) Since the surety is liable for damages resulting from the contractor's default, the surety has certain rights and interests in the completion of the contract work and application of any undisbursed funds. Therefore, the contracting officer must consider carefully the surety's proposals for completing the contract. The contracting officer must take action on the basis of the Government's interest, including the possible effect upon the Government's rights against the surety.

(c) The contracting officer should permit surety offers to complete the contract, unless the contracting officer believes that the persons or firms proposed by the surety to complete the work are not competent and qualified or the proposal is not in the best interest of the Government.

(d) There may be conflicting demands for the defaulting contractor's assets, including unpaid prior earnings (retained percentages and unpaid progress estimates). Therefore, the surety may include a “takeover” agreement in its proposal, fixing the surety's rights to payment from those funds. The contracting officer may (but not before the effective date of termination) enter into a written agreement with the surety. The contracting officer should consider using a tripartite agreement among the Government, the surety, and the defaulting contractor to resolve the defaulting contractor's residual rights, including assertions to unpaid prior earnings.

(e) Any takeover agreement must require the surety to complete the contract and the Government to pay the surety's costs and expenses up to the balance of the contract price unpaid at the time of default, subject to the following conditions:

(1) Any unpaid earnings of the defaulting contractor, including retained percentages and progress estimates for work accomplished before termination, must be subject to debts due the Government by the contractor, except to the extent that the unpaid earnings may be used to pay the completing surety its actual costs and expenses incurred in the completion of the work, but not including its payments and obligations under the payment bond given in connection with the contract.

(2) The surety is bound by contract terms governing liquidated damages for delays in completion of the work, unless the delays are excusable under the contract.

(3) If the contract proceeds have been assigned to a financing institution, the surety must not be paid from unpaid earnings, unless the assignee provides written consent.

(4) The contracting officer must not pay the surety more than the amount it expended completing the work and discharging its liabilities under the defaulting contractor's payment bond. Payments to the surety to reimburse it for discharging its liabilities under the payment bond of the defaulting contractor must be only on authority of—

(i) Mutual agreement among the Government, the defaulting contractor, and the surety;

(ii) Determination of the Comptroller General as to payee and amount; or

(iii) Order of a court of competent jurisdiction.

Overhaul text: Surety-takeover agreements.

On acquisition.gov ↗

(a) These procedures apply mainly, but not exclusively, to fixed-price construction contracts terminated for default.

(b) Since the surety must pay for damages resulting from the contractor's default, the surety has certain rights in completing the contract and using undisbursed funds. The contracting officer must carefully consider the surety's proposals, evaluating how they might affect the Government's rights against the surety.

(c) The contracting officer should allow sureties to complete the contract unless-

(1) The people or companies proposed by the surety are not qualified or competent; or

(2) The proposal does not serve the Government's best interests.

(d) Multiple parties may claim the defaulting contractor's assets, including unpaid earnings. The surety may include a "takeover" agreement in its proposal to establish its rights to payment. The contracting officer may enter into a written agreement with the surety (but not before the termination date). Consider using a three-way agreement among the Government, surety, and defaulting contractor to resolve remaining rights, including claims to unpaid earnings.

(e) Any takeover agreement must require the surety to complete the contract and the Government to pay the surety's costs up to the unpaid contract price, subject to these conditions:

(1) Any unpaid earnings of the defaulting contractor may be used to pay Government claims against the contractor, except when those earnings are needed to pay the surety's actual completion costs and expenses (not including bond payments).

(2) The surety must meet contract requirements for liquidated damages for delays unless the delays qualify as excusable under the contract.

(3) If contract proceeds were assigned to a financing institution, the surety cannot receive payment from unpaid earnings without the assignee's written permission.

(4) The Government must not pay the surety more than it spent completing the work and meeting its payment bond obligations. Payments to the surety for its payment bond obligations require—

(i) Agreement among the Government, defaulting contractor, and surety;

(ii) A determination by the Comptroller General about who gets paid and how much; or

(iii) A court order from a court of competent jurisdiction.

Section by section

SectionTodayOverhaul textStatusWords
49.000Scope of part.Scope of part.Changed · 49% alike43 → 59
49.001Definitions.Definitions.Changed · 58% alike199 → 185
49.002Applicability.Applicability.Changed · 46% alike278 → 226
49.100Scope of subpart.Scope of subpart.Changed · 46% alike99 → 76
49.101Authorities and responsibilities.Authorities and responsibilities.Changed · 51% alike278 → 246
49.102Notice of termination.Notice of termination.Changed · 66% alike328 → 274
49.103Methods of settlement.Methods of settlement.Changed · 93% alike89 → 91
49.104Duties of prime contractor after receipt of notice of termination.Duties of prime contractor after receipt of notice of termination.Changed · 83% alike233 → 228
49.105Duties of termination contracting officer after issuance of notice of termination.Duties of termination contracting officer after issuance of notice of termination.Changed · 64% alike521 → 495
49.105-1Termination status reports.Release of excess funds.Changed · 17% alike34 → 107
49.105-2Release of excess funds.Cleanup of construction site.Changed · 8% alike138 → 33
49.105-3Termination case file.noneNot in the overhaul34 → –
49.105-4Cleanup of construction site.noneNot in the overhaul38 → –
49.106Fraud or other criminal conduct.Fraud or other criminal conduct.Same29 → 29
49.107Audit of prime contract settlement proposals and subcontract settlements.Audit of prime contract settlement proposals and subcontract settlements.Changed · 63% alike529 → 420
49.108Settlement of subcontract settlement proposals.Settlement of subcontract settlement proposals.Same0 → 0
49.108-1Subcontractor's rights.Subcontractor’s rights.Changed · 72% alike59 → 55
49.108-2Prime contractor's rights and obligations.Prime contractor’s rights and obligations.Changed · 57% alike196 → 146
49.108-3Settlement procedure.Settlement procedure.Changed · 69% alike301 → 275
49.108-4Authorization for subcontract settlements without approval or ratification.Authorization for subcontract settlements without approval or ratification.Changed · 82% alike755 → 742
49.108-5Recognition of judgments and arbitration awards.Recognition of judgments and arbitration awards.Changed · 77% alike300 → 275
49.108-6Delay in settling subcontractor settlement proposals.Delay in settling subcontractor settlement proposals.Changed · 83% alike58 → 51
49.108-7Government assistance in settling subcontracts.Assignment of rights under subcontracts.Changed · 16% alike82 → 162
49.108-8Assignment of rights under subcontracts.noneNot in the overhaul208 → –
49.109Settlement agreements.Settlement agreements.Same0 → 0
49.109-1General.General.Changed · 91% alike80 → 79
49.109-2Reservations.Reservations.Changed · 90% alike120 → 112
49.109-3Government property.Government property.Changed · 75% alike60 → 60
49.109-4No-cost settlement.No-cost settlement.Changed · 94% alike54 → 52
49.109-5Partial settlements.Partial settlements.Changed · 68% alike109 → 88
49.109-6Joint settlement of two or more settlement proposals.Joint settlement of two or more settlement proposals.Changed · 83% alike147 → 134
49.109-7Settlement by determination.Settlement by determination.Changed · 94% alike599 → 595
49.110Settlement negotiation memorandum.Settlement negotiation memorandum.Changed · 91% alike153 → 147
49.111Review of proposed settlements.Review of proposed settlements.Changed · 85% alike37 → 36
49.112Payment.Payment.Same0 → 0
49.112-1Partial payments.Partial payments.Changed · 93% alike791 → 754
49.112-2Final payment.Final payment.Changed · 96% alike245 → 245
49.113Cost principles.Unsettled contract changes.Changed · 8% alike65 → 85
49.114Unsettled contract changes.Settlement of terminated incentive contracts.Changed · 7% alike80 → 346
49.115Settlement of terminated incentive contracts.noneNot in the overhaul407 → –
49.201General.General.Changed · 36% alike188 → 143
49.202Profit.Profit.Changed · 37% alike395 → 365
49.203Adjustment for loss.Adjustment for loss.Changed · 70% alike320 → 284
49.204Deductions.Deductions.Changed · 62% alike117 → 85
49.205Completed end items.Completed end items.Changed · 66% alike148 → 142
49.206Settlement proposals.Settlement proposals.Same0 → 0
49.206-1Submission of settlement proposals.Submission of settlement proposals.Changed · 67% alike380 → 333
49.206-2Bases for settlement proposals.Bases for settlement proposals.Changed · 78% alike539 → 493
49.206-3Submission of inventory disposal schedules.Submission of inventory disposal schedules.Changed · 53% alike81 → 50
49.207Limitation on settlements.Limitation on settlements.Changed · 82% alike38 → 40
49.208Equitable adjustment after partial termination.Equitable adjustment after partial termination.Changed · 76% alike125 → 124
49.301General.General.Changed · 38% alike30 → 18
49.302Discontinuance of vouchers.Discontinuance of vouchers.Changed · 75% alike154 → 127
49.303Procedure after discontinuing vouchers.Procedure after discontinuing vouchers.Same0 → 0
49.303-1Submission of settlement proposal.Submission of settlement proposal.Changed · 42% alike83 → 56
49.303-2Submission of inventory disposal schedules.Submission of inventory disposal schedules.Changed · 43% alike82 → 48
49.303-3Audit of settlement proposal.Audit of settlement proposal.Changed · 26% alike37 → 16
49.303-4Adjustment of indirect costs.Adjustment of indirect costs.Changed · 43% alike152 → 79
49.303-5Final settlement.Final settlement.Changed · 39% alike138 → 103
49.304Procedure for partial termination.Procedure for partial termination.Same0 → 0
49.304-1General.General.Changed · 63% alike106 → 74
49.304-2Submission of settlement proposal (fee only).Submission of settlement proposal (fee only).Changed · 57% alike72 → 51
49.304-3Submission of vouchers.Submission of vouchers.Changed · 63% alike58 → 47
49.305Adjustment of fee.Adjustment of fee.Same0 → 0
49.305-1General.General.Changed · 54% alike184 → 124
49.305-2Construction contracts.Construction contracts.Changed · 54% alike198 → 153
49.401General.General.Changed · 66% alike214 → 183
49.402Termination of fixed-price contracts for default.Termination of fixed-price contracts for default.Same0 → 0
49.402-1The Government's right.The Government’s right.Changed · 89% alike73 → 69
49.402-2Effect of termination for default.Effect of termination for default.Changed · 58% alike430 → 275
49.402-3Procedure for default.Procedure for default.Changed · 53% alike1216 → 875
49.402-4Procedure in lieu of termination for default.Procedure in lieu of termination for default.Changed · 53% alike128 → 103
49.402-5Memorandum by the contracting officer.Memorandum by the contracting officer.Changed · 79% alike34 → 34
49.402-6Repurchase against contractor's account.Repurchase against contractor’s account.Changed · 40% alike316 → 199
49.402-7Other damages.Other damages.Changed · 76% alike109 → 88
49.402-8Reporting information.Reporting information.Changed · 54% alike39 → 39
49.403Termination of cost-reimbursement contracts for default.Termination of cost-reimbursement contracts for default.Changed · 68% alike198 → 155
49.404Surety-takeover agreements.Surety-takeover agreements.Changed · 61% alike493 → 353
49.405Completion by another contractor.Liquidation of liability.Changed · 20% alike67 → 61
49.406Liquidation of liability.noneNot in the overhaul82 → –
49.501General.General.Changed · 91% alike52 → 53
49.502Termination for convenience of the Government.Termination for convenience of the Government.Changed · 84% alike865 → 840
49.503Termination for convenience of the Government and default.Termination for convenience of the Government and default.Changed · 86% alike303 → 291
49.504Termination of fixed-price contracts for default.Termination of fixed-price contracts for default.Changed · 92% alike352 → 311
49.505Other termination clauses.Other termination clauses.Changed · 66% alike135 → 88
49.601Notice of termination for convenience.Notice of termination for convenience.Same10 → 10
49.601-1Electronic notice.Electronic notice.Changed · 93% alike337 → 328
49.601-2Letter notice.Letter notice.Changed · 99% alike1137 → 1148
49.602Forms for settlement of terminated contracts.Forms for settlement of terminated contracts.Same40 → 40
49.602-1Termination settlement proposal forms.Termination settlement proposal forms.Same142 → 142
49.602-2Inventory forms.Inventory forms.Same34 → 34
49.602-3Schedule of accounting information.Schedule of accounting information.Same34 → 34
49.602-4Partial payments.Partial payments.Changed · 97% alike19 → 18
49.602-5Settlement agreement.Settlement agreement.Changed · 91% alike23 → 21
49.603Formats for termination for convenience settlement agreements.Formats for termination for convenience settlement agreements.Same54 → 54
49.603-1Fixed-price contracts—complete termination.Fixed price contracts-complete termination.Changed · 98% alike1135 → 1149
49.603-2Fixed-price contracts—partial termination.Fixed-price contracts-partial termination.Changed · 99% alike1058 → 1066
49.603-3Cost-reimbursement contracts—complete termination, if settlement includes cost.Cost reimbursement contracts-complete termination, if settlement includes cost.Changed · 98% alike1421 → 1437
49.603-4Cost-reimbursement contracts—complete termination, with settlement limited to fee.Cost-reimbursement contracts-complete termination, with settlement limited to fee.Changed · 99% alike623 → 628
49.603-5Cost-reimbursement contracts—partial termination.Cost-reimbursement contracts-partial termination.Changed · 99% alike188 → 186
49.603-6No-cost settlement agreement—complete termination.No-cost settlement agreement-complete termination.Same132 → 132
49.603-7No-cost settlement agreement—partial termination.No-cost settlement agreement-partial termination.Changed · 99% alike218 → 217
49.603-8Fixed-price contracts—settlements with subcontractors only.Fixed-price contracts-settlements with subcontractors only.Changed · 99% alike497 → 499
49.603-9Settlement of reservations.Settlement of reservations.Changed · 93% alike153 → 153
49.604Release of excess funds under terminated contracts.Release of excess funds under terminated contracts.Changed · 96% alike197 → 198
49.605Request to settle subcontractor settlement proposals.Request to settle subcontractor settlement proposals.Changed · 96% alike204 → 204
49.606Granting subcontract settlement authorization.Granting subcontract settlement authorization.Changed · 100% alike574 → 574
49.607Delinquency notices.Delinquency notices.Changed · 99% alike479 → 480