7 sections with “adjustment (excluding profit)”

  • DFARS 215.404-71-3 Contract type risk and working capital adjustment.
    …of cost risk accepted by the contractor under varying contract types. The working capital adjustment is an adjustment added to the profit objective for contract type risk. It only applies to fixed-price contracts that provide for progress p…
  • FAR 52.242-17 Government Delay of Work.
    …hin the time specified in this contract, or within a reasonable time if not specified, an adjustment (excluding profit) shall be made for any increase in the cost of performance of this contract caused by the delay or interruption and the c…
  • FAR 52.249-6 Termination (Cost-Reimbursement).
    …o the Government. (l) The Contractor and Contracting Officer must agree to any equitable adjustment in fee for the continued portion of the contract when there is a partial termination. The Contracting Officer shall amend the contract to r…
  • FAR 52.249-2 Termination for Convenience of the Government (Fixed-Price).
    … Contractor failed to submit the termination settlement proposal or request for equitable adjustment within the time provided in paragraph (e) or (l), respectively, and failed to request a time extension, there is no right of appeal. (k) I…
  • FAR 52.242-14 Suspension of Work.
    …in the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspen…
  • FAR 52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements).
    …partial, the Contractor may file a proposal with the Contracting Officer for an equitable adjustment of the price(s) of the continued portion of the contract. The Contracting Officer shall make any equitable adjustment agreed upon. Any prop…
  • FAR 52.216-7 Allowable Cost and Payment.
    …the Contractor's indirect costs for payment purposes). (3) Notwithstanding the audit and adjustment of invoices or vouchers under paragraph (g) below, allowable indirect costs under this contract shall be obtained by applying indirect cost…