6 sections with “constructive acceptance period”

  • FAR 32.904 Determining payment due dates.
    …t penalty that might be due the contractor— (1) Government acceptance is deemed to occur constructively on the 7th day after the contractor delivers supplies or performs services in accordance with the terms and conditions of the contract,…
  • FAR 32.908 Contract clauses.
    … the date in paragraph (a)(4)(i) of the clause to specify a period longer than 7 days for constructive acceptance or constructive approval, if required to afford the Government a practicable opportunity to inspect and test the supplies furn…
  • FAR 52.232-25 Prompt payment.
    …terest penalty that might be due the Contractor, Government acceptance is deemed to occur constructively on the 7th day (unless otherwise specified in this contract) after the Contractor delivers the supplies or performs the services in acc…
  • FAR 52.232-26 Prompt Payment for Fixed-Price Architect-Engineer Contracts.
    …ty that might be due the Contractor, Government acceptance or approval is deemed to occur constructively as shown in paragraphs (a)(4)(i)(A) and (B) of this clause. If actual acceptance or approval occurs within the constructive acceptance …
  • FAR 52.232-27 Prompt Payment for Construction Contracts.
    …paragraph (a)(1)(ii) of this clause, Government acceptance or approval is deemed to occur constructively on the 7th day after the Contractor has completed the work or services in accordance with the terms and conditions of the contract. If …
  • DFARS 232.904 Determining payment due dates.
    (d) In most cases, Government acceptance or approval can occur within the 7-day constructive acceptance period specified in the FAR Prompt Payment clauses. Government payment of construction progress payments can, in most cases, be made wit…