  • FAR 49.108-5 Recognition of judgments and arbitration awards.
    (a) When a subcontractor obtains a final judgment against a prime contractor, the TCO shall, for the purposes of settling the prime contract, treat the amount of the judgment as a cost of settling with the contractor, to the extent the judg…
  • FAR 2.101 Definitions.
    …e Federal agency that, on behalf of all Federal agencies, is responsible for establishing final indirect cost rates and forward pricing rates, if applicable, and administering cost accounting standards for all contracts in a business unit. …
  • FAR 9.406-2 Causes for debarment.
    …oses of this provision if both of the following criteria apply: (1) The tax liability is finally determined. The liability is finally determined if it has been assessed. A liability is not finally determined if there is a pending administr…
  • FAR 52.209-5 Certification Regarding Responsibility Matters.
    … considered delinquent if both of the following criteria apply: (i) The tax liability is finally determined. The liability is finally determined if it has been assessed. A liability is not finally determined if there is a pending administr…
  • FAR 52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services.
    … considered delinquent if both of the following criteria apply: (A) The tax liability is finally determined. The liability is finally determined if it has been assessed. A liability is not finally determined if there is a pending administr…
  • FAR 52.228-11 Individual Surety—Pledge of Assets.
    …50,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later. (2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performanc…
  • DFARS 215.407-5-70 Disclosure, maintenance, and review requirements.
    …tial determination, in consultation with the auditor or functional specialist, and make a final determination. (3) Final determination. (i) The contracting officer shall make a final determination and notify the contractor in writing that—…
  • DFARS 252.215-7002 Cost Estimating System Requirements.
    …Contractor's response and notify the Contractor, in writing, of the Contracting Officer's final determination concerning— (i) Remaining material weaknesses; (ii) The adequacy of any proposed or completed corrective action; and (iii) Syst…
  • FAR 15.408 Solicitation provisions and contract clauses.
    … the agreement, include a copy, and describe its nature. H. As soon as practicable after final agreement on price or an earlier date agreed to by the parties, but before the award resulting from the proposal, you must, under the conditions…
  • FAR 28.203-3 Release of security interest.
    …ph (a). The security interest shall be maintained for the later of— (i) 1 year following final payment; (ii) Until completion of any warranty period (applicable only to performance bonds); or (iii) Pending resolution of all claims filed …
  • FAR 33.207 Contractor certification.
    …deprive a court or an agency BCA of jurisdiction over that claim. Prior to the entry of a final judgment by a court or a decision by an agency BCA, however, the court or agency BCA shall require a defective certification to be corrected.
  • FAR 52.228-7 Insurance—Liability to Third Persons.
    …tractor or of the Contractor's agents, servants, or employees, and must be represented by final judgments or settlements approved in writing by the Government. These liabilities are for— (i) Loss of or damage to property (other than proper…
  • DFARS 252.235-7004 Protection of Human Subjects.
    …sagreement regarding the Contractor's furnished exemption determination, the HRPO retains final judgment on what research activities or classes of research are covered or are exempt under the contract. (d) DoD staff, consultants, and advis…
  • FAR 15.404-1 Proposal analysis techniques.
    (a) General. The objective of proposal analysis is to ensure that the final agreed-to price is fair and reasonable. (1) The contracting officer is responsible for evaluating the reasonableness of the offered prices. The analytical techniqu…
  • FAR 9.403 Definitions.
    …ther disposition that creates a civil liability for the complained of wrongful acts, or a final determination of liability under the Program Fraud Civil Remedies Act of 1986 (31 U.S.C. 3801-3812). Contractor means any individual or other l…
  • FAR 11.106 Purchase descriptions for service contracts.
    …art 7.5) are not assigned to a contractor. These purchase descriptions shall (a) Reserve final determination for Government officials; (b) Require proper identification of contractor personnel who attend meetings, answer Government teleph…
  • FAR 15.405 Price negotiation.
    …eeded to reach a negotiated settlement with the offeror and is solely responsible for the final price agreement. However, when significant audit or other specialist recommendations are not adopted, the contracting officer should provide rat…
  • FAR 49.603-3 Cost-reimbursement contracts—complete termination, if settlement includes cost.
    …titutes a portion of the total amount to which the Contractor is entitled in complete and final settlement of the contract. (ii) Further, the Government agrees to pay to the Contractor or its assignee, upon presentation of a proper invoice…
  • FAR 52.237-7 Indemnification and Medical Liability Insurance.
    …nt shall be provided to the Contracting Officer prior to the expiration of this contract. Final payment under this contract shall be withheld until evidence of the extended reporting endorsement is provided to the Contracting Officer. (e) …
  • FAR 52.249-10 Default (Fixed-Price Construction).
    …r completing the work shall be extended. The findings of the Contracting Officer shall be final and conclusive on the parties, but subject to appeal under the Disputes clause. (c) If, after termination of the Contractor's right to proceed,…