48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

11 sections with “increment of payment”

  • FAR 52.237-6 Incremental Payment by Contractor to Government.
    …r determines that it would be advantageous to the Government for the contractor to pay in increments, and for the Government to transfer title to the contractor for increments of property, only upon receipt of those payments: Incremental P…
  • FAR 37.304 Contract clauses.
    …r determines that it would be advantageous to the Government for the contractor to pay in increments and the government to transfer title to the contractor for increments of property only upon receipt of those payments. (c) The contracting…
  • FAR 52.237-5 Payment by Contractor to Government.
    …r determines that it would be advantageous to the Government for the contractor to pay in increments and the Government to transfer title to the contractor for increments of property only upon receipt of those payments: Payment by Contract…
  • FAR 32.706-2 Clauses for limitation of cost or funds.
    …insert the clause at 52.232-22, Limitation of Funds, in solicitations and contracts if an incrementally funded cost-reimbursement contract is contemplated.
  • FAR 52.232-22 Limitation of Funds.
    …mount will cover. The parties contemplate that the Government will allot additional funds incrementally to the contract up to the full estimated cost to the Government specified in the Schedule, exclusive of any fee. The Contractor agrees t…
  • DFARS 252.232-7007 Limitation of Government's obligation.
    …R 2014) (a) Contract line item(s) [Contracting Officer insert after negotiations] is/are incrementally funded. For this/these item(s), the sum of $____ [Contracting Officer insert after negotiations] of the total price is presently availab…
  • DFARS 252.239-7007 Cancellation or Termination of Orders.
    …ed. Basic termination liability means the nonrecoverable cost amortized in equal monthly increments throughout the liability period. Installed costs means the actual cost of equipment and materials specifically provided or used, plus the …
  • FAR 52.243-2 Changes—Cost-Reimbursement.
    …aragraphs (a) and (b) above, the estimated cost of this contract and, if this contract is incrementally funded, the funds allotted for the performance of this contract, shall not be increased or considered to be increased except by specific…
  • FAR 35.017-1 Sponsoring agreements.
    …agreement will not exceed 5 years, but can be renewed, as a result of periodic review, in increments not to exceed 5 years.
  • FAR 52.245-9 Use and Charges.
    …e constraints therein or the following formula in which rental time shall be expressed in increments of not less than one hour with portions of hours rounded to the next higher hour: The hourly rental charge is calculated by multiplying 2 p…
  • DFARS 204.7103-1 Criteria for establishing.
    …: (A) A single, nonseverable deliverable to be paid for with R&D or other funds properly incrementally obligated over several fiscal years in accordance with DoD policy; (B) A single, nonseverable deliverable to be paid for with different…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.