48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

7 sections with “incremental payment”

  • FAR 52.237-6 Incremental Payment by Contractor to Government.
    …title to the contractor for increments of property, only upon receipt of those payments: Incremental Payment by Contractor to Government (APR 1984) (a) The Contractor shall perform the work called for under this contract and within __ day…
  • FAR 37.304 Contract clauses.
    …eipt of those payments. (c) The contracting officer shall insert the clause at 52.237-6, Incremental Payment by Contractor to Government, in solicitations and contracts for dismantling, demolition, or removal of improvements if (1) the con…
  • FAR 52.243-2 Changes—Cost-Reimbursement.
    …aragraphs (a) and (b) above, the estimated cost of this contract and, if this contract is incrementally funded, the funds allotted for the performance of this contract, shall not be increased or considered to be increased except by specific…
  • FAR 32.706-2 Clauses for limitation of cost or funds.
    …insert the clause at 52.232-22, Limitation of Funds, in solicitations and contracts if an incrementally funded cost-reimbursement contract is contemplated.
  • FAR 52.232-22 Limitation of Funds.
    …mount will cover. The parties contemplate that the Government will allot additional funds incrementally to the contract up to the full estimated cost to the Government specified in the Schedule, exclusive of any fee. The Contractor agrees t…
  • DFARS 204.7103-1 Criteria for establishing.
    …: (A) A single, nonseverable deliverable to be paid for with R&D or other funds properly incrementally obligated over several fiscal years in accordance with DoD policy; (B) A single, nonseverable deliverable to be paid for with different…
  • DFARS 252.232-7007 Limitation of Government's obligation.
    …R 2014) (a) Contract line item(s) [Contracting Officer insert after negotiations] is/are incrementally funded. For this/these item(s), the sum of $____ [Contracting Officer insert after negotiations] of the total price is presently availab…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.