9 sections with “incrementally funded contract”

  • DFARS 232.704-70 Incrementally funded fixed-price contracts.
    (a) Upon receipt of the contractor's notice under paragraph (c) of the clause at 252.232-7007, Limitation of Government's Obligation, the contracting officer shall promptly provide written notice to the contractor that the Government is— (…
  • FAR 43.201 General.
    …ust continue performance of the contract as changed, except that in cost-reimbursement or incrementally funded contracts the contractor is not obligated to continue performance or incur costs beyond the limits established in the Limitation …
  • DFARS 232.703-1 General.
    (1) A fixed-price contract may be incrementally funded only if— (i) The contract (excluding any options) or any exercised option— (A) Is for severable services; (B) Does not exceed one year in length; and (C) Is incrementally funded usi…
  • DFARS 249.501-70 Special termination costs.
    (a) The clause at 252.249-7000, Special Termination Costs, may be used in an incrementally funded contract when its use is approved by the agency head. (b) The clause is authorized when— (1) The contract term is 2 years or more; (2) The …
  • FAR 52.243-2 Changes—Cost-Reimbursement.
    …aragraphs (a) and (b) above, the estimated cost of this contract and, if this contract is incrementally funded, the funds allotted for the performance of this contract, shall not be increased or considered to be increased except by specific…
  • FAR 32.703-1 General.
    … the estimated cost and any fee of a cost-reimbursement contract. (b) If the contract is incrementally funded, funds are obligated to cover the amount allotted and any corresponding increment of fee.
  • FAR 32.706-2 Clauses for limitation of cost or funds.
    …insert the clause at 52.232-22, Limitation of Funds, in solicitations and contracts if an incrementally funded cost-reimbursement contract is contemplated.
  • DFARS 232.706-70 Clause for limitation of Government's obligation.
    …se at 252.232-7007, Limitation of Government's Obligation, in solicitations and resultant incrementally funded fixed-price contracts. The contracting officer may revise the contractor's notification period, in paragraph (c) of the clause, f…
  • DFARS 252.232-7007 Limitation of Government's obligation.
    …R 2014) (a) Contract line item(s) [Contracting Officer insert after negotiations] is/are incrementally funded. For this/these item(s), the sum of $____ [Contracting Officer insert after negotiations] of the total price is presently availab…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.