9 sections with “normal spoilage”

  • FAR 31.205-42 Termination costs.
    …ctors such as— (i) Excessive spoilage due to inexperienced labor; (ii) Idle time and subnormal production due to testing and changing production methods; (iii) Training; and (iv) Lack of familiarity or experience with the product, mater…
  • FAR 32.503-16 Risk of loss.
    (a) Under the Progress Payments clause, and except for normal spoilage, the contractor bears the risk of loss for Government property under the clause, even though title is vested in the Government, unless the Government has expressly assum…
  • FAR 32.1010 Risk of loss.
    (a) Under the clause at 52.232-32, Performance-Based Payments, and except for normal spoilage, the contractor bears the risk of loss for Government property, even though title is vested in the Government, unless the Government has expressly…
  • FAR 49.204 Deductions.
    …Government or to a buyer under part 45, is lost or so damaged as to become undeliverable (normal spoilage is excepted, as is inventory for which the Government has expressly assumed the risk of loss); and (c) Any other amounts as appropria…
  • FAR 52.249-2 Termination for Convenience of the Government (Fixed-Price).
    …he preservation, protection, or disposition of the termination inventory. (h) Except for normal spoilage, and except to the extent that the Government expressly assumed the risk of loss, the Contracting Officer shall exclude from the amoun…
  • FAR 52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements).
    …tion and protection of property under subparagraph (b)(8) of this clause. (h) Except for normal spoilage, and except to the extent that the Government expressly assumed the risk of loss, the Contracting Officer shall exclude from the amoun…
  • FAR 15.404-1 Proposal analysis techniques.
    …e following: (i) Comparison of proposed prices received in response to the solicitation. Normally, adequate price competition establishes a fair and reasonable price (see 15.403-1(c)(1)). (ii) Comparison of the proposed prices to historic…
  • FAR 17.106-1 General.
    …y an “average” prime contractor or subcontractor, which would be applicable to, and which normally would be amortized over, the items or services to be furnished under the multiyear requirements. Nonrecurring costs include such costs, where…
  • FAR 31.205-19 Insurance and indemnification.
    … or casualty losses resulting from defects in materials or workmanship are allowable as a normal business expense. (4) Premiums for retroactive or backdated insurance written to cover losses that have occurred and are known are unallowable…