48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

13 sections with “retained percentage”

  • FAR 49.404 Surety-takeover agreements.
    …flicting demands for the defaulting contractor's assets, including unpaid prior earnings (retained percentages and unpaid progress estimates). Therefore, the surety may include a “takeover” agreement in its proposal, fixing the surety's rig…
  • FAR 49.406 Liquidation of liability.
    …are liable to the Government for resultant damages. The contracting officer shall use all retained percentages of progress payments previously made to the contractor and any progress payments due for work completed before the termination to…
  • DFARS 252.236-7003 Payment for mobilization and preparatory work.
    …on receiving a request for payment, the Government will make payment, less any prescribed retained percentage, if— (1) The Contracting Officer finds the— (i) Construction plant, material, equipment, and the mobilization and preparatory wo…
  • FAR 52.232-27 Prompt Payment for Construction Contracts.
    …actor compliance with contract requirements. (B) The due date for payment of any amounts retained by the Contracting Officer in accordance with the clause at 52.232-5, Payments Under Fixed-Price Construction Contracts, is as specified in t…
  • FAR 11.701 Supply contracts.
    …ies, to provide that— (1) Excess quantities of items totaling up to $250 in value may be retained without compensating the contractor; and (2) Excess quantities of items totaling over $250 in value may, at the Government's option, be eith…
  • FAR 32.103 Progress payments under construction contracts.
    …d for which a progress payment is to be made, a percentage of the progress payment may be retained. Retainage should not be used as a substitute for good contract management, and the contracting officer should not withhold funds without cau…
  • FAR 52.232-12 Advance Payments.
    …se of the Government's lien to the extent that— (i) The termination inventory is sold or retained; and (ii) The sale proceeds or retention credits are applied to reduce any outstanding advance payments. (j) Insurance. (1) The Contractor …
  • FAR 31.205-47 Costs related to legal and other proceedings.
    …ouse or private counsel; the costs of the services of accountants, consultants, or others retained by the contractor or subcontractor to assist it; costs of employees, officers, and directors; and any similar costs incurred before, during, …
  • FAR 52.203-5 Covenant Against Contingent Fees.
    …ees (MAY 2014) (a) The Contractor warrants that no person or agency has been employed or retained to solicit or obtain this contract upon an agreement or understanding for a contingent fee, except a bona fide employee or agency. For breach…
  • FAR 52.212-4 Contract Terms and Conditions—Commercial Products and Commercial Services.
    … personnel; or (ii) The conduct of one or more of the Contractor's employees selected or retained by the Contractor after any of the Contractor's managerial personnel has reasonable grounds to believe that the employee is habitually carele…
  • FAR 52.222-41 Service Contract Labor Standards.
    …tion of any contract being performed at a Federal facility where service employees may be retained in the performance of the succeeding contract and subject to a wage determination which contains vacation or other benefit provisions based u…
  • FAR 52.237-4 Payment by Government to Contractor.
    … all property to be dismantled or demolished that is not specifically designated as being retained by the Government. The title shall vest in the Contractor immediately upon the Government's issuing the notice of award, or if a performance …
  • FAR 52.245-1 Government Property.
    … except for property identified as a deliverable end item. If a deliverable item is to be retained by the Contractor for use after inspection and acceptance by the Government, it shall be made accountable to the contract through a contract …

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.