48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

17 sections with “summary report”

  • DFARS 252.234-7003 Notice of Cost and Software Data Reporting System.
    …plan and related Resource Distribution Table; and (6) Submit the DD Form 1921, Cost Data Summary Report, and DD Form 1921-1, Functional Cost-Hour Report, with its pricing proposal. (c) CSDR reporting will be required for subcontractors at…
  • FAR 22.406-8 Investigations.
    …upporting evidence, to the agency head. Standard Form 1446, Labor Standards Investigation Summary Sheet, is the first page of the report; and (2) The agency head must process the report as follows: (i) The contracting officer must send a …
  • DFARS 252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements.
    …ethodology-Version-1.2.1-6.24.2020.pdf (c) Procedures. (1) The Offeror shall verify that summary level scores of a current NIST SP 800-171 DoD Assessment (i.e., not more than 3 years old unless a lesser time is specified in the solicitatio…
  • DFARS 252.204-7020 NIST SP 800-171 DoD Assessment Requirements.
    …00-171-Assessment-Methodology-Version-1.2.1-6.24.2020.pdf, if necessary. (d) Procedures. Summary level scores for all assessments will be posted in the Supplier Performance Risk System (SPRS) (https://www.sprs.csd.disa.mil/) to provide DoD…
  • DFARS 232.503-15 Application of Government title terms.
    …ty that took place in the prior month; (ii) The contractor prepares, at least monthly, a summary of the transfer activity that took place in the prior month; and (iii) The summary report includes as a minimum, the total number and dollar …
  • DFARS 252.235-7011 Final scientific or technical report.
    …(a) Submit an electronic copy of the approved final scientific or technical report, not a summary, delivered under this contract to the Defense Technical Information Center (DTIC) through the web-based input system at https://discover.dtic.…
  • DFARS 252.245-7005 Management and Reporting of Government Property.
    …y to inspect the property and prepare bids. (vi) For large sales, the Contractor may use summary lists of items offered as bid sheets with detailed descriptions attached. (vii) In addition to providing notice of the proposed sale to prosp…
  • FAR 15.408 Solicitation provisions and contract clauses.
    …st accounting system. E. When more than one line item is proposed, you must also provide summary total amounts covering all line items for each element of cost. F. Whenever you have incurred costs for work performed before submission of a…
  • FAR 42.503-1 Postaward conference arrangements.
    …rson; (5) Conducting a preliminary meeting of Government personnel; and (6) Preparing a summary report of the conference. (b) When the contracting office initiates a conference, the arrangements may be made by that office or, at its requ…
  • FAR 42.503-2 Postaward conference procedure.
    …not take action that in any way alters the contract. The chairperson shall include in the summary report (see 42.503-3 below) all information and guidance provided to the contractor.
  • FAR 52.219-9 Small Business Subcontracting Plan.
    …use by multiple agencies; (iv) Submit the Individual Subcontract Report (ISR) and/or the Summary Subcontract Report (SSR), in accordance with paragraph (l) of this clause using the Electronic Subcontracting Reporting System (eSRS) at http:…
  • DFARS 222.406-8 Investigations.
    … regulations. (d) Contracting officer's report. Forward a detailed enforcement report or summary report to the agency head in accordance with agency procedures. Include in the report, as a minimum, the information specified at PGI 222.406-…
  • DFARS 252.219-7003 Small Business Subcontracting Plan (DoD Contracts).
    …s Subcontracting Plan, clause of this contract. (a) Definition. As used in this clause— Summary Subcontract Report (SSR) Coordinator means the individual who is registered in the Electronic Subcontracting Reporting System (eSRS) at the De…
  • FAR 52.216-7 Allowable Cost and Payment.
    … following data unless otherwise specified by the cognizant Federal agency official: (A) Summary of all claimed indirect expense rates, including pool, base, and calculated indirect rate. (B) General and Administrative expenses (final ind…
  • FAR 19.704 Subcontracting plan requirements.
    …r use by multiple agencies; (iv) Submit the Individual Subcontract Report (ISR), and the Summary Subcontract Report (SSR) using the Electronic Subcontracting Reporting System (eSRS) (http://www.esrs.gov), following the instructions in the …
  • FAR 49.107 Audit of prime contract settlement proposals and subcontract settlements.
    …not warranted, the TCO will perform or have performed a desk review and include a written summary of the review in the termination case file. (b) The TCO shall refer subcontract settlements received for approval or ratification to the appr…
  • DFARS 252.219-7004 Small Business Subcontracting Plan (Test Program).
    …s with subcontracting plans agree to submit an Individual Subcontract Report (ISR) and/or Summary Subcontract Report (SSR) using the Electronic Subcontracting Reporting System (eSRS). (ii) Provide its contract number, its unique entity ide…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.