8 sections with “CPSR”

  • FAR 44.302 Requirements.
    (a) The ACO shall determine the need for a CPSR based on, but not limited to, the past performance of the contractor, and the volume, complexity and dollar value of subcontracts. If a contractor's sales to the Government (excluding competit…
  • FAR 44.101 Definitions.
    …vision, or plant, that performs its own purchasing. Contractor purchasing system review (CPSR) means the complete evaluation of a contractor's purchasing of material and services, subcontracting, and subcontract management from development…
  • FAR 44.301 Objective.
    The objective of a contractor purchasing system review (CPSR) is to evaluate the efficiency and effectiveness with which the contractor spends Government funds and complies with Government policy when subcontracting. The review provides the…
  • FAR 44.303 Extent of review.
    A CPSR requires an evaluation of the contractor's purchasing system. Unless segregation of subcontracts is impracticable, this evaluation shall not include subcontracts awarded by the contractor exclusively in support of Government contract…
  • FAR 44.304 Surveillance.
    …a result of previous Government recommendations. Duplicative reviews of the same areas by CPSR and other surveillance monitors should be avoided.
  • FAR 44.305-2 Notification.
    …ntracts requiring consent. Reasons for selecting the subcontracts include the fact that a CPSR or continuing surveillance has revealed sufficient weaknesses in a particular area of subcontracting to warrant special attention by the ACO. (c…
  • FAR 44.307 Reports.
    The ACO shall distribute copies of CPSR reports; notifications granting, withholding, or withdrawing system approval; and Government recommendations for improvement of an approved system, including the contractor's response, to at least— (…
  • DFARS 244.302 Requirements.
    (a) In lieu of the threshold at FAR 44.302(a), the ACO shall determine the need for a CPSR if a contractor's sales to the Government are expected to exceed $50 million during the next 12 months.

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.