11 sections with “EVMS”

  • FAR 34.201 Policy.
    (a) An Earned Value Management System (EVMS) is required for major acquisitions for development, in accordance with OMB Circular A-11. The Government may also require an EVMS for other acquisitions, in accordance with agency procedures. (b…
  • FAR 52.234-2 Notice of Earned Value Management System—Preaward Integrated Baseline Review.
    …Cognizant Federal Agency has determined that the proposed earned value management system (EVMS) complies with the EVMS guidelines in Electronic Industries Alliance Standard 748 (EIA-748) (current version at time of solicitation). (b) If th…
  • FAR 52.234-3 Notice of Earned Value Management System—Postaward Integrated Baseline Review.
    …Cognizant Federal Agency has determined that the proposed earned value management system (EVMS) complies with the EVMS guidelines in Electronic Industries Alliance Standard 748 (EIA-748)(current version at time of solicitation). (b) If the…
  • FAR 52.234-4 Earned Value Management System.
    …gement System (NOV 2016) (a) The Contractor shall use an earned value management system (EVMS) that has been determined by the Cognizant Federal Agency (CFA) to be compliant with the guidelines in Electronic Industries Alliance Standard 74…
  • DFARS 252.234-7001 Notice of Earned Value Management System.
    …ant Federal Agency (CFA) has determined that the proposed Earned Value Management System (EVMS) complies with the EVMS guidelines in the American National Standards Institute/Electronic Industries Alliance Standard 748, Earned Value Managem…
  • DFARS 252.234-7002 Earned Value Management System.
    …mance of this contract, the Contractor shall use— (1) An Earned Value Management System (EVMS) that complies with the EVMS guidelines in the American National Standards Institute/Electronic Industries Alliance Standard 748, Earned Value Ma…
  • FAR 34.203 Solicitation provisions and contract clause.
    …tions for contracts that require the contractor to use an Earned Value Management System (EVMS) and for which the Government requires an Integrated Baseline Review (IBR) prior to award. (b) The contracting officer shall insert a provision …
  • FAR 7.105 Contents of written acquisition plans.
    …ation factors to the attainment of the acquisition objectives (see subpart 15.3). When an EVMS is required (see FAR 34.202(a)) and a preaward IBR is contemplated, the acquisition plan must discuss— (i) How the pre-award IBR will be conside…
  • DFARS 242.302 Contract administration functions.
    …components. (S-71) DCMA has responsibility for reviewing earned value management system (EVMS) plans and for verifying initial and continuing contractor compliance with DoD EVMS criteria. The contracting officer shall not retain this funct…
  • FAR 34.202 Integrated Baseline Reviews.
    (a) When an EVMS is required, the Government will conduct an Integrated Baseline Review (IBR). (b) The purpose of the IBR is to verify the technical content and the realism of the related performance budgets, resources, and schedules. It s…
  • DFARS 234.203 Solicitation provisions and contract clause.
    …t or incentive contracts valued at $20,000,000 or more, and for other contracts for which EVMS will be applied in accordance with 234.201(1)(iii) and (iv)— (1) Use the provision at 252.234-7001, Notice of Earned Value Management System, in…