9 sections with “Excusable delays”

  • FAR 52.249-14 Excusable Delays.
    … the words “completion time” for “delivery schedule” in the last sentence of the clause. Excusable Delays (APR 1984) (a) Except for defaults of subcontractors at any tier, the Contractor shall not be in default because of any failure to p…
  • FAR 49.505 Other termination clauses.
    …sonal Services), in solicitations and contracts for personal services (see Part 37). (b) Excusable delays. The contracting officer shall insert the clause at 52.249-14, Excusable Delays, in solicitations and contracts for supplies, service…
  • FAR 52.212-4 Contract Terms and Conditions—Commercial Products and Commercial Services.
    …tions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference. (f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Con…
  • FAR 52.213-4 Terms and Conditions—Simplified Acquisitions (Other Than Commercial Products and Commercial Services).
    …rs in the condition of the item, unless the change is due to the defect in the item. (e) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Con…
  • FAR 22.101-2 Contract pricing and administration.
    …ountable for reasonably avoidable delays. Standard contract clauses dealing with default, excusable delays, etc., do not relieve contractors or subcontractors from the responsibility for delays that are within the contractors' or their subc…
  • FAR 52.216-10 Incentive Fee.
    …t shall not include allowable costs arising out of— (i) Any of the causes covered by the Excusable Delays clause to the extent that they are beyond the control and without the fault or negligence of the Contractor or any subcontractor; (i…
  • FAR 52.249-6 Termination (Cost-Reimbursement).
    …ond the control and without the fault or negligence of the Contractor as set forth in the Excusable Delays clause, the rights and obligations of the parties will be the same as if the termination was for the convenience of the Government. …
  • FAR 49.404 Surety-takeover agreements.
    … governing liquidated damages for delays in completion of the work, unless the delays are excusable under the contract. (3) If the contract proceeds have been assigned to a financing institution, the surety must not be paid from unpaid ear…
  • FAR 52.249-10 Default (Fixed-Price Construction).
    …o proceed, it is determined that the Contractor was not in default, or that the delay was excusable, the rights and obligations of the parties will be the same as if the termination had been issued for the convenience of the Government. (d…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.