48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

7 sections with “Insurance—Work on a Government Installation”

  • FAR 52.228-5 Insurance—Work on a Government Installation.
    As prescribed in 28.310, insert the following clause: Insurance—Work on a Government Installation (JAN 1997) (a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the k…
  • FAR 28.310 Contract clause for work on a Government installation.
    (a) Insert the clause at 52.228-5, Insurance—Work on a Government Installation, in solicitations and contracts if a fixed-price contract is contemplated, the contract amount is expected to exceed the simplified acquisition threshold, and th…
  • FAR 28.306 Insurance under fixed-price contracts.
    (a) General. Although the Government is not ordinarily concerned with the contractor's insurance coverage if the contract is a fixed-price contract, in special circumstances agencies may specify insurance requirements under fixed-price cont…
  • FAR 2.101 Definitions.
    …and intermediate assemblies) to determine whether they conform to contract requirements. Insurance means a contract that provides that for a stipulated consideration, one party undertakes to indemnify another against loss, damage, or liabi…
  • DFARS 252.217-7012 Liability and insurance.
    As prescribed in 217.7104(a), use the following clause: Liability and Insurance (AUG 2003) (a) The Contractor shall exercise its best efforts to prevent accidents, injury, or damage to all employees, persons, and property, in and about th…
  • FAR 52.245-1 Government Property.
    … this contract, except when any one of the following applies— (i) The risk is covered by insurance or the Contractor is otherwise reimbursed (to the extent of such insurance or reimbursement). The allowability of insurance costs shall be d…
  • DFARS 252.228-7001 Ground and Flight Risk.
    …tal to work performed under the contract as described in the Schedule; (4) Is covered by insurance; (5) Occurs after the Contracting Officer has, in writing, revoked the Government's assumption of risk in accordance with paragraph (e)(3) …