  • FAR 52.216-5 Price Redetermination—Prospective.
    As prescribed in 16.205-4, insert the following clause: Price Redetermination—Prospective (JAN 2022) (a) General. The unit prices and the total price stated in this contract shall be periodically redetermined in accordance with this claus…
  • FAR 16.205 Fixed-price contracts with prospective price redetermination.
  • FAR 15.408 Solicitation provisions and contract clauses.
    …alue, the contracting officer shall use the clause with— (1) Its Alternate I, if a fixed-price incentive contract is contemplated; or (2) Its Alternate II, if a cost-plus-incentive-fee contract is contemplated. (b) Price Reduction for De…
  • FAR 16.205-2 Application.
    A fixed-price contract with prospective price redetermination may be used in acquisitions of quantity production or services for which it is possible to negotiate a fair and reasonable firm fixed price for an initial period, but not for sub…
  • FAR 31.204 Application of principles and procedures.
    …he subcontractor that are consistent with this part: (i) Cost-reimbursement. (ii) Fixed-price incentive. (iii) Price redeterminable (i.e., fixed-price contracts with prospective price redetermination and fixed-ceiling-price contracts wit…
  • FAR 32.503-9 Liquidation rates—alternate method.
    …te method is to permit the contractor to retain the earned profit element of the contract prices for completed items in the liquidation process. The contracting officer may reduce the liquidation rate if— (1) The contractor requests a redu…
  • FAR 48.001 Definitions.
    …nd implementation costs; (2) Concurrent contract savings, that are net reductions in the prices of other contracts that are definitized and ongoing at the time the VECP is accepted; and (3) Future contract savings, that are the product of…
  • FAR 52.248-1 Value Engineering.
    …d implementation costs; (2) Concurrent contract savings, which are net reductions in the prices of other contracts that are definitized and ongoing at the time the VECP is accepted; and (3) Future contract savings, which are the product o…
  • DFARS 215.404-71-3 Contract type risk and working capital adjustment.
    …adjustment added to the profit objective for contract type risk. It only applies to fixed-price contracts that provide for progress payments. Though it uses a formula approach, it is not intended to be an exact calculation of the cost of wo…
  • FAR 16.205-1 Description.
    A fixed-price contract with prospective price redetermination provides for (a) a firm fixed price for an initial period of contract deliveries or performance and (b) prospective redetermination, at a stated time or times during performance,…
  • FAR 16.205-3 Limitations.
    …nless— (a) Negotiations have established that (1) the conditions for use of a firm-fixed-price contract are not present (see 16.202-2), and (2) a fixed-price incentive contract would not be more appropriate; (b) The contractor's accountin…
  • FAR 16.205-4 Contract clause.
    …ontracting officer shall, when contracting by negotiation, insert the clause at 52.216-5, Price Redetermination—Prospective, in solicitations and contracts when a fixed-price contract is contemplated and the conditions specified in 16.205-2…