48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

5 sections with “SF 1034”

  • FAR 53.249 Termination of contracts.
    …t https://www.gsa.gov/forms. These forms are authorized for local reproduction except for SF 1034. (1) SF 1034 (GAO), Public Voucher for Purchases and Services Other Than Personal. (See 49.302(a).) (2) SF 1435 (Rev. 03/2016), Settlement P…
  • FAR 49.603-5 Cost-reimbursement contracts—partial termination.
    [Insert the following in Block 14 of SF 30, Amendment of Solicitation/Modification of Contract, for settlement agreements for cost-reimbursement contracts as a result of partial termination.] (a) This supplemental agreement settles the ter…
  • FAR 49.103 Methods of settlement.
    … negotiated agreement, (b) determination by the TCO, (c) costing-out under vouchers using SF 1034, Public Voucher for Purchases and Services Other Than Personal, for cost-reimbursement contracts (as prescribed in subpart 49.3), or (d) a com…
  • FAR 49.304-3 Submission of vouchers.
    …n settlement is limited to adjustment of fee, the contractor shall continue to submit the SF 1034, Public Voucher for Purchases and Services Other than Personal, for costs reimbursable under the contract. The contractor shall not be reimbur…
  • FAR 49.302 Discontinuance of vouchers.
    … out all costs within the 6-month period, a proposal for fee, if any, may be submitted on SF 1437 (see 49.602-1) or by letter appropriately certified. The contractor must submit a substantiated proposal for fee to the TCO within 1 year from…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.