4 sections with “Site Investigation and Conditions Affecting the Work”

  • FAR 52.236-3 Site Investigation and Conditions Affecting the Work.
    As prescribed in 36.503, insert the following clause: Site Investigation and Conditions Affecting the Work (APR 1984) (a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the…
  • FAR 36.503 Site investigation and conditions affecting the work.
    The contracting officer shall insert the clause at 52.236-3, Site Investigation and Conditions Affecting the Work, in solicitations and contracts when a fixed-price construction contract or a fixed-price dismantling, demolition, or removal …
  • FAR 52.236-27 Site Visit (Construction).
    As prescribed in 36.523, insert a provision substantially the same as the following: Site Visit (Construction) (FEB 1995) (a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigation and Conditions Affecting th…
  • FAR 36.523 Site visit.
    …ng officer shall insert a provision substantially the same as the provision at 52.236-27, Site Visit (Construction), in solicitations which include the clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Co…