12 sections with “advance acquisition planning”

  • FAR 5.404 Release of long-range acquisition estimates.
    …f unclassified long-range acquisition requirements. Estimates may be publicized as far in advance as possible.
  • FAR 2.101 Definitions.
    …product that evolved from a product described in paragraph (1) of this definition through advances in technology or performance and that is not yet available in the commercial marketplace, but will be available in the commercial marketplace…
  • FAR 25.802 Procedures.
    …al agreements and ensure compliance with these agreements; and (2) Conduct the necessary advance acquisition planning and coordination between the appropriate U.S. executive agencies and foreign interests as required by these agreements. …
  • DFARS 231.205-70 External restructuring costs.
    …reviews the audit report and the projected costs and projected savings, and negotiates an advance agreement in accordance with paragraph (d) of this subsection; and (4)(i) The official designated in paragraph (c)(4)(ii) of this subsection …
  • FAR 1.102-2 Performance standards.
    …ng as an integral part of the overall process of acquiring products or services. Although advance planning is required, each member of the Team must be flexible in order to accommodate changing or unforeseen mission needs. Planning is a too…
  • FAR 4.803 Contents of contract files.
    …e policies or certificates of insurance or references to them. (13) Documents supporting advance or progress payments. (14) Progressing, expediting, and production surveillance records. (15) Quality assurance records. (16) Property admi…
  • FAR 5.404-1 Release procedures.
    …ssible, in the same manner as the original; and (6) Each release— (i) Is coordinated in advance with small business, public information, and public relations personnel, as appropriate; (ii) Contains, if applicable, a statement that small…
  • FAR 6.301 Policy.
    …ding for full and open competition shall not be justified on the basis of— (1) A lack of advance planning by the requiring activity; or (2) Concerns related to the amount of funds available (e.g., funds will expire) to the agency or activ…
  • FAR 7.103 Agency-head responsibilities.
    … officers consult the Disaster Response Registry via https://www.sam.gov, Search Records, Advanced Search, Disaster Response Registry Search as a part of acquisition planning for debris removal, distribution of supplies, reconstruction, and…
  • FAR 7.104 General procedures.
    …sition planning should begin as soon as the agency need is identified, preferably well in advance of the fiscal year in which contract award or order placement is necessary. In developing the plan, the planner shall form a team consisting o…
  • FAR 52.245-1 Government Property.
    …ents. The Contractor shall notify the Plant Clearance Officer at least 10 working days in advance of its intent to remove an item from an approved inventory disposal schedule. Upon approval of the Plant Clearance Officer, or upon expiration…
  • DFARS 252.225-7040 Contractor Personnel Supporting U.S. Armed Forces Deployed Outside the United States.
    …b-based source, if specified in the contract or approved by the Contracting Officer. (B) Advanced training, commensurate with their duties and responsibilities, may be required for some Contractor personnel as specified in the contract. (…