48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

22 sections with “construction progress payments”

  • FAR 32.103 Progress payments under construction contracts.
    When satisfactory progress has not been achieved by a contractor during any period for which a progress payment is to be made, a percentage of the progress payment may be retained. Retainage should not be used as a substitute for good contr…
  • FAR 52.232-5 Payments Under Fixed-Price Construction Contracts.
    As prescribed in 32.111(a)(5), insert the following clause: Payments Under Fixed-Price Construction Contracts (MAY 2014) (a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract. (b) P…
  • FAR 52.232-27 Prompt Payment for Construction Contracts.
    As prescribed in 32.908(b), insert the following clause: Prompt Payment for Construction Contracts (JAN 2017) Notwithstanding any other payment terms in this contract, the Government will make invoice payments under the terms and conditio…
  • FAR 32.904 Determining payment due dates.
    …fication for extending the constructive acceptance or approval period beyond 7 days. (d) Construction contracts. (1) The due date for making payments on construction contracts is as follows: (i) The due date for making progress payments b…
  • FAR 52.236-15 Schedules for Construction Contracts.
    As prescribed in 36.515, insert the following clause: Schedules for Construction Contracts (APR 1984) (a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contract…
  • DFARS 232.904 Determining payment due dates.
    …tive acceptance period specified in the FAR Prompt Payment clauses. Government payment of construction progress payments can, in most cases, be made within the 14-day period allowed by the Prompt Payment for Construction Contracts clause. W…
  • FAR 49.206-2 Bases for settlement proposals.
    … appropriate for use under the following circumstances: (i) The partial termination of a construction or related professional services contract. (ii) The partial or complete termination of supply orders under any terminated construction c…
  • FAR 32.001 Definitions.
    …ee 32.102(e)), except those made under the clause at 52.232-5, Payments Under Fixed-Price Construction Contracts, or the clause at 52.232-10, Payments Under Fixed-Price Architect-Engineer Contracts; and (vi) Interim payments under a cost r…
  • FAR 32.112-1 Subcontractor assertions of nonpayment.
    …er agreement with the prime contractor, the contracting officer may determine— (1) For a construction contract, whether the contractor has made— (i) Progress payments to the subcontractor or supplier in compliance with Chapter 39 of Title…
  • FAR 52.236-16 Quantity Surveys.
    …officer may insert the following clause in solicitations and contracts when a fixed-price construction contract providing for unit pricing of items and for payment based on quantity surveys is contemplated: Quantity Surveys (APR 1984) (a)…
  • FAR 52.249-6 Termination (Cost-Reimbursement).
    … does not include a fee. (End of clause) Alternate I (SEP 1996). If the contract is for construction, substitute the following subparagraph (h)(4) for subparagraph (h)(4) of the basic clause: (h)(4) A portion of the fee payable under the…
  • DFARS 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.
    …2.102(e)), except those made under the clause at FAR 52.232-5, Payments Under Fixed-Price Construction Contracts, or the clause at FAR 52.232-10, Payments Under Fixed-Price Architect-Engineer Contracts; and (vi) Interim payments under a co…
  • FAR 32.113 Customary contract financing.
    …ide for progress payments based on a percentage or stage of completion. (b) Financing of construction or architect-engineer services purchased under the authority of part 36. (c) Financing of contracts for supplies or services awarded und…
  • FAR 32.500 Scope of subpart.
    …ts made to subcontractors under cost-reimbursement prime contracts; or (b) Contracts for construction or for shipbuilding or ship conversion, alteration, or repair, when the contracts provide for progress payments based on a percentage or …
  • FAR 32.905 Payment documentation and process.
    …st, if the request is being made under the clause at 52.232-5, Payments Under Fixed-Price Construction Contracts, or the clause at 52.232-10, Payments Under Fixed-Price Architect-Engineer Contracts. (6) Signature, printed name, title, mail…
  • FAR 32.1001 Policy.
    …ts under cost-reimbursement line items; (2) Contracts for architect-engineer services or construction, or for shipbuilding or ship conversion, alteration, or repair, when the contracts provide for progress payments based upon a percentage …
  • FAR 42.302 Contract administration functions.
    …ders and negotiate and execute resulting supplemental agreements under contracts for ship construction, conversion, and repair. (9) Execute supplemental agreements on firm-fixed price supply contracts to reduce required line item quantitie…
  • FAR 49.402-3 Procedure for default.
    …advice, which should be furnished at the earliest practicable time. (i) In the case of a construction contract, promptly after issuance of the termination notice, the contracting officer shall determine the manner in which the work is to b…
  • FAR 49.404 Surety-takeover agreements.
    (a) The procedures in this section apply primarily, but not solely, to fixed-price construction contracts terminated for default. (b) Since the surety is liable for damages resulting from the contractor's default, the surety has certain ri…
  • FAR 52.216-7 Allowable Cost and Payment.
    …r is required to pay pursuant to the clause of this contract entitled “Prompt Payment for Construction Contracts.” Payments shall be made by cash, check, or other form of payment to the Contractor's subcontractors under similar cost standar…
  • FAR 52.241-9 Connection Charge.
    …and other charges in connection therewith, together with all liability arising out of the construction, operations, maintenance, or repair of such facilities, shall be the obligation of the Contractor. (c) Credits. (1) The Contractor agree…
  • DFARS 232.102 Description of contract financing methods.
    …payments based on percentage or stage of completion are authorized only for contracts for construction (as defined in FAR 36.102), shipbuilding, and ship conversion, alteration, or repair. However, percentage or state of completion methods …

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.