  • FAR 52.209-3 First Article Approval—Contractor Testing.
    As prescribed in 9.308-1 (a) and (b), insert the following clause: First Article Approval—Contractor Testing (SEP 1989) [Contracting Officer shall insert details] (a) The Contractor shall test __ unit(s) of Lot/Item __ as specified in th…
  • FAR 52.209-4 First Article Approval—Government Testing.
    As prescribed in 9.308-2 (a) and (b), insert the following clause: First Article Approval—Government Testing (SEP 1989) [Contracting Officer shall insert details] (a) The Contractor shall deliver __ units(s) of Lot/Item __ within __ cale…
  • FAR 9.305 Risk.
    Before first article approval, the acquisition of materials or components, or commencement of production, is normally at the sole risk of the contractor. To minimize this risk, the contracting officer shall provide sufficient time in the de…
  • FAR 9.306 Solicitation requirements.
    …hall— (a) Provide, in the circumstance where the contractor is to be responsible for the first article approval testing— (1) The performance or other characteristics that the first article must meet for approval; (2) The detailed technic…
  • FAR 9.307 Government administration procedures.
    (a) Before the contractor ships the first article, or the first article test report, to the Government laboratory or other activity responsible for approval at the address specified in the contract, the contract administration office shall …
  • FAR 9.308-1 Testing performed by the contractor.
    (a)(1) The contracting officer shall insert the clause at 52.209-3, First Article Approval—Contractor Testing, in solicitations and contracts when a fixed-price contract is contemplated and it is intended that the contract require— (i) Fir…
  • FAR 9.308-2 Testing performed by the Government.
    (a)(1) The contracting officer shall insert the clause at 52.209-4, First Article Approval—Government Testing, in solicitations and contracts when a fixed-price contract is contemplated and it is intended that the contract require first art…
  • FAR 27.404-3 Copyrighted works.
    (a) Data first produced in the performance of a contract. (1) Generally, the contractor must obtain permission of the contracting officer prior to asserting rights in any copyrighted work containing data first produced in the performance of…
  • FAR 52.227-14 Rights in Data—General.
    …in paragraph (c) of this clause, the Government shall have unlimited rights in— (i) Data first produced in the performance of this contract; (ii) Form, fit, and function data delivered under this contract; (iii) Data delivered under this…
  • FAR 52.105 Procedures for using alternates.
    … date shall be cited along with the date of the basic provision or clause; e.g., 52.209-3 FIRST ARTICLE APPROVAL—CONTRACTOR TESTING (OCT 1983)—ALTERNATE I (DEC 1983). (c) Under certain circumstances, a provision or clause may be used with …
  • FAR 52.219-9 Small Business Subcontracting Plan.
    …Offeror's official responsible for acknowledging receipt of or rejecting the ISRs, to all first-tier subcontractors with subcontracting plans so they can enter this information into the eSRS when submitting their ISRs; and (vii) Require th…
  • FAR 46.201 General.
    …sts, and simulated service tests); and (2) Contracts that require Government testing for first article approval (see subpart 9.3). (d) Except as otherwise specified by the contract, required contractor testing may be performed in the cont…
  • DFARS 252.227-7013 Rights in Technical Data—Other Than Commercial Products and Commercial Services.
    …fort, provided that the contractor— (1) Is not affiliated with the prime contractor or a first-tier subcontractor on the program or effort, or with any direct competitor of such prime contractor or any such first-tier subcontractor in furn…
  • FAR 4.1003 Establishing line items.
    …ment of work or performance work statement. (3) If the procurement instrument involves a first article (see subpart 9.3), establish a separate line item for each item requiring a separate approval. If the first article consists of a lot co…
  • FAR 19.704 Subcontracting plan requirements.
    … offeror's official responsible for acknowledging receipt of or rejecting the ISRs to all first-tier subcontractors with subcontracting plans so they can enter this information into the eSRS when submitting their ISRs; and (vii) Require th…
  • FAR 52.232-16 Progress Payments.
    …cted to involve a minimum of approximately 6 months between the beginning of work and the first delivery; or, if the subcontractor is a small business concern, 4 months. (3) If the financing payments are in the form of progress payments, t…
  • FAR 9.000 Scope of part.
    …ontractors' responsibility; debarment, suspension, and ineligibility; qualified products; first article testing and approval; contractor team arrangements; defense production pools and research and development pools; and organizational conf…
  • FAR 9.301 Definition.
    …acting officer's written notification to the contractor accepting the test results of the first article.
  • FAR 9.302 General.
    First article testing and approval (hereafter referred to as testing and approval) ensures that the contractor can furnish a product that conforms to all contract requirements for acceptance. Before requiring testing and approval, the contr…
  • FAR 9.303 Use.
    … is described by a performance specification; or (d) It is essential to have an approved first article to serve as a manufacturing standard.
  • FAR 52.245-1 Government Property.
    …ce; or (C) Reimbursement of the cost of the property by the Government, whichever occurs first. (f) Contractor plans and systems. (1) Contractors shall establish and implement property management plans, systems, and procedures at the cont…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.