48 CFR · Federal Acquisition Regulation and Defense supplement
FAR and DFARS navigator
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
Ask the FAR
Try: · · ·
36 sections with “fixed-price contracts with economic price adjustment”
- FAR 16.203 Fixed-price contracts with economic price adjustment.
- DFARS 216.203 Fixed-price contracts with economic price adjustment.
- FAR 36.207 Pricing fixed-price construction contracts.(a) Generally, firm-fixed-price contracts shall be used to acquire construction. They may be priced (1) on a lump-sum basis (when a lump sum is paid for the total work or defined parts of the work), (2) on a unit-price basis (when a unit pr…
- FAR 12.207 Contract type.(a) Except as provided in paragraph (b) of this section, agencies shall use firm-fixed-price contracts or fixed-price contracts with economic price adjustment for the acquisition of commercial products or commercial services. (b)(1) A time…
- FAR 14.104 Types of contracts.Firm-fixed-price contracts shall be used when the method of contracting is sealed bidding, except that fixed-price contracts with economic price adjustment clauses may be used if authorized in accordance with 16.203 when some flexibility is…
- DFARS 215.404-71-3 Contract type risk and working capital adjustment.…is an adjustment added to the profit objective for contract type risk. It only applies to fixed-price contracts that provide for progress payments. Though it uses a formula approach, it is not intended to be an exact calculation of the cost…
- FAR 16.102 Policies.(a) Contracts resulting from sealed bidding shall be firm-fixed-price contracts or fixed-price contracts with economic price adjustment. (b) Contracts negotiated under part 15 may be of any type or combination of types that will promote th…
- FAR 52.226-1 Utilization of Indian Organizations and Indian-Owned Economic Enterprises.…f a cost-plus-incentive-fee prime contract. (iii) The target cost and ceiling price of a fixed-price incentive prime contract. (iv) The price of a firm-fixed-price prime contract. (3) The amount of the adjustment to the prime contract is…
- FAR 7.105 Contents of written acquisition plans.… selection. Discuss the rationale for the selection of contract type. For other than firm-fixed-price contracts, see 16.103(d) for additional documentation guidance. Acquisition personnel shall document the acquisition plan with findings th…
- FAR 15.407-1 Defective certified cost or pricing data.…based are not themselves defective. (2) Under cost-reimbursement contracts and under all fixed-price contracts except firm-fixed-price contracts and fixed-price contracts with economic price adjustment, payments to subcontractors that are …
- FAR 15.408 Solicitation provisions and contract clauses.…cant value, the contracting officer shall use the clause with— (1) Its Alternate I, if a fixed-price incentive contract is contemplated; or (2) Its Alternate II, if a cost-plus-incentive-fee contract is contemplated. (b) Price Reduction …
- FAR 16.104 Factors in selecting contract types.…ce competition. Normally, effective price competition results in realistic pricing, and a fixed-price contract is ordinarily in the Government's interest. (b) Price analysis. Price analysis with or without competition, may provide a basis …
- FAR 16.201 General.(a) Fixed-price types of contracts provide for a firm price or, in appropriate cases, an adjustable price. Fixed-price contracts providing for an adjustable price may include a ceiling price, a target price (including target cost), or both.…
- FAR 31.204 Application of principles and procedures.…d by the subcontractor that are consistent with this part: (i) Cost-reimbursement. (ii) Fixed-price incentive. (iii) Price redeterminable (i.e., fixed-price contracts with prospective price redetermination and fixed-ceiling-price contrac…
- FAR 15.305 Proposal evaluation.…ally, competition establishes price reasonableness. Therefore, when contracting on a firm-fixed-price or fixed-price with economic price adjustment basis, comparison of the proposed prices will usually satisfy the requirement to perform a p…
- FAR 22.404-12 Labor standards for contracts containing construction requirements and option provisions that extend the term of the contract.… those task orders without further revision. (c) The contracting officer must include in fixed-price contracts a clause that specifies one of the following methods, suitable to the interest of the Government, to provide an allowance for an…
- FAR 12.214 Cost Accounting Standards.…commercial products or commercial services when these contracts and subcontracts are firm-fixed-price or fixed-price with economic price adjustment (provided that the price adjustment is not based on actual costs incurred). See 30.201-1 for…
- FAR 17.106-3 Special procedures applicable to DoD, NASA, and the Coast Guard.…anceled or terminated. (d) Contracts awarded under the multiyear procedure shall be firm-fixed-price, fixed-price with economic price adjustment, or fixed-price incentive. (e) Recurring costs in cancellation ceiling. The inclusion of recu…
- DFARS 216.203-4-70 Additional provisions and clauses.… Adjustment—Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products, may be used in fixed-price supply solicitations and contracts for basic steel, aluminum, brass, bronze, or copper mill products, such as sheets, plates, and bars, wh…
- FAR 12.403 Termination.…eflecting the percentage of the work performed prior to the notice of the termination for fixed-price or fixed-price with economic price adjustment contracts; or (B) An amount for direct labor hours (as defined in the Schedule of the contr…
- FAR 14.201-1 Uniform contract format.…here in this regulation that are inconsistent with the uniform contract format. (5) Firm-fixed-price or fixed-price with economic price adjustment acquisitions that use the simplified contract format (see 14.201-9). (b) Information suitab…
- FAR 16.203-4 Contract clauses.… below, in solicitations and contracts when all of the following conditions apply: (i) A fixed-price contract is contemplated. (ii) The requirement is for standard supplies that have an established catalog or market price. (iii) The cont…
- FAR 17.208 Solicitation provisions and contract clauses.… clause; (2) An option is not to be exercised at the time of contract award; (3) A firm-fixed-price contract, a fixed-price contract with economic price adjustment, or other type of contract approved under agency procedures is contemplate…
- FAR 31.205-18 Independent research and development and bid and proposal costs.…sales of that product. (2) When deferred costs are recognized, the contract (except firm-fixed-price and fixed-price with economic price adjustment) will include a specific provision setting forth the amount of deferred IR&D costs that are…
- FAR 42.1503 Procedures.…i) Technical (quality of product or service). (ii) Cost control (not applicable for firm-fixed-price or fixed-price with economic price adjustment arrangements). (iii) Schedule/timeliness. (iv) Management or business relations. (v) Smal…
- FAR 44.302 Requirements.…ontracts. If a contractor's sales to the Government (excluding competitively awarded firm-fixed-price and competitively awarded fixed-price with economic price adjustment contracts and sales of commercial products and commercial services pu…
- FAR 44.303 Extent of review.…ractor exclusively in support of Government contracts that are competitively awarded firm-fixed-price, competitively awarded fixed-price with economic price adjustment, or awarded for commercial products and commercial services pursuant to …
- FAR 52.204-8 Annual Representations and Certifications.…e of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless— (A) The acquisition is to be made under the simp…
- DFARS 242.7203 Review procedures.….C. 3702, as implemented in FAR 15.403, or that are contracts priced on other than a firm-fixed-price or fixed-price with economic price adjustment basis. Sales include prime contracts, subcontracts, and modifications to such contracts and …
- DFARS 242.7302 Requirements.….C. 3702, as implemented in FAR 15.403, or that are contracts priced on other than a firm-fixed-price or fixed-price with economic price adjustment basis. Sales include prime contracts, subcontracts, and modifications to such contracts and …
- FAR 16.203-2 Application.A fixed-price contract with economic price adjustment may be used when (i) there is serious doubt concerning the stability of market or labor conditions that will exist during an extended period of contract performance, and (ii) contingenci…
- FAR 17.106-1 General.…longer performance period associated with multiyear acquisition, consideration in pricing fixed-priced contracts should be given to the use of economic price adjustment terms and profit objectives commensurate with contractor risk and finan…
- FAR 17.207 Exercise of options.…rovided in the basic contract, but not including renegotiation of the price for work in a fixed-price type contract; (3) In the case of a cost-type contract, if— (i) The option contains a fixed or maximum fee; or (ii) The fixed or maximu…
- FAR 42.302 Contract administration functions.…lemental agreements to permit a chance in place of inspection at origin specified in firm fixed-price supply contracts awarded to nonmanufacturers, as deemed necessary to protect the Government's interests. (11) Prepare evaluations of cont…
- FAR 52.245-1 Government Property.…r Cost-Reimbursement or Time-and-Material Contracts or Cost-Reimbursable line items under Fixed-Price contracts. (i) Title to all property purchased by the Contractor for which the Contractor is entitled to be reimbursed as a direct item of…
- DFARS 252.204-7007 Alternate A, Annual Representations and Certifications.…Rates or Material Prices Controlled by a Foreign Government. Applies to solicitations for fixed-price supply and service contracts when the contract is to be performed wholly or in part in a foreign country, and a foreign government control…
FAR (chapter 1)
- Part 1 Federal Acquisition Regulations System 58 sections
- Part 2 Definitions of Words and Terms 3 sections
- Part 3 Improper Business Practices and Personal Conflicts of Interest 98 sections
- Part 4 Administrative and Information Matters 116 sections
- Part 5 Publicizing Contract Actions 34 sections
- Part 6 Competition Requirements 34 sections
- Part 7 Acquisition Planning 34 sections
- Part 8 Required Sources of Supplies and Services 67 sections
- Part 9 Contractor Qualifications 106 sections
- Part 10 Market Research 4 sections
- Part 11 Describing Agency Needs 33 sections
- Part 12 Acquisition of Commercial Products and Commercial Services 38 sections
- Part 13 Simplified Acquisition Procedures 49 sections
- Part 14 Sealed Bidding 82 sections
- Part 15 Contracting by Negotiation 81 sections
- Part 16 Types of Contracts 74 sections
- Part 17 Special Contracting Methods 50 sections
- Part 18 Emergency Acquisitions 34 sections
- Part 19 Small Business Programs 126 sections
- Part 22 Application of Labor Laws to Government Acquisitions 205 sections
- Part 23 Environment, Sustainable Acquisition, and Material Safety 38 sections
- Part 24 Protection of Privacy and Freedom of Information 10 sections
- Part 25 Foreign Acquisition 81 sections
- Part 26 Other Socioeconomic Programs 36 sections
- Part 27 Patents, Data, and Copyrights 59 sections
- Part 28 Bonds and Insurance 61 sections
- Part 29 Taxes 23 sections
- Part 30 Cost Accounting Standards Administration 30 sections
- Part 31 Contract Cost Principles and Procedures 87 sections
- Part 32 Contract Financing 175 sections
- Part 33 Protests, Disputes, and Appeals 23 sections
- Part 34 Major System Acquisition 20 sections
- Part 35 Research and Development Contracting 25 sections
- Part 36 Construction and Architect-engineer Contracts 81 sections
- Part 37 Service Contracting 46 sections
- Part 38 Federal Supply Schedule Contracting 3 sections
- Part 39 Acquisition of Information Technology 14 sections
- Part 40 Information Security and Supply Chain Security 12 sections
- Part 41 Acquisition of Utility Services 17 sections
- Part 42 Contract Administration and Audit Services 84 sections
- Part 43 Contract Modifications 14 sections
- Part 44 Subcontracting Policies and Procedures 24 sections
- Part 45 Government Property 33 sections
- Part 46 Quality Assurance 60 sections
- Part 47 Transportation 106 sections
- Part 48 Value Engineering 13 sections
- Part 49 Termination of Contracts 108 sections
- Part 50 Extraordinary Contractual Actions and the Safety Act 34 sections
- Part 51 Use of Government Sources by Contractors 15 sections
- Part 52 Solicitation Provisions and Contract Clauses 680 sections
- Part 53 Forms 61 sections
DFARS (chapter 2, Defense)
- Part 201 Federal Acquisition Regulations System 24 sections
- Part 202 Definitions of Words and Terms 1 sections
- Part 203 Improper Business Practices and Personal Conflicts of Interest 28 sections
- Part 204 Administrative and Information Matters 76 sections
- Part 205 Publicizing Contract Actions 11 sections
- Part 206 Competition Requirements 20 sections
- Part 207 Acquisition Planning 22 sections
- Part 208 Required Sources of Supplies and Services 31 sections
- Part 209 Contractor Qualifications 55 sections
- Part 210 Market Research 2 sections
- Part 211 Describing Agency Needs 22 sections
- Part 212 Acquisition of Commercial Products and Commercial Services 24 sections
- Part 213 Simplified Acquisition Procedures 23 sections
- Part 214 Sealed Bidding 14 sections
- Part 215 Contracting by Negotiation 66 sections
- Part 216 Types of Contracts 36 sections
- Part 217 Special Contracting Methods 64 sections
- Part 218 Emergency Acquisitions 7 sections
- Part 219 Small Business Programs 47 sections
- Part 222 Application of Labor Laws to Government Acquisitions 56 sections
- Part 223 Environment, Sustainable Acquisition, and Material Safety 34 sections
- Part 224 Protection of Privacy and Freedom of Information 2 sections
- Part 225 Foreign Acquisition 251 sections
- Part 226 Other Socioeconomic Programs 14 sections
- Part 227 Patents, Data, and Copyrights 99 sections
- Part 228 Bonds and Insurance 17 sections
- Part 229 Taxes 9 sections
- Part 230 Cost Accounting Standards Administration 2 sections
- Part 231 Contract Cost Principles and Procedures 13 sections
- Part 232 Contract Financing 74 sections
- Part 233 Protests, Disputes, and Appeals 8 sections
- Part 234 Major System Acquisition 13 sections
- Part 235 Research and Development Contracting 16 sections
- Part 236 Construction and Architect-engineer Contracts 25 sections
- Part 237 Service Contracting 67 sections
- Part 239 Acquisition of Information Technology 38 sections
- Part 241 Acquisition of Utility Services 8 sections
- Part 242 Contract Administration and Audit Services 40 sections
- Part 243 Contract Modifications 18 sections
- Part 244 Subcontracting Policies and Procedures 13 sections
- Part 245 Government Property 23 sections
- Part 246 Quality Assurance 39 sections
- Part 247 Transportation 27 sections
- Part 249 Termination of Contracts 14 sections
- Part 250 Extraordinary Contractual Actions and the Safety Act 16 sections
- Part 251 Use of Government Sources by Contractors 5 sections
- Part 252 Solicitation Provisions and Contract Clauses 405 sections
- Part 253 Forms 10 sections
- Part 270 Defense Contracting Programs 7 sections
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.