4 sections with “initial target prices”

  • FAR 52.216-17 Incentive Price Revision—Successive Targets.
    …ling price of ___ dollars ($___). The prices of these items shown in the Schedule are the initial target prices, which include an initial target profit of ___ [Contracting Officer insert percent] percent of the initial target cost. Any supp…
  • FAR 52.246-2 Inspection of Supplies—Fixed-Price.
    … contract or otherwise, remove, replace, or correct the supplies and equitably reduce the initial contract prices or, if established, the redetermined contract prices or (2) terminate the contract for default. Unless the Contractor corrects…
  • FAR 52.216-16 Incentive Price Revision—Firm Target.
    …been established; (iii) The portion of the total target profit (used in establishing the initial contract price or agreed to for the purpose of this paragraph (g)) that is in direct proportion to the supplies delivered (or services perform…
  • FAR 32.503-9 Liquidation rates—alternate method.
    …eration for these contract modifications is provided by the consideration included in the initial contract. The parties shall promptly make the payment or liquidation required in the circumstances.

FAR (chapter 1)