  • FAR 34.202 Integrated Baseline Reviews.
    (a) When an EVMS is required, the Government will conduct an Integrated Baseline Review (IBR). (b) The purpose of the IBR is to verify the technical content and the realism of the related performance budgets, resources, and schedules. It s…
  • FAR 52.234-2 Notice of Earned Value Management System—Preaward Integrated Baseline Review.
    …34.203(a) use the following provision: Notice of Earned Value Management System—Preaward Integrated Baseline Review (NOV 2016) (a) The offeror shall provide documentation that the Cognizant Federal Agency has determined that the proposed …
  • FAR 52.234-3 Notice of Earned Value Management System—Postaward Integrated Baseline Review.
    …4.203(b) use the following provision: Notice of Earned Value Management System—Postaward Integrated Baseline Review (NOV 2016) (a) The offeror shall provide documentation that the Cognizant Federal Agency has determined that the proposed …
  • FAR 34.203 Solicitation provisions and contract clause.
    … same as the provision at FAR 52.234-2, Notice of Earned Value Management System—Preaward Integrated Baseline Review , in solicitations for contracts that require the contractor to use an Earned Value Management System (EVMS) and for which …
  • DFARS 252.234-7002 Earned Value Management System.
    …y, reliable, and verifiable information for the Contract Performance Report (CPR) and the Integrated Master Schedule (IMS) required by the CPR and IMS data items of this contract. (c) If this contract has a value of $50 million or more, th…
  • FAR 7.105 Contents of written acquisition plans.
    … the Electronic Industries Alliance Standard 748 (EIA-748), and the timing and conduct of integrated baseline reviews (whether prior to or post award). (See 34.202.) (12) Make or buy. Discuss any consideration given to make-or-buy programs…
  • FAR 52.234-4 Earned Value Management System.
    …ctor's EVMS plan approved by the Contracting Officer. (c) The Government will conduct an Integrated Baseline Review (IBR). If a pre-award IBR has not been conducted, a post award IBR shall be conducted as early as practicable after contrac…