48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

10 sections with “low quoter”

  • FAR 13.003 Policy.
    … services not exceeding the simplified acquisition threshold (including purchases at or below the micro-purchase threshold). This policy does not apply if an agency can meet its requirement using— (1) Required sources of supply under part …
  • FAR 13.106-1 Soliciting competition.
    …ing competition, the contracting officer shall consider the guidance in 13.104 and the following before requesting quotations or offers: (1)(i) The nature of the article or service to be purchased and whether it is highly competitive and r…
  • FAR 13.203 Purchase guidelines.
    …umentation. If competitive quotations were solicited and award was made to other than the low quoter, documentation to support the purchase may be limited to identification of the solicited concerns and an explanation for the award decision…
  • DFARS 204.7603 Procedures.
    …ering the information available in SPRS on item risk, price risk, and supplier risk as follows: (a) Item risk. (1) Consider item risk to determine whether the procurement of products represents a high performance risk to the Government. If…
  • DFARS 252.204-7024 Notice on the Use of the Supplier Performance Risk System.
    As prescribed in 204.7604, use the following provision: Notice on the Use of the Supplier Performance Risk System (MAR 2023) (a) Definitions. As used in this provision— Item risk means the probability that a product, based on intended us…
  • FAR 52.203-2 Certificate of Independent Price Determination.
    As prescribed in 3.103-1, insert the following provision. If the solicitation is a Request for Quotations, the terms Quotation and Quoter may be substituted for Offer and Offeror. Certificate of Independent Price Determination (APR 1985) …
  • FAR 52.236-27 Site Visit (Construction).
    As prescribed in 36.523, insert a provision substantially the same as the following: Site Visit (Construction) (FEB 1995) (a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigation and Conditions Affecting th…
  • FAR 4.803 Contents of contract files.
    The following are examples of the records normally contained, if applicable, in contract files: (a) Contracting office contract file. (1) Purchase request, acquisition planning information, and other presolicitation documents. (2) Justifi…
  • FAR 4.1102 Policy.
    …etition due to unusual or compelling urgency (see 6.302-2); (6) Contract actions at or below $40,000 awarded to foreign vendors for work performed outside the United States, if it is impractical to obtain SAM registration; and (7) Micro-p…
  • FAR 52.237-1 Site Visit.
    As prescribed in 37.110(a), insert the following provision in solicitations for services to be performed on Government installations, unless the solicitation is for construction: Site Visit (APR 1984) Offerors or quoters are urged and exp…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.