10 sections with “original signature”

  • FAR 4.703 Policy.
    …fter final payment, whichever period expires first. (3) The contractor does not meet the original due date for submission of final indirect cost rate proposals specified in paragraph (d)(2) of the clause at 52.216-7, Allowable Cost and Pay…
  • FAR 4.805 Storage, handling, and contract files.
    …types of media, including microfilm and various electronic media. Agencies may change the original medium to facilitate storage as long as the requirements of this part, law, and other regulations are satisfied. The process used to create a…
  • FAR 28.101-3 Authority of an attorney-in-fact for a bid bond.
    …in-fact shall include with the bid bond evidence of authority to bind the surety. (b) An original, or a photocopy or facsimile of an original, power of attorney is sufficient evidence of such authority. (c) For purposes of this section, e…
  • FAR 2.101 Definitions.
    …ernment that recognizes the legal change of name of the contractor without disturbing the original contractual rights and obligations of the parties. Change order means a written order, signed by the contracting officer, directing the cont…
  • FAR 32.805 Procedure.
    …er oaths. (b) Filing. The assignee shall forward to each party specified in 32.802(e) an original and three copies of the notice of assignment, together with one true copy of the instrument of assignment. The true copy shall be a certified…
  • DFARS 204.802 Contract files.
    …ronic, mechanically-applied and printed signature, seal, and date are considered to be an original signature, seal, and date.
  • FAR 4.804-5 Procedures for closing out contract files.
    …hen the statement is completed, the contracting officer must ensure that— (1) The signed original is placed in the contracting office contract file (or forwarded to the contracting office for placement in the files if the contract administ…
  • FAR 15.408 Solicitation provisions and contract clauses.
    … of what the cost would have been to complete the deleted work not yet performed (not the original proposal estimates), and the cost of deleted work already performed. (3) Include the incurred cost of deleted work already performed, using …
  • FAR 52.214-31 Facsimile Bids.
    …tracting Officer, the apparently successful bidder agrees to promptly submit the complete original signed bid. (f) Facsimile receiving data and compatibility characteristics are as follows: (1) Telephone number of receiving facsimile equi…
  • FAR 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items.
    …ot include those materials and by-products generated from, and commonly reused within, an original manufacturing process. (b) The Contractor, on completion of this contract, shall— (1) Estimate the percentage of the total recovered materi…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.