48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

9 sections with “repurchase”

  • FAR 49.402-6 Repurchase against contractor's account.
    … supplies or services are still required after termination, the contracting officer shall repurchase the same or similar supplies or services against the contractor's account as soon as practicable. The contracting officer shall repurchase …
  • FAR 8.406-4 Termination for cause.
    …with FAR 12.403, and may include charging the contractor with excess costs resulting from repurchase. (2) The schedule contracting office shall be notified of all instances where an ordering activity contracting officer has terminated for …
  • FAR 7.105 Contents of written acquisition plans.
    …d use of warranties (see part 46); (iii) The requirements for contractor data (including repurchase data) and data rights, their estimated cost, and the use to be made of the data (see part 27); and (iv) Standardization concepts, includin…
  • FAR 11.501 Policy.
    … seek expeditiously to obtain performance by the contractor or terminate the contract and repurchase (see subpart 49.4). Prompt contracting officer action will prevent excessive loss to defaulting contractors and protect the interests of th…
  • FAR 49.402-2 Effect of termination for default.
    …to those terminated for default (see 49.402-6), and for any other damages, whether or not repurchase is effected (see 49.402-7).
  • FAR 49.402-7 Other damages.
    …ract. Under the contract clause at 52.211-11, these damages are in addition to any excess repurchase costs. (b) If the Government has suffered any other ascertainable damages, including administrative costs, as a result of the contractor's…
  • FAR 49.403 Termination of cost-reimbursement contracts for default.
    …ever, a cost-reimbursement contract does not contain any provision for recovery of excess repurchase costs after termination for default (but see paragraph (g) of the clause at 52.246-3 with respect to failure of the contractor to replace o…
  • FAR 52.211-11 Liquidated Damages—Supplies, Services, or Research and Development.
    …similar supplies or services. These liquidated damages are in addition to excess costs of repurchase under the Termination clause. (c) The Contractor will not be charged with liquidated damages when the delay in delivery or performance is …
  • FAR 52.211-12 Liquidated Damages—Construction.
    … until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause. (End of clause)

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.