48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

25 sections with “stakes”

  • FAR 14.407-3 Other mistakes disclosed before award.
    …inistrative determinations may be made as described in this 14.407-3 in connection with mistakes in bids alleged after opening of bids and before award. The authority to permit correction of bids is limited to bids that, as submitted, are r…
  • FAR 15.508 Discovery of mistakes.
    Mistakes in a contractor's proposal that are disclosed after award shall be processed substantially in accordance with the procedures for mistakes in bids at 14.407-4.
  • FAR 14.407-2 Apparent clerical mistakes.
    …t shall obtain from the bidder a verification of the bid intended. Examples of apparent mistakes are— (1) Obvious misplacement of a decimal point; (2) Obviously incorrect discounts (for example, 1 percent 10 days, 2 percent 20 days, 5 per…
  • FAR 14.407-4 Mistakes after award.
    …tion shall be coordinated with legal counsel in accordance with agency procedures. (e) Mistakes alleged or disclosed after award shall be processed as follows: (1) The contracting officer shall request the contractor to support the allege…
  • FAR 14.407 Mistakes in bids.
  • DFARS 214.407 Mistakes in bids.
  • DFARS 214.407-3 Other mistakes disclosed before award.
    (e) Authority for making a determination under FAR 14.407-3(a), (b) and (d) is delegated for the defense agencies, without power of redelegation, as follows: (i) Defense Advanced Research Projects Agency: General Counsel, DARPA. (ii) Defe…
  • FAR 50.103-2 Types of contract adjustment.
    … loss to the contractor, fairness may make some adjustment appropriate. (b) Correcting mistakes. (1) A contract may be amended or modified to correct or mitigate the effect of a mistake. The following are examples of mistakes that may make…
  • FAR 14.407-1 General.
    After the opening of bids, contracting officers shall examine all bids for mistakes. In cases of apparent mistakes and in cases where the contracting officer has reason to believe that a mistake may have been made, the contracting officer s…
  • FAR 52.236-17 Layout of Work.
    …ents in connection with the layout. The Contractor shall furnish, at its own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for…
  • FAR 8.406-2 Inspection and acceptance.
    …tract, acceptance is conclusive, except as regards latent defects, fraud, or such gross mistakes as amount to fraud. (b) Services. The ordering activity has the right to inspect all services in accordance with the contract requirements and…
  • FAR 14.400 Scope of subpart.
    …ntains procedures for the receipt, handling, opening, and disposition of bids including mistakes in bids, and subsequent award of contracts.
  • FAR 15.306 Exchanges with offerors after receipt of proposals.
    …osal or other concerns (e.g., perceived deficiencies, weaknesses, errors, omissions, or mistakes (see 14.407)); and (ii) Information relating to relevant past performance; and (4) Shall address adverse past performance information to whic…
  • FAR 18.127 Extraordinary contractual actions.
    …ending contracts without consideration (see 50.103-2(a)); (b) Correcting or mitigating mistakes in a contract (see 50.103-2(b)); and (c) Formalizing informal commitments (See 50.103-2(c)).
  • FAR 37.111 Extension of services.
    …ing offices. Examples of circumstances causing such delays are bid protests and alleged mistakes in bid. In order to avoid negotiation of short extensions to existing contracts, the contracting officer may include an option clause (see 17.2…
  • FAR 43.301 Use of forms.
    …of the contractor; (iv) Administrative changes such as the correction of typographical mistakes, changes in the paying office, and changes in accounting and appropriation data; (v) Supplemental agreements (see 43.103); and (vi) Removal, …
  • FAR 46.705 Limitations.
    … an inspection clause (see subpart 46.3) in relation to latent defects, fraud, or gross mistakes that amount to fraud. (c) Except for warranty clauses in construction contracts, warranty clauses shall provide that the warranty applies notw…
  • FAR 49.102 Notice of termination.
    … The contracting officer may amend a termination notice to— (1) Correct nonsubstantive mistakes in the notice; (2) Add supplemental data or instructions; or (3) Rescind the notice if it is determined that items terminated had been comple…
  • FAR 50.102-3 Limitations on exercise of authority.
    …t Accountability Office; or (iv) Involve disposal of Government surplus property. (2) Mistakes shall not be corrected by an action obligating the Government for over $1,000, unless the contracting officer receives notice of the mistake be…
  • FAR 50.103-4 Facts and evidence.
    …ifically from the Government action, with detailed supporting analysis. (d) Correcting mistakes. When a request involves possible correction of a mistake (50.103-2(b)), the contractor may be asked to furnish, in addition to the facts and e…
  • FAR 52.246-2 Inspection of Supplies—Fixed-Price.
    …ore acceptance. Acceptance shall be conclusive, except for latent defects, fraud, gross mistakes amounting to fraud, or as otherwise provided in the contract. (l) If acceptance is not conclusive for any of the reasons in paragraph (k) here…
  • FAR 52.246-7 Inspection of Research and Development—Fixed-Price.
    …ore acceptance. Acceptance shall be conclusive, except for latent defects, fraud, gross mistakes amounting to fraud, or as otherwise specified in the contract. If acceptance is not conclusive for any of these causes, the Government, in addi…
  • FAR 52.246-12 Inspection of Construction.
    …ately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee. (End of clause)
  • FAR 52.246-21 Warranty of Construction.
    …Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud. (End of clause) Alternate I (APR 1984). If the Government specifies in the contract the use of any equipment by brand name and mod…
  • DFARS 252.246-7002 Warranty of construction (Germany).
    …ght under the Inspection clause of this contract, with respect to latent defects, gross mistakes, or fraud. (End of clause)

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.